Scaffold system
Korean system scaffold scaffold: bay lengths, depths and parts list
Korean system scaffold has bay lengths of 0.91–1.83 m and depths of 0.61–1.22 m in ScaFix. Enter your walls, and ScaFix draws the Korean system scaffold scaffold in 3D and works out its parts list. Any other size: Scaffold calculator.
By Ole Emil Frikstad Urstad · How the numbers are computed ·

How many parts does Korean system scaffold need for a house?
ScaFix plans Korean system scaffold with the bay lengths 1.83 m, 1.52 m, 1.22 m and 0.91 m and scaffold depth 0.61–1.22 m. On ScaFix’s 11.4 m × 5.3 m example house, scaffolded all round, Korean system scaffold needs 811 parts; Layher Allround needs 515 on the same house.
Scaffold calculator
What is Korean system scaffold?
The Korean system scaffold (시스템비계) is a scaffold type several Korean makers build. ScaFix plans it in 1.9 m lifts with bays of 0.914 to 1.829 m, from two Korean suppliers’ part lists. The 475 mm node pitch and the widths of 0.61, 0.914 and 1.219 m are derived from those part lengths; no page on file prints them.
It suits estimates for facade scaffolds on Korean sites. On ScaFix’s example house it needs 811 parts. ScaFix counts the ties at most 5 m apart vertically and 5 m apart along the wall, with ties at the top level and at the ends.
What does the Korean system scaffold documentation warn about?
Korean law leaves the tie spacing to the manufacturer (Rules on Occupational Safety and Health Standards, article 69, item 5), and ScaFix has no manufacturer rule. It plans the fallback of the Korean construction specification KCS 21 60 10 : 2025 (§3.3.5 (1): at most 5 m vertically and 5 m horizontally).
The same clause bases the tie spacing on a structural design that considers the ties’ performance and the acting loads, so the plan says «calculation required» with nets or sheets, which add wind load. KOSHA Guide D-C-7-2026 (§7.4.2 (4)) asks for an expert’s safety check when a system scaffold is 31 m high or more. The height flag depends only on the top platform exceeding 30 m; if your scaffold is 31 m or more to the top of the standards, get the expert check whether or not the plan shows the flag. Check the tie pattern in the instructions of the maker whose material you use.
Bracing (diagonals)
Not yet sourced: ScaFix does not have the manufacturer's bracing rule for this system. Check the bracing against the manufacturer's instructions before you order or build.
What bay lengths and depths does Korean system scaffold have?
Korean system scaffold is planned in ScaFix with 1.83 m, 1.52 m, 1.22 m and 0.91 m as bay lengths and 1.22 m, 0.91 m and 0.61 m as depths. Japanese frame scaffold shares this exact size set; on the example house the counts still differ (Japanese frame scaffold −289), as ScaFix applies system-specific rules to Korean system scaffold.
- System type
- Modular scaffold with rosettes
- Bay lengths · Depths
- 1.83 m, 1.52 m, 1.22 m, 0.91 m · 1.22 m, 0.91 m, 0.61 m
- Source
- 산업안전보건기준에 관한 규칙 제69조 제5호 (named in ScaFix’s catalogue; no checked PDF link yet)
- Source of bay lengths and depths
- ScaFix's general set for this system type, not one maker's tables. Check the bay lengths against your maker's documents.
- How ScaFix plans Korean system scaffold
- 1.9 m lifts; ties every 5 m vertically, every 3.66 m (2 × 1.83 m) / 4.57 m (3 × 1.52 m) / 4.88 m (4 × 1.22 m) along the wall (estimate); nodes every 0.48 m; diagonals at least one per 5 bays in every lift
How far apart are Korean system scaffold wall ties? (≈, not yet checked)
Korean system scaffold wall ties sit every 5 m in height and every ≈ 3.66 m along the wall with the 1.83 m bay. Rule: 산업안전보건기준에 관한 규칙 제69조 제5호 (벽 연결재: 제조사가 정한 기준). That is a regulation or standard, not the manufacturer’s manual; check the tie pattern in the manufacturer’s instructions. Estimate – no manufacturer rule on file; follow the supplier's manual.
| Bay length | Bays between ties | Tie spacing along the wall |
|---|---|---|
| 1.83 m | 2 | ≈ 3.66 m |
| 1.52 m | 3 | ≈ 4.57 m |
| 1.22 m | 4 | ≈ 4.88 m |
| 0.91 m | 5 | ≈ 4.57 m |
How each system's tie rule was checked, with its source: verification status of all systems.
Good to know
Korea's system scaffold (시스템비계), a type several makers build. Korean law leaves the tie spacing to the manufacturer and ScaFix has no manufacturer rule, so it plans the fallback of KCS 21 60 10 : 2025. The widths and the 475 mm node pitch are derived from suppliers' part lists, not printed.
With nets or sheets, and above a top platform of 30 m, the plan says calculation required.
Sources for Korean system scaffold
Tie rule for Korean system scaffold: 산업안전보건기준에 관한 규칙 제69조 제5호 (벽 연결재: 제조사가 정한 기준). ScaFix is a planning tool, not a structural approval.
- 산업안전보건기준에 관한 규칙 · 국가법령정보센터 (법제처) · 시행 2026. 3. 2. · KO · link checked 11 Nov 2026
- KCS 21 60 10 비계 · 국가건설기준센터 (KCSC) · KCS 21 60 10 : 2025 · KO · link checked 11 Nov 2026
Close-ups from the 3D model


The example house with Korean system scaffold
| Wall | Length | Height | Bays |
|---|---|---|---|
| Wall 1 + 3 | 11.4 m | 4.5 m | 1 × 0.91 m + 3 × 1.83 m + 4 × 1.52 m |
| Wall 2 + 4 (gable) | 5.3 m | 6 m | 1 × 0.91 m + 3 × 1.83 m |
What is on the Korean system scaffold parts list for the example house?
For the example house, Korean system scaffold needs 811 parts, planned 0.91 m deep with ladder access and decks at 2.2 m, 4.1 m and 6 m. Most pieces fall in ledgers and beams (236), frames and standards (176) and guardrails (148).
| Part | Length | Count |
|---|---|---|
| Frames and standards | ||
| Standards | 1.9 m | 120 |
| Standards | 1 m | 56 |
| Ledgers and beams | ||
| Ledgers | 1.83 m | 76 |
| Ledgers | 1.52 m | 48 |
| Ledgers | 0.91 m | 24 |
| Transoms | 88 | |
| Decks | ||
| Decks without ladder | 1.83 m | 23 |
| Decks without ladder | 1.52 m | 16 |
| Decks without ladder | 0.91 m | 8 |
| Decks with ladder | 1.83 m | 4 |
| Guardrails | ||
| Front guardrails | 1.83 m | 76 |
| Front guardrails | 1.52 m | 48 |
| Front guardrails | 0.91 m | 24 |
| Toeboards | ||
| Toeboards | 1.83 m | 26 |
| Toeboards | 1.52 m | 16 |
| Toeboards | 0.91 m | 8 |
| Diagonals | ||
| Diagonals | 1.83 m | 6 |
| Diagonals | 1.52 m | 8 |
| Diagonals | 0.91 m | 8 |
| Ends | ||
| End guardrails | 12 | |
| Wall ties and fittings · estimate – no manufacturer rule on file; follow the supplier's manual | ||
| Wall ties | ≈30 (estimate) | |
| Wall-anchor fittings | ≈30 (estimate) | |
| Base jacks and legs | ||
| Base jacks / legs | 56 | |
Korean system scaffold (시스템비계) · Scaffold depth: 0.91 m · Decks at: 2.2 m, 4.1 m, 6 m · Decks with ladders · Parts in all: 811
Calculated with ScaFix, a scaffold planning app for browser and iPhone (115 scaffold systems from 57 manufacturers, checked 10 November 2026).
How does Korean system scaffold compare with similar systems?
Same house, same planning rules: Korean system scaffold takes 811 parts, against Layher Allround (515, −296), PERI UP (605, −206) and Plettac Contur (561, −250). The nearest count is PERI UP, 206 parts away; it is planned 0.75 m deep, Korean system scaffold 0.91 m deep.
| System | Bays on the long wall | Depth | Parts in all | Against Korean system scaffold |
|---|---|---|---|---|
| Korean system scaffold | 1 × 0.91 m + 3 × 1.83 m + 4 × 1.52 m | 0.91 m | 811 | this page |
| Layher Allround | 4 × 3.07 m | 0.73 m | 515 | -296 (-36%) |
| PERI UP | 1 × 0.75 m + 3 × 3 m + 1 × 2.5 m | 0.75 m | 605 | -206 (-25%) |
| Plettac Contur | 1 × 0.75 m + 3 × 3 m + 1 × 2.5 m | 0.74 m | 561 | -250 (-31%) |
Korean system scaffold against Layher Allround and PERI UP, family by family
Against Layher Allround (515 parts) on the example house, the Korean system scaffold list (811) has 116 more ledgers and beams, 80 more frames and standards and 76 more guardrails. Against PERI UP (605), it has 80 more ledgers and beams, 56 more frames and standards and 52 more guardrails.
The Layher Allround list has U-lift-off preventers (34), end toeboards (8) and right-angle couplers for wall ties (8), which the Korean system scaffold list does not. The PERI UP list has right-angle couplers for wall ties (32) and base collars (40), which the Korean system scaffold list does not.
How many parts does Korean system scaffold need per wall size?
Wall size drives the count for Korean system scaffold: 53 parts at 3.66 × 4 m, 732 at 18.29 × 12 m, 0.91 m deep. 6 of the 183 parts on the 7.32 × 6 m wall are ties (estimated), rising to 24 ties at 18.29 × 12 m.
| Wall (length × height) | Bays | Decked lifts | Frames and standards | Decks | Base jacks and legs | Wall ties and fittings | Parts in all |
|---|---|---|---|---|---|---|---|
| 3.66 × 4 m | 2 × 1.83 m | 1 | 12 | 3 | 6 | 4 | 53 |
| 7.32 × 6 m | 4 × 1.83 m | 3 | 40 | 13 | 10 | 12 | 183 |
| 10.97 × 8 m | 6 × 1.83 m | 4 | 70 | 25 | 14 | 24 | 328 |
| 14.63 × 10 m | 8 × 1.83 m | 5 | 108 | 41 | 18 | 30 | 508 |
| 18.29 × 12 m | 10 × 1.83 m | 6 | 154 | 61 | 22 | 48 | 732 |
Korean system scaffold: technical data in ScaFix
| Item | Value in ScaFix | Document |
|---|---|---|
| Make-up frame heights | 0.95 m and 0.48 m | ScaFix catalogue |
| Node pitch on the standard | 0.48 m | ScaFix catalogue |
| First tie row, at most | 4 m | ScaFix setting (no clause) |
| Anchoring calculated above (top platform) | 30 m | ScaFix value from KOSHA GUIDE D-C-7-2026 §7.4.2 (4) (31 m) |
| Base jack the tie pattern assumes, at most | 0.4 m | 산업안전보건기준에 관한 규칙 제69조 제2호 «겹침길이는 받침철물 전체길이의 3분의 1 이상» (600 mm 받침철물: 세움 OK비계시스템 «최대 40cm 조절») |
How ScaFix builds Korean system scaffold: lifts, bottom rail, ties and access
- Net and tarpaulin. With a net on Korean system scaffold the manufacturer requires a calculation (KCS 21 60 10 : 2025 §3.3.5 (1) «벽 이음재의 성능과 작용하중을 고려한 구조설계에 따르며»). With a tarpaulin on Korean system scaffold the manufacturer requires a calculation (KCS 21 60 10 : 2025 §3.3.5 (1) «벽 이음재의 성능과 작용하중을 고려한 구조설계에 따르며»).
- Limits. The Korean system scaffold tie pattern assumes a base jack of at most 0.4 m (산업안전보건기준에 관한 규칙 제69조 제2호 «겹침길이는 받침철물 전체길이의 3분의 1 이상» (600 mm 받침철물: 세움 OK비계시스템 «최대 40cm 조절»)).
- Notices in the editor. This entry rests on two Korean suppliers' tables, not on a maker's catalogue: the 1.9 m lift follows from the brace table, while the widths (0.914 / 1.219 / 0.61 m), the 475 mm node pitch and the number of boards per width are derived, and the top-level posts are listed as 1.0 m standards where the tables list 950 mm. Check every part against the supplier's own list before ordering.
Korean system scaffold on a 12 m × 6 m wall: pieces and estimated weight
| Part group | Pieces | Estimated weight |
|---|---|---|
| Frames and standards | 64 | 542 kg |
| Ledgers and beams | 88 | 512 kg |
| Decks | 22 | 279 kg |
| Guardrails | 56 | 400 kg |
| Toeboards | 21 | 68 kg |
| Diagonals | 9 | 71 kg |
| Ends | 6 | 24 kg |
| Wall ties and fittings | 16 | 22 kg |
| Base jacks and legs | 16 | 58 kg |
| In all | 298 | 1976 kg |
Documents behind the Korean system scaffold rules in ScaFix
| Used for | Document and passage |
|---|---|
| Wall-tie rule | 산업안전보건기준에 관한 규칙 제69조 제5호 (벽 연결재: 제조사가 정한 기준) |
| Ties behind a net · Ties under a tarpaulin | KCS 21 60 10 : 2025 §3.3.5 (1) «벽 이음재의 성능과 작용하중을 고려한 구조설계에 따르며» |
Compare Korean system scaffold
Closest to Korean system scaffold by type and longest bay in ScaFix’s catalogue: Disk-lock Type B (China) (same type, longest bay 1.8 m), CETA Multiceta (same type, longest bay 2.5 m) and Pilosio MP (same type, longest bay 2.5 m).
Pick Korean system scaffold if…
- space along the wall is tight: Korean system scaffold comes as narrow as 0.61 m.
- you build in lifts of 1.9 m: that is this system’s lift height in ScaFix, against 2 m for most systems.
Other scaffolds for sites in Japan, China and Korea
ScaFix has a page of its own, with bay lengths, widths and the parts list, for these scaffolds used on sites in Japan, China and Korea: beside this one, the Japanese frame scaffold (枠組足場), the Japanese wedge scaffold, B and A type (くさび緊結式足場), China’s tube-and-coupler scaffold to JGJ 130-2011 (扣件式钢管脚手架), China’s cup-lock scaffold to JGJ 166-2016 (碗扣式钢管脚手架) and the Chinese disk-lock scaffold, Type B. Each page names the standard or source its set-up was taken from.