Scaffolding regulations by country: nine countries compared
Every country agrees that a scaffold needs edge protection, a competent erector and an inspection before use. They disagree on the numbers: the height at which rules start, how tall the guardrail is, how often someone checks, and what paper the erector must hold. This comparison puts those numbers side by side for Norway, Sweden, Denmark, Germany, the UK, the US, Poland, the Netherlands and France, each with its primary source.
By Ole Emil Frikstad Urstad · How the numbers are computed ·

How do scaffolding regulations differ between countries?
Principles match; numbers differ. Guardrails range from 950 mm in the UK and Sweden to 1.1 m in Poland (WAHR Sch. 2; AFS 2023:11; Dz.U. 2003 § 15). Inspection runs from every US work shift and daily in France to every 7 days in the UK and monthly in Poland, with France adding a full check every three months.
How do the scaffolding rules compare in one table?
The table condenses each country's main rule. The sections below give the clause and a link to the primary text. The last column names the first step a firm from abroad must take; a dash means this guide does not cover posting for that country.
| Country | Main regulation | Standard or design basis | Who may erect | Inspection rule | Guardrail height | Training or certification | Before a foreign crew starts |
|---|---|---|---|---|---|---|---|
| Norway | Forskrift om utførelse av arbeid, chapter 17 | Manufacturer documentation; Arbeidstilsynet cites NS-EN 12811-1 | Workers trained to the height band | Before use, at regular intervals, after bad weather, after a week or more out of use (§ 17-9) | At least 1 m; 0.95 m allowed on system scaffolds; toe board 0.15 m | 7.5 + 7.5 h (2–5 m), 15 + 15 h (5–9 m), 36 + 72 h (from 9 m) | HMS card per worker; contract reported to the tax authority (§ 7-6) |
| Sweden | AFS 2023:11, chapter 8 | SS-EN 12811-1, type certificates or design | Workers with the training level in Annex 6 | Erector checks and documents when ready; user checks before use and continuously | Required from 2 m fall; 950 mm absolute minimum per SS-EN 12811-1 | Four levels: up to 2 m, 5 m, 9 m, above 9 m | Posting report + contact person in Sweden |
| Denmark | BEK nr. 428 of 5 April 2022 (technical equipment) | Supplier's instructions; calculation outside standard set-up | Over 3 m: holder of a training certificate | By a person with scaffold experience; sign updated after each check | Handrail 1 m, knee rail 0.5 m, toe board 15 cm | Certificate above 3 m; thorough instruction up to 3 m | RUT notification; recognition above 3 m |
| Germany | BetrSichV Annex 1 no. 3, TRBS 2121 Part 1 | DIN EN 12810, DIN EN 12811, DIN 4420-1, DIBt approval | Registered scaffolding firm for third parties since July 2024; competent supervisor | Qualified person after erection, after alterations and after storms; user check before use | Top rail 1.00 m, gaps up to 0.47 m, toe board 0.15 m (BG BAU) | Competent person supervises, qualified person (TRBS 1203) inspects | Customs registration (§ 16 MiLoG) |
| United Kingdom | Work at Height Regulations 2005 | TG20:21 or bespoke design | Competent scaffolders; trainees supervised | Before first use, then at most every 7 days, and after high winds | Top guard-rail at least 950 mm, gaps up to 470 mm | Competence often shown through CISRS | – |
| United States | 29 CFR 1926 Subpart L | Subpart L itself | Under a competent person's supervision | Competent person before each work shift | 38 to 45 in (0.97 to 1.2 m) on supported scaffolds since 2000 | Training by a qualified or competent person (1926.454) | – |
| Poland | Dz.U. 2003 No. 47 item 401, chapter 8 | PN-EN 12810-1, PN-EN 12811-1 | Holder of the scaffolder permit | After strong wind, rain, breaks over 10 days, and at least monthly | Top rail 1.1 m (1 m on system scaffolds), toe board 0.15 m | Test before a Łukasiewicz – WIT commission | Statement to PIP by day one (art. 24) |
| Netherlands | Arbobesluit art. 7.23b and 7.34 | Standard configuration or calculation; Richtlijn Steigers | Under a competent person, by specifically trained workers | Before use, after every change, after disuse, after abnormal weather | Protection up to at least 1 m; fall risk from 2.5 m | Specific training on the six topics in art. 7.23b(9) | – |
| France | Code du travail R4323-69 to R4323-80 | NF EN 12810, NF EN 12811 | Under a competent person, by specifically trained workers | Before (re)commissioning, daily, and at most every 3 months | 1 m to 1.10 m, mid rail, toe board 10 to 15 cm | Training in R4323-69; Cnam recommendation R408 as reference | – |
What stands out in each country's own rules?
The country guides carry the clause tables. Here is the one point per country that matters most when you compare:
- Norway: the guardrail is not in the scaffold chapter at all. Chapter 17 of forskrift om utførelse av arbeid sets the training hours, while the rail heights sit in arbeidsplassforskriften § 2-22. See scaffolding rules in Norway.
- Sweden: since 1 January 2025 the rules sit in AFS 2023:11, chapter 8 (adopted in 2023), and section 24 adds a penalty fee for each worker without written proof of training. See scaffolding rules in Sweden.
- Denmark: the certificate threshold sits at 3 m, a metre above Norway's training threshold, and every fixed scaffold above 2 m carries a sign with its erector and last inspection date (BEK nr. 428 §§ 95–98). See scaffolding rules in Denmark.
- Germany: the system approval itself is a site document; a DIBt decision must be available where the scaffold stands, and the BG BAU module B 100 gives the 1.00 m rail. See scaffolding rules in Germany.
- United Kingdom: the statute fixes no toe-board height; Schedule 2 says only "suitable and sufficient", and HSE points to TG20 or a bespoke design for the hardware. See UK scaffolding regulations and TG20.
- United States: it inspects at every work shift, as often as France's daily check, and starts scaffold fall protection only above 10 feet (3.1 m) under 1926.451(g)(1), higher than any European threshold here. Training is split by role in 1926.454. See OSHA scaffolding requirements.
- Poland: the permit to erect comes from a separate machinery regulation, the 2001 regulation, with a test before a Łukasiewicz – WIT commission, while the 2003 regulation sets the 1.1 m rail and the monthly check. See scaffolding rules in Poland.

Netherlands: the Arbobesluit
The Dutch Working Conditions Decree (Arbobesluit) defines fall risk in article 3.16 as a risk of falling 2.5 m or more, or less where openings or other risk-raising circumstances exist, and treats railings as effective when they protect up to at least 1 m above the work surface. Article 7.23b is the scaffold article: a strength and stability calculation unless the scaffold follows a generally recognised standard configuration, an erection, dismantling and alteration scheme drawn up by a competent person, and erection only under a competent person's lead by workers with adequate, specific training on six listed topics, from reading the scheme to permitted loads. Article 7.34 adds the site inspection by an expert person before use, after every change, after a period of disuse and after abnormal weather. In practice the industry works to the Richtlijn Steigers; the construction-sector body Volandis publishes an A-sheet on scaffold building that forms one whole with that guideline.
France: Code du travail R4323-69 to R4323-80
France writes its scaffold rules into the Labour Code. Article R4323-69 allows scaffolds to be erected, dismantled or significantly altered only under the direction of a competent person, by workers with adequate and specific training covering the erection plan, fall prevention, weather and permitted loads. R4323-77 puts collective protection on the outer sides as defined in R4323-59: a guardrail between 1 m and 1.10 m, a toe board of 10 to 15 cm and a mid rail at half height. According to INRS, the arrêté of 21 December 2004 adds three checks: before first use or reuse, daily, and of the scaffold's state of preservation at most every three months. The Cnam recommendation R408 for base-supported scaffolds is not a regulation but a competence reference that INRS uses for designers, erectors, inspectors and users; R457 does the same for mobile towers.
What do the numbers mean for a planner working across borders?
Three patterns stand out once the rules are side by side. For why the rules exist at all, see what the fall statistics show.
- Guardrail height is not interchangeable. A system rail that sits at 950 mm meets the UK and Swedish minimum and the Norwegian system-scaffold allowance, but not the 1.1 m Polish default or the 1 m Danish handrail. Always check the rail height in the system's instructions against the country of use. The glossary entries on the guardrail and toe board explain the parts.
- Inspection intervals range from one shift to three months. A site schedule built for a 7-day UK cycle under-inspects in the US and over-inspects in France. The practical overlap is the trigger list: before first use, after alterations, after storms. Our scaffold inspection checklist gives a bottom-to-top routine that fits all of them.
- Training rules follow height in the Nordics. Norway, Sweden and Denmark set height bands in the regulation itself, and Poland requires a test for metal scaffolds of any height. Germany, the Netherlands, France, the UK and the US describe competence by role: who supervises, who inspects and what the training must cover.
Load classes, by contrast, are shared wherever EN 12811-1 is used; see scaffold load classes.
How ScaFix fits in
ScaFix counts guardrails, toe boards and access bays per lift on many systems, so you can see what a 1 m or 1.1 m rail rule adds to the order before material ships; the methodology explains the model.
This comparison is planning information, not structural approval and not legal advice. In each country the regulator and the text linked above decide (Arbeidstilsynet, Arbetsmiljöverket, Arbejdstilsynet, the BG BAU and the Länder, HSE, OSHA, PIP, the Dutch Labour Inspectorate and the French Labour Code), together with the manufacturer's assembly instructions, and a competent person inspects before use. Check the current text before you rely on it.
Frequently asked questions
What is the minimum scaffold guardrail height in Europe?
There is no single European figure in law. The UK and Sweden accept 950 mm, Norway asks for 1 m (0.95 m on system scaffolds), Denmark and Germany use 1 m, France 1 m to 1.10 m, and Poland 1.1 m, or 1 m on system scaffolds.
Which country inspects scaffolds most often?
The United States and France. OSHA requires a competent person to inspect before each work shift, and France checks daily plus a full check at most every three months. The UK interval is 7 days and Poland at least monthly.
Do I need a scaffolding licence to work abroad?
It depends on the country. Norway, Sweden, Denmark and Poland tie mandatory training or certificates to scaffold height or type, while the UK, US, Germany, the Netherlands and France write competence and supervision duties into their rules by role.
Is EN 12811 mandatory?
Not as such in most countries, but national rules point to it: Sweden's general advice cites SS-EN 12811-1, Germany's system approvals refer to DIN EN 12811-1, and INRS names NF EN 12811-1 for assessing fixed scaffolds in France.
At what height do scaffold fall rules start?
Commonly at 2 m: Norway, Sweden and German construction sites use 2 m for ordinary workplaces. The Netherlands uses 2.5 m, Poland 1 m, the US 10 feet (3.1 m), and Denmark relaxes knee rails and toe boards below 2 m.
Sources
Primary sources used for this article, with the date each was read.
- Lovdata: forskrift om utførelse av arbeid, kapittel 17 Arbeid i høyden (read 23 October 2026)
- Arbeidstilsynet: HMS-kort (read 23 October 2026)
- Lovdata: skatteforvaltningsloven § 7-6 Oppdragstakere og arbeidstakere (read 23 October 2026)
- Swedish Work Environment Authority: Contact person when posting workers to Sweden (read 23 October 2026)
- Workplace Denmark: Register of Foreign Service Providers (RUT) (read 23 October 2026)
- Workplace Denmark: Recognition of qualifications (read 23 October 2026)
- Mindestlohngesetz § 16 Meldepflicht (gesetze-im-internet.de) (read 23 October 2026)
- Ustawa o delegowaniu pracowników, Dz.U. 2025 poz. 1682 (ELI, pdf) (read 23 October 2026)
- Lovdata: arbeidsplassforskriften § 2-22 Utforming av rekkverk (read 23 October 2026)
- Arbeidstilsynet: Montering og bruk av stillas (read 23 October 2026)
- Arbetsmiljöverket: AFS 2023:11, kap. 8 och bilaga 6 (pdf) (read 23 October 2026)
- Arbetsmiljöverket: Ställningar (read 23 October 2026)
- Retsinformation: BEK nr. 428 af 05/04/2022 om anvendelse af tekniske hjælpemidler (pdf) (read 23 October 2026)
- Betriebssicherheitsverordnung, Anhang 1 (gesetze-im-internet.de) (read 23 October 2026)
- TRBS 2121 Teil 1, Abschnitt 4 Schutzmaßnahmen (BGN-Branchenwissen) (read 23 October 2026)
- TRBS 2121 Teil 1, Abschnitt 5 Prüfung (BGN-Branchenwissen) (read 23 October 2026)
- BG BAU: Baustein-Merkheft Gerüstbau, Stand 07/2021 (pdf) (read 23 October 2026)
- The Work at Height Regulations 2005, Schedule 2 (read 23 October 2026)
- HSE: Scaffolding (read 23 October 2026)
- 29 CFR 1926.451, General requirements for scaffolds (Cornell LII) (read 23 October 2026)
- 29 CFR 1926.454, Training requirements (Cornell LII) (read 23 October 2026)
- Dz.U. 2003 nr 47 poz. 401: rozporządzenie w sprawie bhp podczas wykonywania robót budowlanych (ELI, pdf) (read 23 October 2026)
- Dz.U. 2001 nr 118 poz. 1263: rozporządzenie w sprawie bhp podczas eksploatacji maszyn do robót budowlanych (ELI, pdf) (read 23 October 2026)
- Wetten.overheid.nl: Arbeidsomstandighedenbesluit, art. 3.16, 7.23b en 7.34 (read 23 October 2026)
- Volandis: A-blad Steigerbouwen (pdf) (read 23 October 2026)
- Code du travail numérique: article R4323-59 (read 23 October 2026)
- Code du travail numérique: article R4323-69 (read 23 October 2026)
- Code du travail numérique: article R4323-77 (read 23 October 2026)
- INRS: Réglementation sur le travail en hauteur (read 23 October 2026)
- INRS: Échafaudages et plateformes individuelles (read 23 October 2026)