MJ UNI TOP 65 scaffold: bay lengths, depths and parts list

MJ UNI TOP 65 has bay lengths of 1.5–3 m and a depth of 0.65 m in ScaFix. Enter your walls, and ScaFix draws the MJ UNI TOP 65 scaffold in 3D and works out its parts list. Below is our example house with MJ UNI TOP 65. Any other size: Scaffold calculator.

· How the numbers are computed ·

MJ UNI TOP 65 scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
MJ UNI TOP 65 around the example house, as ScaFix draws it in 3D.

How many parts does MJ UNI TOP 65 need for a house?

ScaFix plans MJ UNI TOP 65 with the bay lengths 3 m, 2.5 m, 2 m and 1.5 m and scaffold depth 0.65 m. On ScaFix’s 11.4 m × 5.3 m example house, scaffolded all round, MJ UNI TOP 65 needs 288 parts; Jamax needs 268 on the same house.

MJ UNI TOP 65 in ScaFix

Manufacturer · System type
MJ-Gerüst · Frame scaffold (facade scaffold)
Variants in the system picker
MJ UNI TOP 65
Bay lengths · Depths
3 m, 2.5 m, 2 m, 1.5 m · 0.65 m
Source of bay lengths and depths
Depth: DIBt Z-8.1-902 (read 23 October 2026); ScaFix has no page reference for the bay lengths yet.
Source of the tie rule
DIBt Z-8.1-902 MJ UNI TOP 65 (18.08.2026 – 18.08.2031) Anlage B §B.5 a–c (p. 198)
How ScaFix plans MJ UNI TOP 65
2 m lifts; ties every 4 m vertically, every 6 m (2 × 3 m) / 5 m (2 × 2.5 m) / 4 m (2 × 2 m) along the wall; diagonals at least one per 5 bays in every lift

Wall-tie spacing along the wall for MJ UNI TOP 65

ScaFix ties MJ UNI TOP 65 every 4 m in height. Along the wall a tie sits on a standard, so the spacing is always a whole number of bays: for a wall built from one bay length, the table shows how many bays lie between two tied standards and the spacing that gives. Rule: DIBt Z-8.1-902 MJ UNI TOP 65 (18.08.2026 – 18.08.2031) Anlage B §B.5 a–c (p. 198). ScaFix is a planning tool, not a structural approval.

Wall-tie spacing along the wall for each bay length of MJ UNI TOP 65 in ScaFix
Bay lengthBays between tiesTie spacing along the wall
3 m26 m
2.5 m25 m
2 m24 m
1.5 m23 m

Sources for MJ UNI TOP 65

Tie rule for MJ UNI TOP 65: DIBt Z-8.1-902 MJ UNI TOP 65 (18.08.2026 – 18.08.2031) Anlage B §B.5 a–c (p. 198). DIBt Z-8.1-902 MJ UNI TOP 65 (18.08.2026 – 18.08.2031) can be looked up by its number in the DIBt approval database. ScaFix is a planning tool, not a structural approval.

  1. dibt.de/en/service/approval-download/search

Close-ups from the 3D model

The example house with MJ UNI TOP 65

The walls of the example house with MJ UNI TOP 65
WallLengthHeightBays
Wall 1 + 311.4 m4.5 m1 × 1.5 m + 3 × 3 m + 1 × 2.5 m
Wall 2 + 4 (gable)5.3 m6 m1 × 1.5 m + 1 × 3 m + 1 × 2.5 m

The parts list for the example house with MJ UNI TOP 65

The parts list for the example house with MJ UNI TOP 65
PartLengthCount
Frames and standards
Frames2 m40
Frames1 m4
Top-lift guardrail posts16
Decks
Decks without ladder3 m14
Decks without ladder2.5 m8
Decks without ladder1.5 m8
Decks with ladder3 m2
Guardrails
Front guardrails3 m24
Front guardrails2.5 m12
Front guardrails1.5 m12
Toeboards
Toeboards3 m16
Toeboards2.5 m8
Toeboards1.5 m8
Diagonals
Diagonals1.5 m8
Ends
End guardrails8
Wall ties and fittings
Wall ties30
Wall-anchor fittings30
Base jacks and legs
Base jacks / legs40

MJ UNI TOP 65 · Scaffold depth: 0.65 m · Decks at: 2.5 m, 4.5 m · Decks with ladders · Parts in all: 288

MJ UNI TOP 65 compared with similar systems on the same house

The example house with MJ UNI TOP 65 and similar systems
SystemBays on the long wallDepthParts in allAgainst MJ UNI TOP 65
MJ UNI TOP 651 × 1.5 m + 3 × 3 m + 1 × 2.5 m0.65 m288this page
Jamax4 × 3 m0.68 m268-20 (-7%)
Layher Blitz4 × 3.07 m0.73 m308+20 (+7%)
Plettac SL 70/1001 × 1.5 m + 3 × 3 m + 1 × 2.5 m0.73 m316+28 (+10%)

MJ UNI TOP 65: parts by wall size

Scaffold depth 0.65 m, access: decks with ladders. Each wall is a whole number of 3 m bays, so the scaffold covers it exactly.

Parts by wall size with MJ UNI TOP 65
Wall (length × height)BaysDecked liftsFrames and standardsDecksBase jacks and legsWall ties and fittingsParts in all
6 × 4 m2 × 3 m1626629
12 × 6 m4 × 3 m2158101877
18 × 8 m6 × 3 m328181424138
24 × 10 m8 × 3 m445321844227
30 × 12 m10 × 3 m566502252320

Pick MJ UNI TOP 65 if…

  • space along the wall is tight: MJ UNI TOP 65 comes as narrow as 0.65 m.

Questions about MJ UNI TOP 65

How many parts does MJ UNI TOP 65 need for a 12 m × 6 m wall?

A 12 m long, 6 m high wall with MJ UNI TOP 65 (4 × 3 m) needs 77 parts according to ScaFix: 15 frames and standards, 8 decks, 10 base jacks and legs and 18 wall ties and fittings, with decks on 2 lifts. A 30 m wall 12 m high needs 320.