Wall tie spacing by scaffold system

How far apart the wall ties go on each scaffold system ScaFix plans: the largest vertical distance between tie rows, which standards in a row are tied, and how high the first row may sit, for an open (unclad) facade.

Each rule names the document and the page it comes from; a rule not yet checked against its document is marked ≈ (estimate).

· How the numbers are computed ·

HAKI Universal scaffolding (2.5 m bays, 1.01 m deep) around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
HAKI Universal (2.5 m bays, 1.01 m deep) around the example house, as ScaFix draws it in 3D.

How far apart should scaffold wall ties be?

In ScaFix's catalogue, 99 of 115 scaffold systems put their tie rows at most 4 m apart vertically; along the face, 24 tie every standard and 71 every second standard. The system's own document decides: 91 of the 115 tie rules here are checked against the document they cite; 24 are estimates (≈). Sheeting, brackets and height tighten the spacing.

Vertical tie spacing across the catalogue

The largest vertical distance between two tie rows on an open facade, and how many systems' rules use it. Estimates are rules not yet checked against their document.

Vertical spacingSystemsChecked against a documentEstimates (≈)
4 m998118
2 m550
5 m303
3.6 m202
6 m220
6.1 m220
1.73 m101
9 m110

Tie rules checked against their document

91 systems. The document is the first one the rule cites, in its own language, with the pages and sections the catalogue gives; «Derived» marks a figure the engine reads from the document where it leaves a choice. Scaffold system specifications has the full source of every rule in its CSV.

SystemVerticalAlong the faceFirst tieDocumentPages and sectionsType of source
Acrow QUICKSTAGE (AU)4 mEvery 3rd standard, staggered rows≤ 4 mWaco Kwikform «Kwikstage» guide PPM51 (08/2013) s. 5 (AS/NZS 1576.3 / 4576): up to 20 m ties at each end standard and at least every 3rd standard, vertically ≤ 4.0 m, staggereds. 5Third-party document (derived)
Acrow SUPERCUPLOK (AU)4 mEvery standard≤ 4 m and ≤ 3 × depthAcrow «SUPERCUPLOK Technical Guide» (CUPLOK_OCT2026 issue J) s. 70–72 (PDF s. 71: ties commence where the height exceeds 3 × the least widths. 70–72, s. 71, s. 72, s. 73, s. 71–72Manufacturer's document (derived)
AFIXFAST (Rosette spigot)4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.22-1012 «AFIXFAST X52» (Afix Group NV, 04.12.2025) Anlage C §C.1 (PDF S. 63: 24 m), §C.5 (PDF S. 64: Schutzwand oberste Lage an jedem Ständer), Anlage D S.1 (PDF S. 67)Anlage C, §C.1, S. 63, §C.5, S. 64, Anlage D, S.1, S. 67Manufacturer's document (derived)
ALBERT BLITZFIX 704 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-885 ALBERT BLITZFIX 70 (12.07.2021, geänd. 23.08.2023, verl. 06.07.2026 bis 14.07.2031) Anlage B S. 5 §B.5 a–c (PDF S. 124: V-Halter nicht am Rand), Anlage C S. 1 (PDF S. 131: 1 V-Halter je 5 Felder), S. 13 (PDF S. 143: Schutzwand 2 V-Halter im 5-Felder-Bild, strengste Lesung 2 je angefangene 5 Felder)Anlage B, S. 5, §B.5, S. 124, Anlage C, S. 1, S. 131, S. 13, S. 143Manufacturer's document (derived)
ALBERT UNITAC 704 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-979 ALBERT UNITAC 70 (02.04.2019, geänd. 19.03.2024 + 08.11.2024, bis 03.04.2029) Anlage B S. 3 §B.5 a–c (PDF S. 152), §B.10, Tab. B.5 (PDF S. 159: Netz 2 Dreieckhalter pro 5 Felder), Anlage C S. 1/2/3 (PDF S. 162–164: Dreieckhalter in jeder AnkerebeneAnlage B, S. 3, §B.5, S. 152, §B.10, S. 159, Anlage C, S. 1, S. 162–164Manufacturer's document (derived)
ALFIX ALBLITZ 70 S4 mEvery standard≤ 4 mDIBt Z-8.1-864 ALBLITZ 70 S (16.01.2023, bis 11.01.2028) Anlage B S. 3–5 §B.5 (PDF S. 382–384: Dreieckshalter nicht an den außenliegenden RahmenzügenAnlage B, S. 3–5, §B.5, S. 382–384, Anlage C, S. 1, S. 393, S. 5Manufacturer's document (derived)
ALFIX Facade4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-862 ALFIX 70 (16.12.2020 bis 05.01.2027) Anl. B S. 7–8 §B.5 (PDF S. 179–180: V-Halter nicht an den Stirnseiten, Kopplungsrohre am Leitergang), Tab. B.4 (PDF S. 181), Anl. C S. 2 (PDF S. 185: 8 m versetzt, durchgehende Verankerung bei H = 4,0 m, mindestens 1 Dreieckshalter pro 5 Felder), S. 6 (PDF S. 189: Außenkonsole Dreieckshalter an jedem 2. Rahmenzug)Anl. B, S. 7–8, §B.5, S. 179–180, S. 181, Anl. C, S. 2, S. 185, S. 6, S. 189Manufacturer's document (derived)
ALFIX Modul4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.22-906 ALFIX Modul (15.10.2021, Bescheide 31.01.2023, 02.04.2025, verl. 12.10.2026 bis 16.10.2031) Anl. C s.1–2 §C.1/§C.5 (PDF s. 196–197), Anl. D s.1 (PDF s. 201: mindestens 1 Dreieckshalter je 5 Felder, Schutzwandlage 2 je 5 Felder)Anl. C, s.1–2, §C.1, §C.5, s. 196–197, Anl. D, s.1, s. 201, s.2Manufacturer's document (derived)
ALFIX UNIFIX 704 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-847 UNIFIX 70 (21.12.2020, geänd. 04.04.2022, verl. bis 06.04.2027, geänd. 02.04.2025) Anlage B S. 8–9 §B.5 a–c (PDF S. 278–279: V-Halter nicht an den Stirnseiten), Anlage C S. 1 (PDF S. 284: mindestens 1 Dreieckshalter je 5 Felder, Schutzwandlage 2 je 5 Felder), S. 12 (Netz: 2 je 5 Felder) (2 pro 5 Felder als 2 je angefangene 5 Felder gelesen, strengste Lesung)Anlage B, S. 8–9, §B.5, S. 278–279, Anlage C, S. 1, S. 284, S. 12Manufacturer's document (derived)
ALTEC AluSprint4 mEvery standard≤ 4 mALTEC AluSprint AuV Regelausführung, Fassung 01.02.2010, §2.1 s.4 + §2.4.11 s.26 + Bild 17 s.24§2.1, s.4, §2.4.11, s.26, s.24Manufacturer's document
ALTRAD MAG 424 mEvery 2nd standard, staggered rows≤ 4 mALTRAD Saint Denis «Echafaudage MAG 42» fiche (ASD 11/2019s. 4, § 5.4.2, s. 5Manufacturer's document (derived)
ALTRAD Baumann ProfiTech A 73 plus4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-910 (19.12.2019, Bescheid 06.01.2026, verl. bis 13.01.2027) PROFITECH A 73 PLUS Anlage B S. 1 §B.1 (PDF S. 120: 24 m), S. 2 §B.5 a–c, Anlage C S. 1/8 (PDF S. 127/134: oberste Lage jeder Ständer, ② Zusatzanker in 4 m vor teilweise offener Fassade, Leitergang in jeder Ankerebene)Anlage B, S. 1, §B.1, S. 120, S. 2, §B.5, Anlage C, S. 127Manufacturer's document (derived)
ALTRAD Baumann ProfiTech S 73 plus4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-912 ProfiTech S 73 plus (08.05.2018, Bescheid 22.05.2023, verl. bis 03.06.2028) Anlage B S. 1 §B.1 (PDF S. 181: 24 m), S. 3 §B.5 (PDF S. 183), Anlage C S. 1 (PDF S. 191), S. 5/6/7/11 (Leitergang in jeder Ankerebene)Anlage B, S. 1, §B.1, S. 181, S. 3, §B.5, S. 183, Anlage C, S. 191, S. 5, S. 6Manufacturer's document (derived)
ALTRAD Baumann PROFITECH S 1094 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-909 PROFITECH S 109 (18.05.2021, verl. 02.01.2025 bis 08.01.2030) Anlage B S. 3 §B.5 (PDF S. 148: V-Anker nicht an den außenliegenden RahmenzügenAnlage B, S. 3, §B.5, S. 148, Anlage C, S. 1, S. 155Manufacturer's document (derived)
MOSTOSTAL Plus2 mEvery 2nd standard, staggered rows≤ 2 mALTRAD-Mostostal «MOSTOSTAL Plus frame scaffolding — assembly manual» (EN, 05.2023) §3.5.1 p. 20 (PDF 22), §3.5.5 basic option p. 22 (PDF 24)§3.5.1, p. 20, §3.5.5, p. 22Manufacturer's document (derived)
ROTAX Plus (Modular)4 mEvery standard≤ 4 mAltrad-Mostostal Instrukcja montażu ROTAX Plus 11.03.2026 §5 s. 32–34 (PDF 34–36) + RISE C900555 utg. 1 (2023-07-07, giltig t.o.m. 2033-07-07) vilkår 7–8§5, s. 32–34Manufacturer's document (derived)
Aluhak (Facade)4 mEvery standard≤ 2 mAluhak MONTERINGSVEILEDNING Rammestillas alu. kl. 1-3, M-02-2025-R001-NO rev. 25.06.2025 s.16–17s.16–17Manufacturer's document (derived)
Aluhak (Modular)4 mEvery standard≤ 2 mAluhak MONTERINGSVEILEDNING Systemstillas alu. kl. 1-6, M-01-2024-R001-NO rev. 18.12.2024 s.19–20s.19–20Manufacturer's document (derived)
ANKA H-Tipi Cephe6 mEvery standard≤ 2 mANKA «Cephe İskelesi Mamul ve Talimat El Kitabı» (30.12.2016) s. 29, 36–43 (ankraj detayları LC 3 / LC 4, 24 m), 44 (not published online)s. 29Manufacturer's document (derived)
assco Futuro4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.22-841 ASSCO FUTURO (23.1.2024) Anl. C §C.1, §C.5Anl. C, §C.1, §C.5, Anl. D, s.1, s. 8, §2.4.5.1, s.26, s. 30Manufacturer's document (derived)
ASSCO QUADRO 704 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-190 ASSCO QUADRO 70 (27.04.2018, Bescheid 02.05.2023, verl. bis 02.05.2028) Anlage B S. 3 §B.5 a–c (PDF S. 183), Anlage C S. 1 (PDF S. 191), S. 5/6/11Anlage B, S. 3, §B.5, S. 183, Anlage C, S. 1, S. 191, S. 5, S. 6Manufacturer's document (derived)
AT-PAC Ringlock4 mEvery 2nd standard, staggered rows≤ 4 mDoka Ringlock User Information 999817902 (09/2023) s.74 + Appendix D s.75–76 (= DIBt Z-8.22-992): 8 m versetzt, V-anchor ≥ 1 per 5 bays, wall tie directly below the node, lowest anchor plane b = 4 m with hSP ≤ 29 cm (s.76)s.74, s.75–76, s.76, s.91, s.97, Anlage C, §C.1, §C.5, S. 121Third-party document (derived)
BrandSafway SafLock6 m≤ 6 m apart≤ 6 m and ≤ 3 × depthBrandSafway «SafLock System Scaffold Technical Manual» ORN 2203 Rev. H (4/20) §3 p.57: first tie ≤ 3 × base width, ties at each end and ≤ 6 m along, ≤ 3 lifts vertically, the top within one lift, «all ties … as close to ledgers as possible» (not published online)§3, p.57, § 1926.452Manufacturer's document
Safway Systems Scaffold (USA)6.1 m≤ 6 m apart≤ 3.66 m and ≤ 4 × depthBrandSafway «Systems™ Scaffold Product Selection Guide» ORN 210 Rev. F § I.8b/8c (p.19): first tie ≤ 4 × base (3'-0": 3.66 m), ≤ 20 ft (≤ 3 ft wide) / 26 ft vertical, ends + ≤ 30 ft along§ I.8, p.19, § 1926.452Manufacturer's document (derived)
CETA Multiceta4 mEvery 2nd standard, staggered rows≤ 4 mCETA «Manuale Ancoraggi» Rev.2 (10/2009) s. 3–4 «area d'influenza: massimo 22 m2 … non coperta da teli … 20 m»s. 3–4Manufacturer's document (derived)
Condor (Modular/Ringlock)4 mEvery 2nd standard, staggered rows≤ 4 mCondor MULTICOM, NF 096 certificate R25.03 (AFNOR, 01.12.2025, valid until 30.11.2026, no renewal published on 11.11.2026) annex s. 1/4 «Anchored in alternate rows all 24 m²»s. 1, § 5.4.2Manufacturer's document (derived)
DELTA (Facade)4 mEvery 2nd standard, staggered rows≤ 4 mDELTA 73 DTR (Delta-Bud, Warszawa, wyd. 05.2020) §3.2.3 s. 57, §3.2.5 s. 58–59 «Podstawowe zasady wykonywania zakotwień» a–f, §6.2 s. 73, Wariant I s. 75 (not published online)§3.2.3, s. 57, §3.2.5, s. 58–59, §6.2, s. 73, s. 75, s. 59Manufacturer's document
DELTA (Modular/Wedge)4 mEvery 2nd standard, staggered rows≤ 4 mDELTA MODUŁ Instrukcja montażu (Delta Rusztowania, Warszawa (not published online)§6.3, s. 53, s. 55Manufacturer's document
Disk-lock Type B (China)4 mEvery 2nd standard, staggered rows≤ 4 mGB 55023-2022 §4.4.6 (≤ 3 跨 × 3 步 (not published online)§4.4.6, §6.3.6, §4.4.6-2Third-party document (derived)
Doka Ringlock4 mEvery 2nd standard, staggered rows≤ 4 mDoka Ringlock User Information 999817902 (09/2023) s.74 + Appendix D s.75–76 (= DIBt Z-8.22-992): 8 m versetzt, V-anchor ≥ 1 per 5 bays, wall tie directly below the node, lowest anchor plane b = 4 m with hSP ≤ 29 cm (s.76)s.74, s.75–76, s.76, s.91, s.97, Anlage C, §C.1, §C.5, S. 121Manufacturer's document (derived)
Excel Modular Scaffold (USA)6.1 m≤ 6 m apart≤ 4 m and ≤ 4 × depthExcel Modular Scaffold «Standard Component Technical Manual» Rev. AL PDF p. 115 (printed p. 109, SIA Code of Safe Practices item 5): ties at each end and ≤ 30 ft along, ≤ 26 ft vertical, the top anchor no lower than 4 × the base dimension from the topPDF p. 115, p. 109, § 1926.451, § 1926.452Manufacturer's document (derived)
FERMAR Fer484 m≤ 6 m apart≤ 4 mFERMAR «Andamio Europeo Fer48»: página web (leída 11.11.2026) § «Montaje» «La separación entre amarres será de 4 mtrs en altura y 6 en longitud» (primera fila ≤ 4 m: DERIVED)s. 7–9Manufacturer's document (derived)
Fortal (Facade)4 mEvery 2nd standard≤ 3 mFortal NT-054 V12 (FORTEC 650, 01.2023) §8 s. 12 «Tous les 24 m² maximum … non recouvert … en évitant d'avoir plus de 2 niveaux ou deux travées entre deux points d'ancrages consécutifs» (figure: every 2nd frame line every 2 levels), «ancrages fixés à l'intersection des montants avec les traverses»§8, s. 12, §9, s. 13, §5, s. 20Manufacturer's document (derived)
HAKI Ram4 mEvery standard≤ 4.5 mHAKI Monteringsveiledning Ram © HAKI AS 2023 06 (P000077) s. 26–27s. 26–27Manufacturer's document (derived)
HAKI Universal4 mEvery standard≤ 4.8 mHAKI Monteringsveiledning HAKI Universal (NO) © HAKI AS 2022 10 Rev 5 (P000073) s. 30s. 30Manufacturer's document (derived)
Hünnebeck BOSTA 70/1004 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-54.2 BOSTA 70 (16.06.2025, 07.05.2025 bis 07.05.2030) Anl. B §B.1 (PDF S. 176)/§B.5 (Ankerböcke nicht an den Stirnseiten, sonst einheitlich lange Gerüsthalter), Anl. C s.01/05/07Anl. B, §B.1, S. 176, §B.5, Anl. C, s.01Manufacturer's document (derived)
Hünnebeck MODEX2 mEvery 2nd standard, staggered rows≤ 4 mHünnebeck MODEX User guide EN 2020 §9 Tab. 9.1, mønster 1/3 s. 113–117 (åpen fasade§9, s. 113–117, s. 115, §9.2, s. 114–115, §4.1, s.14, §7.1, s.30Manufacturer's document (derived)
Instant Blitz-Fix 734 mEvery standard≤ 4 mRISE C901286 utg. 1 (2025-07-01) s. 3 pkt. 3 + s. 5 vilkår 5s. 3, s. 5, s. 25, s. 31Manufacturer's document (derived)
Jamax4 mEvery standard≤ 4 mAlutec «Brukerveiledning JAMAX stillassystemer» 4. utg. rev. 2 (28.08.2025) § 6.4.1 s. 16 Fordelingsmåte 1 (distribution method 1) + «Enkelt fag» (single bay)§ 6.4.1, s. 16, § 6.4.3–6.4.4, s. 17, § 10.5, s. 40, § 14, s. 41–42Manufacturer's document (derived)
JUMBO Facade2 mEvery 2nd standard, staggered rows≤ 2 mJUMBO FLEX Montagevejledning JUMBO 2MM Facadestillads 3/2024 (DK) s. 6 §4.7.2 + figur 1 (forskudt ved hverandet knudepunkt), s. 2 (maks. byggehøjde 30 m)s. 6, §4.7.2, s. 2Manufacturer's document (derived)
KERO RHU 0704 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-940 KERO RHU 070 (23.03.2023, bis 20.03.2028) Anlage B S. 3–4 §B.5 (PDF S. 216–217: jeder dritte Anker als Ankerbock, nicht an den Stirnseiten, sonst einheitlich lange Gerüsthalter), Anlage C S. 1/3/5 (PDF S. 223/225/227)Anlage B, S. 3–4, §B.5, S. 216–217, Anlage C, S. 1, S. 223Manufacturer's document (derived)
KERO RK 0734 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-895 KERO RK 073 (06.02.2020, Bescheid 24.02.2025, bis 07.02.2030) Anlage B S. 4 §B.5 + Tab. B.2 (PDF S. 163), S. 7 (PDF S. 166), Anlage C S. 1 (PDF S. 173): «Gerüsthalter "lang"»Anlage B, S. 4, §B.5, S. 163, S. 7, S. 166, Anlage C, S. 1, S. 173Manufacturer's document (derived)
KERO RPL 0704 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-975 KERO RPL 070 (02.04.2019, verl. 19.03.2024 bis 03.04.2029) Anlage B S. 3 §B.5 a–c (PDF S. 138), §B.10, Tab. B.5 (PDF S. 145: Netz 2 Dreieckhalter pro 5 Felder), Anlage C S. 1/2/3 (PDF S. 148–150: L = 3,00 m in 4 m Höhe alle Knoten) (2 pro 5 Felder als 2 je angefangene 5 Felder gelesen, strengste Lesung)Anlage B, S. 3, §B.5, S. 138, §B.10, S. 145, Anlage C, S. 1, S. 148–150Manufacturer's document (derived)
Layher Allround4 mEvery standard≤ 4 mDIBt Z-8.22-64 (23.04.2018, forlenget 02.05.2027) Anl. C s.2 §C.5 Ausf. B + Anl. D s.3Anl. C, s.2, §C.5, Anl. D, s.3, §12, s.35, s.36, s.52, s.37Manufacturer's document (derived)
Layher Allround STAR 704 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-919 Layher Allround STAR 70 (07.11.2022, bis 02.11.2027) Anlage B S. 3 §B.5 (PDF S. 145: V-Anker nicht an den außenliegenden RahmenzügenAnlage B, S. 3, §B.5, S. 145, S. 6, S. 148, Anlage C, S. 22, S. 176, S. 1Manufacturer's document (derived)
Layher Blitz4 mEvery standard≤ 4 mDIBt Z-8.1-16.2 Anlage B s. 1 §B.1 + s. 4 §B.5 bs. 27, §8, s. 28, s. 4, s. 6, Anlage B, s. 1, §B.1, §B.5, Anl. B, s. 3, Anlage C, s. 2–3Manufacturer's document (derived)
Layher Blitz 70 Alu4 mEvery standard≤ 4 mDIBt Z-8.1-844 Layher Blitz Gerüst 70 Alu (20.04.2020, verl. bis 21.04.2030) Anlage B §B.1 (PDF S. 178), §B.5 a–b (PDF S. 180), Anlage C S. 1 (PDF S. 188)Anlage B, §B.1, S. 178, §B.5, S. 180, Anlage C, S. 1, S. 188Manufacturer's document (derived)
Metaltech Saferstack (USA)4 m≤ 6 m apart≤ 2.7 m and ≤ 3 × depthMetaltech «Exterior Scaffolding Set Up Instructions / Safety Guidelines» (undated poster, PDF 22.04.2015) p. 1: 3 to 1 rule (tie above 3 × the smallest base dimension)p. 1, § 1926.451, § 1926.452Manufacturer's document (derived)
Metaltech Saferstack Mason (USA)4 m≤ 6 m apart≤ 1.83 m and ≤ 3 × depthMetaltech «Exterior Scaffolding Set Up Instructions / Safety Guidelines» (undated poster, PDF 22.04.2015) p. 1: 3 to 1 rule (24" narrowest frame: 1.83 m)p. 1, § 1926.451, § 1926.452Manufacturer's document (derived)
MJ COMBI4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.22-921 MJ COMBI (13.10.2020, geänd. 05.09.2025, verl. bis 04.09.2030) Anlage C §C.1, §C.2, §C.5 (PDF S. 112–113: 8 m versetztAnlage C, §C.1, §C.2, §C.5, S. 112–113, Anlage D, S. 1, S. 116, S. 2, S. 117Manufacturer's document (derived)
MJ OPTIMA4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.22-986 MJ OPTIMA (17.03.2021, Bescheide 13.06.2022, 17.04.2024, 06.07.2026, bis 23.07.2027) Anlage C S. 2 §C.5 (PDF S. 90: V-Halter nicht am RandAnlage C, S. 2, §C.5, S. 90, Anlage D, S. 32Manufacturer's document (derived)
MJ UNI 70/1004 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-184 MJ UNI 70 (21.06.2019, verl. 06.07.2026 bis 13.07.2027) Anlage B S. 3 §B.5 a–c (PDF S. 94), §B.9, Anlage C S. 1 (PDF S. 98: langer Anker am Innen- und Außenständer, V-Anker), S. 3 (PDF S. 100: Schutzwand 2 V-Anker im 5-Felder-Bild, strengste Lesung 2 je angefangene 5 Felder), S. 8 (PDF S. 105: Netz, Randrahmen alle 2 m, 2 V-Anker im 5-Felder-Bild, strengste Lesung 2 je angefangene 5 Felder), S. 12 (PDF S. 109: L = 3,0 m, 4 m-Ebene alle Rahmen)Anlage B, S. 3, §B.5, S. 94, §B.9, Anlage C, S. 1, S. 98, S. 100, S. 8, S. 105, S. 12, S. 109Manufacturer's document (derived)
MJ UNI TOP 654 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-902 MJ UNI TOP 65 (11.08.2026, 18.08.2026 – 18.08.2031) Anlage B S. 3–4 §B.5 a–c (PDF S. 197–198: V-Halter nicht am Rand), §B.9 (PDF S. 200), Anlage C S. 1 (PDF S. 204: 1 V-Halter je 5 Felder), S. 4 (Netz: 2 V-Halter im 5-Felder-Bild, strengste Lesung 2 je angefangene 5 Felder), S. 7 (Schutzwand: 2 V-Halter im 5-Felder-Bild, strengste Lesung 2 je angefangene 5 Felder)Anlage B, S. 3–4, §B.5, S. 197–198, §B.9, S. 200, Anlage C, S. 1, S. 204, S. 4, S. 7Manufacturer's document (derived)
MJ UNI-CONNECT4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-872 MJ UNI-CONNECT 70 DUO (16.03.2022, Bescheid 10.06.2024) Anlage B S. 5 §B.5 a–c (PDF S. 403), Anlage C S. 1 (PDF S. 413: Fußnote 1 kurzer Gerüsthalter entfällt vor der geschlossenen Fassade, Rohr ø48,3 + NK innen unter den V-Haltern), S. 5/6 (PDF S. 417/418: Netz ohne Konsolen), S. 11 (Plane), S. 14 (PDF S. 426: Schutzwand, 2 V-Halter im 5-Felder-Bild, strengste Lesung 2 je angefangene 5 Felder)Anlage B, S. 5, §B.5, S. 403, Anlage C, S. 1, S. 413, S. 417, S. 11, S. 14, S. 426Manufacturer's document (derived)
Müller & Baum FIX 70S4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-182 Rahmengerüst FIX 70S (30.01.2020, verl. 21.01.2025 bis 31.01.2030) Anlage B S. 3 §B.5 a–c (PDF S. 135: Dreiecksanker nicht am Rand), Anlage C S. 1/2 (PDF S. 140/141: mindestens zwei Dreiecksanker pro 5 Felder, durchgehend bei H = 4,0 m), S. 8/11 (2 pro 5 Felder als 2 je angefangene 5 Felder gelesen, strengste Lesung)Anlage B, S. 3, §B.5, S. 135, Anlage C, S. 1, S. 140, S. 8Manufacturer's document (derived)
OLAN (Facade)2 mEvery 2nd standard, staggered rows≤ 2 mOLAN Euro+ Instrukcja montażu wyd. 2 (05.2017) §4.F s. 20 (PDF 21) + §9 A schemat s. 44 (PDF 45): kotwy na każdym poziomie co drugi stojak, przesunięte o jeden stojak (każdy stojak co 4 m), kotwa podwójna V jedna na 5 pól i minimum dwie na każdej kotwionej kondygnacji, do 34 m§4, s. 20, §9, s. 44Manufacturer's document
OLAN (Modular)4 mEvery 2nd standard, staggered rows≤ 4 mOLAN «R+ modular scaffolding – Operation and Maintenance Manual» (Żabokliki 2020) ch. 9 s. 46–47, §4 s. 24, rule 22 s. 9s. 46–47, §4, s. 24, s. 9Manufacturer's document (derived)
PERALTA Donnergerüst 70 S4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-936 PERALTA – Donnergerüst 70 S (30.06.2023, geänd. 04.03.2026, bis 20.03.2031) Anlage B S. 4 §B.5 + Tab. B.2 (PDF S. 342–343), Anlage C S. 1 (PDF S. 354: Gerüsthalter "lang" oder Blitzanker), S. 21Anlage B, S. 4, §B.5, S. 342–343, Anlage C, S. 1, S. 354, S. 21Manufacturer's document (derived)
PERI UP4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.22-863 (22.09.2025) Anlage C §C.1/§C.5 (mindestens zwei Gerüsthalter oder ein Dreiecksanker je AnkerlageAnlage C, §C.1, §C.5, §C.4, Anlage D, s.2, s.1, §B4.5.1-B4.5.2Manufacturer's document (derived)
PERI UP Easy4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-957 PERI UP Easy (16.05.2022, Bescheide 26.09.2022, 30.09.2024, 12.05.2025, b = 0,67 m, bis 16.05.2027) Anlage C S. 3–4 §C.5 (PDF S. 304–305), Anlage C S. 9 (PDF S. 310: mindestens zwei Gerüsthalter oder ein Dreiecksanker je Ankerlage), Anlage D S. 3 (PDF S. 322: Grundvariante 1a)Anlage C, S. 3–4, §C.5, S. 304–305, S. 9, S. 310, Anlage D, S. 3, S. 322Manufacturer's document (derived)
Plettac Contur4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.22-843 plettac contur (9.5.2019, forl. 19.3.2024 bis 3.4.2029) Anl. C §C.1, §C.5 s.1–2Anl. C, §C.1, §C.5, s.1–2, Anl. D, s.1, S. 10, §2.4.5.1Manufacturer's document (derived)
Plettac PD 70/1004 mEvery 2nd standard, staggered rows≤ 4.6 mplettac Distribution PD 70/100 Assembly and use manual (Ostrzeszów, July 2013, EN 12810-3N, certificate Z/002/034/25 valid 19.12.2025–18.12.2028) §1.1 pt 3/7/8 (PDF S. 5: max h 24 m), §3.1.3.6 (PDF S. 21), anchor drawings PDF S. 24–26 (● long anchors)§1.1, S. 5, §3.1.3.6, S. 21, S. 24–26Manufacturer's document (derived)
Plettac SL 70 Alu4 mEvery standard≤ 4 mDIBt Z-8.1-29.1 plettac SL 70-Alu (16.12.2020, verl. bis 03.01.2031) Anlage B §B.1 (PDF S. 110), §B.5 (PDF S. 111), Anlage C (3,00 m, teilweise offen: 4 m durchgehend)Anlage B, §B.1, S. 110, §B.5, S. 111, Anlage CManufacturer's document
Plettac SL 70/1004 mEvery 2nd standard, staggered rows≤ 4.6 mDIBt Z-8.1-29 PLETTAC SL 70 (5.6.2020, endr. 29.10.2020, 28.5.2025 og 21.8.2026, bis 3.6.2030) Anl. B §B.1 (PDF S. 167), §B.5 a s.3–4, Tab. B.3 s.8, Anl. C s.6–8/17/18Anl. B, §B.1, S. 167, §B.5, s.3–4, s.8, Anl. C, s.6–8Manufacturer's document (derived)
Plettac Distribution (Modular)4 mEvery standard≤ 4 mPlettac Distribution «Instruction manual on assembly and use of PDM and PDM/c» (June 2025) §5.1 c (PDF S. 27: H = 24 m), §5.2.9 s. 28 (PDF p30), Fig. 30 (PDF S. 29: long anchors), §5.1 h§5.1, S. 27, §5.2.9, s. 28, PDF p30, S. 29Manufacturer's document
Ponteggi Dalmine (Facade)4 mEvery 2nd standard, staggered rows≤ 4 mMarcegaglia Buildtech «Manuale di utilizzo – sistemi di ponteggio a telai prefabbricati» (07/2017) s. 32 «ogni 22 mq di ponteggio di facciata», s. 30 (> 20 m: progetto)s. 32, s. 30Manufacturer's document (derived)
RARIS Alu (Facade)4 mEvery 2nd standard, staggered rows≤ 4 mRARIS «Schele de faţadă — Manual de utilizare» s. 13 (ancorare < 20 m: cadre laterale din 4 în 4 m, celelalte din 8 în 8 m în zig-zag)s. 13Manufacturer's document
Ringer Doppelgeländer4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-858 Ringer Doppelgeländer (10.02.2020, verl. 11.02.2025 bis 14.02.2030) Anlage B §B.1 (PDF S. 51), §B.5 a–c, Anlage C S.1–S.7 (PDF S. 56–62)Anlage B, §B.1, S. 51, §B.5, Anlage C, S.1, S.7, S. 56–62Manufacturer's document
ROLLE BLIZZARD S-704 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-974 ROLLE BLIZZARD S-70 (06.02.2025, geänd. 01.04.2026, bis 28.03.2031) Anlage B S. 3–4 §B.5 + Tab. B.2 (PDF S. 264–265), Anlage C S. 1 (PDF S. 276: Gerüsthalter "lang" oder Blitzanker), S. 20Anlage B, S. 3–4, §B.5, S. 264–265, Anlage C, S. 1, S. 276, S. 20Manufacturer's document (derived)
Scaffolding Center SC 704 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-990 SC 70 (03.03.2026, 16.03.2026 – 16.03.2031) Anlage B S. 3–4 §B.5 a–c (PDF S. 184–185), Anlage C S. 6 (PDF S. 194: 1 Dreieckhalter je 5-Felder-Abschnitt, ① Anker bei teilweise offener Fassade), S. 10 (PDF S. 198: Netz 2 Dreieckhalter je 5-Felder-Abschnitt in jeder Ankerebene, nur gezeichnet, strengste Lesung 2 je angefangene 5 Felder), S. 11 (PDF S. 199: Plane, strengste Lesung 2 je angefangene 5 Felder), S. 32 (PDF S. 220: Kopplungsrohr unter allen Durchstiegen)Anlage B, S. 3–4, §B.5, S. 184–185, Anlage C, S. 6, S. 194, S. 10, S. 198, S. 11, S. 199, S. 32, S. 220Manufacturer's document (derived)
Scaffolding Center SC 734 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-991 SC 73 (20.01.2022, bis 20.01.2027) Anlage B S. 4 §B.5 + Tab. B.2 (PDF S. 245–246), Anlage C S. 1 (PDF S. 256: Gerüsthalter "lang" oder Blitzanker)Anlage B, S. 4, §B.5, S. 245–246, Anlage C, S. 1, S. 256Manufacturer's document (derived)
FRAMESCAFF 734 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-924 FRAMESCAFF 73 (05.07.2021, geänd. 02.09.2025, verl. 18.06.2026 bis 06.07.2031) Anlage B S. 3–4 §B.5 (PDF S. 255–256: «Unbekleidete Gerüste sind in Höhe 4 m durchgehend zu verankern»Anlage B, S. 3–4, §B.5, S. 255–256, Anlage C, S. 1, S. 262, S. 4, S. 7, S. 268Manufacturer's document (derived)
Scafom-Rux RINGSCAFF4 mEvery standard≤ 4 mDIBt Z-8.22-869 RINGSCAFF (09.04.2021, geänd. 02.04.2025, verl. 20.03.2026 bis 11.04.2031) Anlage C S. 2 §C.5 (PDF S. 91: jeder Ständerzug alle 4 m, in der obersten Ebene jeder StänderzugAnlage C, S. 2, §C.5, S. 91, Anlage D, S. 01, S. 94, S. 28–29Manufacturer's document (derived)
Scafom-Rux SUPER4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-185.2 RUX Super 100 (20.02.2023, bis 13.02.2028) Anlage B §B.5 a (PDF s. 131), Anlage C S.1 «8 m versetzt, Zusatzanker in H = 4 m», S.3 «Zusatzanker in H = 4 m, 20 m, 24 m»Anlage B, §B.5, s. 131, Anlage C, S.1, S.3Manufacturer's document (derived)
Scafom-Rux SUPER 654 mEvery standard≤ 4 mDIBt Z-8.1-185.1 RUX SUPER 65 (30.06.2023, geänd. 23.01.2024, bis 05.01.2027) Anlage B §B.5 (PDF S. 153–154), Tab. B.3/B.4 (PDF S. 159–160), Anlage C S. 1 (PDF S. 163), S. 3 (PDF S. 165: Innen- und Außenkonsolen), S. 4 (PDF S. 166: Netz, 2 V-Halter im 5-Felder-Bild, strengste Lesung 2 je angefangene 5 Felder), S. 6 (PDF S. 168: Plane, jeder Knoten), S. 8 (PDF S. 170: Schutzwand, 2 V-Halter in der obersten Ankerlage)Anlage B, §B.5, S. 153–154, S. 159–160, Anlage C, S. 1, S. 163, S. 3, S. 165, S. 4, S. 166, S. 6, S. 168, S. 8, S. 170Manufacturer's document (derived)
SGB CUPLOK4 mEvery standard≤ 4.5 mSGB CUPLOK® User Manual UK (Brand Energy & Infrastructure Services UK, 2016) s. 48 (PDF) «A. CUPLOK 2.0m lifts - 4m tie pattern · Horizontal spacing - every standard · Vertical spacing - maximum 4.0m», s. 36 Table 4 (8m tie pattern ≤ 4 lifts without foot ties), p31 rules 4 + 6, p32 «limit heights … to 12 lifts (24m)», p29 «unsheeted scaffolds only»s. 48, s. 36, p31, p32, p29, Anlage C, §C.2, §C.5, S. 48–49, Anlage D, S. 1, S. 52, p52Manufacturer's document (derived)
SIGMA (Facade)4 mEvery standard≤ 4 mSIGMA 73LB DTR «Instrukcja montażu i użytkowania rusztowania SIGMA 73LB» §2.2.2 s. 12, §5.1, §5.3, §5.6, Rys. 21 s. 25§2.2.2, s. 12, §5.1, §5.3, §5.6, s. 25Manufacturer's document
SIGMA RTM (Wedge)4 mEvery 2nd standard, staggered rows≤ 4 mSIGMA RTM DTR «Instrukcja montażu i użytkowania rusztowania modułowego SIGMA RTM» 09/2024 §5.1, §5.3 s. 29 (PDF), Rys. 31 s. 32§5.1, §5.3, s. 29, s. 32Manufacturer's document
Solideq RAMSCAFF4 mEvery standard≤ 4.5 mSolideq RAMSCAFF, RISE sertifikat C900487 utg. 1 2022-10-01 (gyldig til 2032-10-01) s. 7 vilkår 6 + Monteringsanvisning Ramscaff 2022-02 (norsk) s. 33 §2.5.1, s. 34 fig. 4.3, s. 4 (maks. 24 m + 0,5 m)s. 7, s. 33, §2.5.1, s. 34, s. 4Manufacturer's document (derived)
Tobler MATO4 mEvery 2nd standard, staggered rows≤ 4 mDIBt Z-8.1-937 Tobler MATO 1 (15.08.2022 bis 15.08.2027, Bescheide 07.02.2023, 02.01.2024, 10.06.2024) Anlage B §B.1 (PDF S. 87), §B.5, Anlage C S.1, S.4–S.6Anlage B, §B.1, S. 87, §B.5, Anlage C, S.1, S.4, S.6, S. 3, S. 89Manufacturer's document (derived)
Tubesca-Comabi M368 (Modular)4 mEvery 2nd standard, staggered rows≤ 3 mTubesca-Comabi «Notice de montage M368/R200P/R200R» 100-00035775-ind.2 (09.2024) §14.1 s. 68 (cas 1: extrémités tous les 4 m, autres files tous les 8 m en quinconce, 24 m², «immédiatement au-dessous du plancher (ou maximum à 0.15 m)»), s. 69 (protection couvreur: chaque file au dernier niveau de plancher), §6.1 s. 34 (> 24 m: étude BEAC)§14.1, s. 68, s. 69, §6.1, s. 34Manufacturer's document (derived)
Tubesca-Comabi R200 Progress4 mEvery 2nd standard, staggered rows≤ 3 mTubesca-Comabi «Notice de montage M368/R200P/R200R» 100-00035775-ind.2 (09.2024), R200 PROGRESS: §14.1 s. 68 (cas 1: extrémités tous les 4 m, autres files tous les 8 m en quinconce, 24 m², «immédiatement au-dessous du plancher (ou maximum à 0.15 m)»), s. 69 (protection couvreur: chaque file au dernier niveau de plancher), ch. 5 s. 30 (NR 24 / 20 / 16 m², R 12 / 10 / 8 m² pour une maille de 3 / 2,5 / 2 m), §6.1 s. 34 (> 24 m: étude BEAC)§14.1, s. 68, s. 69, s. 30, §6.1, s. 34Manufacturer's document (derived)
Waco Frame (USA)4 m≤ 6 m apart≤ 4 m and ≤ 4 × depthWaco RED frame scaffolding brochure ORN1701 (BrandSafway 2020) p. 20 «Scaffolding Safety Guidelines» F (SSFI): first tie at 4 × the minimum base, vertical ≤ 26 ft (7.9 m), at each end and ≤ 30 ft (9.1 m) alongp. 20, § 1926.451, § 1926.452Manufacturer's document (derived)
WACO Narrow Frame (USA)4 m≤ 6 m apart≤ 2.81 m and ≤ 4 × depthWACO ORN1701 p. 5 (Narrow Frame 2'-3 5/8" × 6'-7")p. 5, § 1926.451, § 1926.452Manufacturer's document (derived)
WACO RED Access Frame (USA)4 m≤ 6 m apart≤ 4 m and ≤ 4 × depthWaco RED frame scaffolding brochure ORN1701 (BrandSafway 2020) p. 20 «Scaffolding Safety Guidelines» F (SSFI): first tie at 4 × the minimum base, vertical ≤ 26 ft (7.9 m), at each end and ≤ 30 ft (9.1 m) alongp. 20, § 1926.451, § 1926.452Manufacturer's document (derived)
WACO RED Box Frame (USA)4 m≤ 6 m apart≤ 4 m and ≤ 4 × depthWaco RED frame scaffolding brochure ORN1701 (BrandSafway 2020) p. 20 «Scaffolding Safety Guidelines» F (SSFI): first tie at 4 × the minimum base, vertical ≤ 26 ft (7.9 m), at each end and ≤ 30 ft (9.1 m) alongp. 20, § 1926.451, § 1926.452Manufacturer's document (derived)
Yagmur Iskele (H-Type)4 mEvery standard≤ 3 mYağmur «Güvenlikli İskele Sistemi Mamul El Kitabı» (2026-07) §9.1.9 s. 43 (ankraj: tüm panolar, 6 m kaplamasız, 4 m fileli, 2 m brandalı), s. 9 (24 m üzeri hesap)§9.1.9, s. 43, s. 9Manufacturer's document (derived)
Yagmur Iskele (Ringlock)4 mEvery standard≤ 3 mYağmur «Flanşlı İskele Sistemi Mamul El Kitabı» (2026-07) §11 s. 66–68 (ankraj: 6 m kaplamasız, 4 m fileli, 2 m brandalı, 24 m), s. 9 (24 m üzeri hesap)§11, s. 66–68, s. 9Manufacturer's document (derived)
Japanese frame scaffold (枠組足場)9 m≤ 8 m apart≤ 4 m労働安全衛生規則 §570 第1項第5号イ (枠組足場: 垂直方向 9 m、水平方向 8 m 以下)§570, p. 58, p. 98Regulation (derived)
Kwikstage4 mEvery 2nd standard, staggered rows≤ 4 mWaco Kwikform «Guidelines for safe use of scaffold – Wedgelok / Kwikstage» PPM51 (08/2013) s. 5 «Scaffold Ties» 1(a)/(b) + table «Tie configurations for scaffolds up to 30 metres» (each end + ≤ every 3rd standard, first ≤ 4.0 m, ≤ 4.0 m ups. 5Third-party document (derived)
ЛРСП-402 mEvery 2nd standard, staggered rows≤ 4 mЛРСП-40 паспорт (ТУ 5225-001-11713507-04) §4.5 с. 6 «через 4м в шахматном порядке», с. 8 «Схема крепления лесов к стене» (каждый ярус с 4 м, стойки через одну, в шахматном порядке), §2.1 «Максимальная высота лесов, м 40» (not published online)§4.5, §2.1Manufacturer's document (derived)

Estimates (≈): rules not yet checked

24 systems. ScaFix still plans them, with the spacing below, but prints their tie counts as estimates until the rule is checked against the manufacturer's document. Verification status by scaffold system tracks the status.

SystemVerticalAlong the faceFirst tieWhat the figure isWhy an estimate
Bil-Jax Ring Lock≈4 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualNo document cited: ScaFix's general planning default (from no manufacturer document and no clause of a standard)
Catari US Ringlock≈4 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualNo document cited: ScaFix's general planning default (from no manufacturer document and no clause of a standard)
Condor (Facade)≈4 mEvery 2nd standard, staggered rows≤ ≈4.6 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: D.Lgs. 81/2008 art. 125 c. 6 «ancorato alla costruzione almeno in corrispondenza ad ogni due piani di ponteggio e ad ogni due montanti, con disposizione di ancoraggi a rombo o di pari efficacia»
Condor (Tube & coupler)≈4 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: D.Lgs. 81/2008 art. 125 c. 6 «ancorato alla costruzione almeno in corrispondenza ad ogni due piani di ponteggio e ad ogni due montanti, con disposizione di ancoraggi a rombo o di pari efficacia»
DECKMAN (Facade)≈4 mEvery 2nd standard, staggered rows≤ ≈4.6 m≈ estimate – no manufacturer rule on file; follow the supplier's manualNo document cited: ScaFix's general planning default (from no manufacturer document and no clause of a standard)
JUMBO System≈4 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualNo document cited: ScaFix's general planning default (from no manufacturer document and no clause of a standard)
ÖZLER (Shoring/Falsework)≈4 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualNo document cited: ScaFix's general planning default (from no manufacturer document and no clause of a standard)
Pilosio MP≈4 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: D.Lgs. 81/2008 art. 125 c. 6 «ancorato … ogni due piani di ponteggio e ad ogni due montanti, con disposizione di ancoraggi a rombo» (art. 138 c. 5), art. 133 c. 1 (oltre 20 m: progetto)
Ponteggi Dalmine (Modular)≈4 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: D.Lgs. 81/2008 art. 125 c. 6 «ancorato … ogni due piani di ponteggio e ad ogni due montanti, con disposizione di ancoraggi a rombo» (art. 138 c. 5), art. 133 c. 1 (oltre 20 m: progetto)
RUBO RK (klinowe)≈4 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: Rozp. MI 6.02.2003 (Dz.U. 2003 nr 47 poz. 401) §115 ust. 1–3: siatkę kotew określa dokumentacja producenta lub projekt, ≥ 2,5 kN na kotwę, pomost ≤ 1,5 m nad najwyżej położoną linią kotew
StepUp Cuplock≈4 mEvery 2nd standard, staggered rows≤ ≈3.6 m and ≤ 4 × depth≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: 29 CFR § 1926.451(c)(1)(ii): first tie at the 4:1 height, then ≤ 20 ft (≤ 3 ft wide) / ≤ 26 ft (7.9 m) vertically, at each end and ≤ 30 ft (9.1 m) along (the same numbers reprinted in WACO ORN1701 p. 20 F «Scaffolding Safety Guidelines»). StepUp publishes no tie rule (StepUp catalogs 2024-02)
StepUp Frame & Brace≈4 m≤ 6 m apart≤ ≈3.6 m and ≤ 4 × depth≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: 29 CFR § 1926.451(c)(1)(ii): first tie at the 4:1 height, then ≤ 20 ft (≤ 3 ft wide) / ≤ 26 ft (7.9 m) vertically, at each end and ≤ 30 ft (9.1 m) along (the same numbers reprinted in WACO ORN1701 p. 20 F «Scaffolding Safety Guidelines»). StepUp publishes no tie rule (StepUp catalogs 2024-02)
StepUp RingLock≈4 mEvery 2nd standard, staggered rows≤ ≈3.6 m and ≤ 4 × depth≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: 29 CFR § 1926.451(c)(1)(ii): first tie at the 4:1 height, then ≤ 20 ft (≤ 3 ft wide) / ≤ 26 ft (7.9 m) vertically, at each end and ≤ 30 ft (9.1 m) along (the same numbers reprinted in WACO ORN1701 p. 20 F «Scaffolding Safety Guidelines»). StepUp publishes no tie rule (StepUp catalogs 2024-02)
ULMA BRIO≈4 m≤ 6 m apart, staggered rows≤ ≈4 m≈ estimate – rule not yet checked against the manufacturer's document; follow the supplier's manualCited, not yet checked: ULMA Guía de Usuario Andamio Multidireccional BRIO, dok. 02FAN08, s.66/s.82/s.156-157 (1 feste per 24 m²) (not published online)
Cup-lock JGJ 166 (China)≈3.6 m≤ 4.5 m apart≤ ≈2.5 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: JGJ 166-2016 表6.2.1 (PDF s. 45–46: 二步三跨, 步距 1.8 m, 横距 0.9 / 1.2 m, 纵距 1.5 / 1.2 m, H 34–50 m by w0), §6.2.9-2 (PDF s. 48: «水平投影间距不得超过三跨,竖向垂直间距不得超过三步,… 悬臂高度不得超过两步»), §6.2.9-3 (PDF s. 49: 转角处、开口型端部, ≤ 层高且 ≤ 4m), §6.2.9-4, -7 (PDF s. 49: «从底层第一道水平杆处开始设置», «距架体碗扣主节点距离不应大于 300mm») (not published online)
Cuplock≈4 mEvery standard≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualNo document cited: ScaFix's general planning default (from no manufacturer document and no clause of a standard)
Japanese wedge scaffold A-type (くさび緊結式足場)≈5 m≤ 5.5 m apart≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: 労働安全衛生規則 §570 第1項第5号イ (単管足場: 垂直方向 5 m、水平方向 5.5 m 以下)
Japanese wedge scaffold B-type (くさび緊結式足場)≈5 m≤ 5.5 m apart≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: 労働安全衛生規則 §570 第1項第5号イ (単管足場: 垂直方向 5 m、水平方向 5.5 m 以下)
Korean system scaffold (시스템비계)≈5 m≤ 5 m apart≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: 산업안전보건기준에 관한 규칙 제69조 제5호 (벽 연결재: 제조사가 정한 기준)
Rusztowanie warszawskie≈1.73 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: Rozp. MI 6.02.2003 (Dz.U. 2003 nr 47 poz. 401) §115 ust. 1–3: siatkę kotew określa dokumentacja producenta lub projekt, ≥ 2,5 kN na kotwę, pomost ≤ 1,5 m nad najwyżej położoną linią kotew
Shoring / falsework≈4 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualNo document cited: ScaFix's general planning default (from no manufacturer document and no clause of a standard)
Tube & coupler≈4 m≤ 6 m apart≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualNo document cited: ScaFix's general planning default (from no manufacturer document and no clause of a standard)
Tube & coupler JGJ 130 (China)≈3.6 m≤ 4.5 m apart≤ ≈2.5 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: JGJ 130-2011 表6.1.1-1 (s. 27, PDF s. 36: 二步三跨, lb 1.05 / 1.30 m, h 1.80 m, H 32 / 30 m, w0 = 0.4 kN/m²), 表6.4.2 (PDF s. 41: 竖向 ≤ 3h, 水平 ≤ 3la, ≤ 40 m²), §6.4.3 (PDF s. 41–42: «偏离主节点的距离不应大于 300mm», «从底层第一步纵向水平杆处开始设置»), §6.4.4 (PDF s. 42: 开口型两端, ≤ 层高且 ≤ 4m)
ЛСК-60≈4 mEvery 2nd standard, staggered rows≤ ≈4 m≈ estimate – no manufacturer rule on file; follow the supplier's manualCited, not yet checked: Приказ Минтруда России № 782н (ред. 29.04.2025) п. 89 (крайние стойки через ярус, верхний ярус через два пролета, 1 крепление на 50 м²)

What changes the spacing on a real scaffold

The tables are the open-facade rules. The engine tightens them where the manufacturer or the situation asks for it:

  • Sheeting and netting: a sheeted (tarp) scaffold is tied at every standard every 2 m in ScaFix's general adjustment, a netted one at most 4 m apart both ways; 103 systems have the manufacturer's own cladding rule instead.
  • Roof-edge brackets: 33 rules add ties for the brackets (consoles) of a roof-edge protection on the wall.
  • V-ties and cross anchors: 49 rules add a second tie in some standards of each tie row, which keeps the scaffold from moving along the facade.
  • 106 rules state a top platform height above which the manufacturer requires a calculation or that is the system's maximum, from 4.6 m to 60 m.
  • One-bay scaffolds, long bays on a long base jack and the top of a scaffold with roof-edge protection get extra ties where the system's rule says so.

A planning aid, not a structural approval

These are the rules ScaFix plans and counts ties with. They do not replace the manufacturer's instructions for the configuration you build, the tie's capacity in the actual wall, or a structural calculation where the rule or the regulations require one. ScaFix is a planning aid, not structural approval.

Limits

  • The number of wall ties follows the system's tie rule. Their positions must be checked against the manufacturer's assembly instructions.
  • Round corners, silos and hanging scaffolds are in Pro. A round scaffold is not a standard configuration and needs a calculation or the supplier's documentation. A hanging scaffold (Layher Allround and HAKI Universal) always needs a structural calculation from the supplier or an engineer.

Questions and answers

What is the maximum vertical spacing of scaffold wall ties?

It is the manufacturer's figure for the system and the cladding. In ScaFix's catalogue 99 of 115 rules use 4 m on an open facade; the others use 2 m (5), 5 m (3), 3.6 m (2), 6 m (2), 6.1 m (2), 1.73 m (1) and 9 m (1). A sheeted scaffold is tied more densely.

How high may the first wall tie be?

In most rules (86 of 115) the first tie row must sit at or below 4 m. 13 rules also cap it at a multiple of the scaffold's own depth (4:1 and 3:1), from the US rule 29 CFR § 1926.451(c)(1)(ii) and the makers' own manuals. The table above gives every system's figure.

How many wall ties per 100 m² of scaffold?

On ScaFix's reference house the engine places a median of 13.3 ties per 100 m² of scaffold face, from 6.0 to 51.0 depending on the system; the scaffold statistics page lists every system. Spacing, bay length and cladding move the figure.

Why is a tie spacing marked ≈?

Because ScaFix has not yet checked that system's rule against the manufacturer's document, or no document is cited and the engine uses its general rule. The count is then an estimate: check the manufacturer's instructions before you order or erect.

Sources

ScaFix plans each scaffold system from the documents that system's page names (the manufacturer's manual or approval, where one is on file); the rules come from EN 12811-1 and the national authority. Read 10 November 2026. The documents, not this page, decide how the scaffold is built: ScaFix plans, it does not approve.