Taking a scaffold job in Poland: posting duties, permits and the 2003 regulation
A foreign firm on a Polish site answers to two regimes: the posting act, which starts on the first day of the service, and the construction safety regulations, which decide how the scaffold is built and who may build it. This guide gives the Polish terms and the paragraph behind each duty.
By Ole Emil Frikstad Urstad · How the numbers are computed ·

What are the scaffolding regulations in Poland?
Poland regulates scaffolds through the 2003 construction safety regulation (Dz.U. 2003 No. 47 item 401): a top rail at 1.1 m (1 m on system scaffolds) with a 0.15 m toe board, fall protection from 1 m, and formal acceptance before use. Erectors need a Polish permit, and a foreign employer must file a posting statement with PIP.
Which Polish terms will you meet?
| Polish | English | Where it comes from |
|---|---|---|
| rusztowanie systemowe | system scaffold with fixed grid dimensions | 2003 regulation, definitions |
| kierownik budowy | site manager | Building Law, art. 22 |
| odbiór rusztowania | formal acceptance before use | 2003 regulation, § 110 |
| dziennik budowy | the site log book | Building Law |
| plan BIOZ | site health and safety plan | Building Law, art. 21a |
| książka operatora | operator's record card proving a permit | 2001 regulation, § 26 |
| DTR / instrukcja producenta | manufacturer's technical and operating documentation | 2001 and 2003 regulations |
| balustrada, poręcz, krawężnik | guardrail system, top rail, toe board | 2003 regulation, § 15 |
| strefa niebezpieczna | exclusion zone below the work | 2003 regulation, §§ 20–21 |
| PIP | National Labour Inspectorate |
What must a foreign employer file before the crew starts?
The posting act of 10 June 2016 (consolidated text Dz.U. 2025 item 1682) sets three duties for an employer posting workers to Poland:
- A statement to the PIP, the National Labour Inspectorate, no later than the day the service starts (art. 24(3)). It lists the employer, the expected number of posted workers with names, dates of birth and nationality, the start and end dates, the work addresses, the nature of the service, the contact person and where the documents are kept. It may be filed in Polish or English (art. 24(6)), and changes to the employer, contact person or document location must be notified within 7 working days (art. 24(5)).
- A contact person in Poland for the whole posting, who deals with the PIP and sends and receives documents (art. 24(1)).
- Documents kept in Poland on paper or electronically: the employment contract, records of working time and the pay documents (art. 25(1)). On a PIP request they must be produced with a Polish translation within 5 working days (art. 25(2)), and for 2 years after the posting ends within 15 working days (art. 25(3)).
None of this replaces the site rules below.

Which laws apply to scaffolds in Poland?
- The regulation on health and safety during construction work of 6 February 2003 (Dz.U. 2003 No. 47 item 401). Chapter 8, §§ 108 to 132, covers scaffolds and mobile work platforms. The Sejm database lists it as in force.
- The regulation of 20 September 2001 on health and safety when operating machinery and equipment for earthworks, construction and road works (Dz.U. 2001 No. 118 item 1263). It is still in force, amended in 2017, 2020 and 2023, and it is where the scaffolder permit lives.
- The Building Law of 7 July 1994, consolidated text Dz.U. 2026 item 524, for the site manager and the BIOZ plan.
- The Polish versions of the European standards, and the manufacturer's documentation or an individual design.
What does the 2003 regulation require on site?
The rules a planner meets first:
| Topic | Rule | Paragraph |
|---|---|---|
| Order of protection | Collective protection (guardrails, safety nets) first; harnesses only where that is not possible | § 6 |
| Height threshold | Workplaces at 1 m or more above floor or ground are protected against falls, including walkways and access | § 133 |
| Guardrail | Toe board 0.15 m, top rail at 1.1 m, gap between them filled; system scaffolds may have the top rail at 1 m | § 15(2) and (3) |
| Documents | Built to the manufacturer's documentation or an individual design | § 108 |
| Public roads | Approval of the road authority and measures from the traffic plan; fans and netting next to streets, nets do not replace guardrails | §§ 118–119 |
| Exclusion zone | Fenced before erection and dismantling; at least 1/10 of the height objects can fall from, and not less than 6 m | § 120(2), § 21(2) |
| Erectors | Use fall protection devices while erecting and dismantling | § 120(1) |
| Power lines | Work only outside the danger zone, otherwise the line is switched off | § 122 |
| Lifting arms | Hoist on a bracket fixed to the scaffold: capacity no more than 1.5 kN | § 116 |
| Dismantling | No throwing components down | § 125 |
| Mobile towers | Level, firm, drained route with no more than 1% slope; secured at two points at least; never moved with people on | §§ 130–132 |
The 2001 regulation adds a weather rule in § 22(2): no erection or dismantling in poor visibility without lighting, in rain or snow, on black ice, or in storms and wind above 10 m/s. Acceptance (odbiór), the seven items of the acceptance record and the monthly checks are covered in our scaffold inspection checklist.
The same thresholds in eight other countries are compared in scaffolding regulations by country.
Who may erect scaffolding in Poland?
§ 109 of the 2003 regulation says only that people erecting and dismantling scaffolds must hold "the required permits". The 2001 regulation fills that in. Its Annex 1 lists "metal construction and assembly scaffolds" with the scope "erection", without classes. Under § 23, as worded since 1 January 2023, such equipment may only be handled by people who completed training and passed a test before a commission appointed by the Łukasiewicz Research Network – Warsaw Institute of Technology. Before that date the commission came from the Institute of Construction Mechanisation and Rock Mining (IMBiGS). Training has a theory part and a practical part (§ 24), and a pass gives a certificate and an entry in the operator's book (§ 26).
The amending regulation of 8 February 2023 also replaced the operator's book with a plastic ID-1 card, and it keeps permits obtained earlier valid. The regulation names only the Łukasiewicz – WIT commission; a foreign certificate is not listed as an equivalent. A foreign erector should therefore plan for the Polish training and test before the job.
The language point is practical rather than written: § 2 of the 2003 regulation makes the contractor prepare a safe work instruction before work starts and acquaint the workers with it, and it names no language, so agree with the main contractor which language the instruction and the site briefings will use.
What a Polish scaffolder permit is not: a UDT (technical inspection office) licence. Scaffolds are absent from the 2012 list of technical equipment under technical supervision, which does include mobile work platforms.
What do the site manager and the client have to do?
Article 21a of the Building Law requires the site manager to prepare a BIOZ plan before work starts if any high-risk work from its paragraph 2 takes place, or if the work lasts more than 30 working days with at least 20 workers at once, or exceeds 500 person-days. The BIOZ regulation (§ 6) names work with a fall risk from more than 5.0 m, a height many facade scaffolds reach. Article 22 makes the site manager coordinate safety measures and stop work where a hazard may arise. Separately, § 3 of the 2003 regulation makes the investor notify the labour inspector 7 days before construction starts on sites above the same 30-day / 20-person / 500-person-day thresholds.
Which standards apply?
The Polish editions are PN-EN 12810-1:2010 and PN-EN 12811-1:2007, both in the certification scope of Łukasiewicz – WIT. Load and width classes are explained in scaffold load classes.
What does the labour inspectorate find?
In 2022 the PIP carried out 2,311 inspections on small construction sites at 2,150 firms, and 91% of the irregularities it found concerned work involving scaffolds. The recurring defects were missing or faulty guardrails, missing, incomplete or improvised decks, missing access towers, missing or weak ties, and scaffolds standing on soft ground, boards, bricks or aerated concrete blocks.
How ScaFix fits in
ScaFix places the § 15 rails and toe boards and the access bays on every lift of a Polish job in many scaffold systems, but the § 110 acceptance stays with the site manager (methodology).
Planning information based on the Polish regulations published in the Journal of Laws (ISAP/ELI) and the posting act, not legal advice or a structural approval. The manufacturer's documentation or an individual design and the Polish text decide how a scaffold is built, and the site manager or an authorised person must accept it under § 110 before anyone uses it.
Frequently asked questions
Do I have to notify PIP when posting scaffolders to Poland?
Yes. The posting act requires a statement to the National Labour Inspectorate no later than the day the service starts, in Polish or English, naming the workers, the sites and a contact person in Poland.
Do I need a permit to erect scaffolding in Poland?
Yes, for metal construction scaffolds. The 2001 regulation requires training and a passed test before a commission of the Łukasiewicz – Warsaw Institute of Technology; a foreign certificate is not listed as an equivalent.
What guardrail height does Poland require?
A top rail at 1.1 m with a 0.15 m toe board and the space between filled in (§ 15(2)). On system scaffolds the top rail may sit at 1 m (§ 15(3)).
Is a scaffold subject to UDT inspection in Poland?
No. Scaffolds are not on the list of equipment under technical supervision; mobile work platforms are.
Who accepts a scaffold before use in Poland?
The site manager (kierownik budowy) or an authorised person, recorded in the site log book or a technical acceptance record under § 110 of the 2003 regulation.
How large is the exclusion zone around scaffold erection?
At least one tenth of the height from which objects can fall and never less than 6 m, fenced before erection or dismantling starts.
Sources
Primary sources used for this article, with the date each was read.
- Ustawa z 10 czerwca 2016 r. o delegowaniu pracowników w ramach świadczenia usług, tekst jednolity Dz.U. 2025 poz. 1682 (ELI, pdf) (read 23 October 2026)
- Rozporządzenie Ministra Infrastruktury z 6 lutego 2003 r. w sprawie bhp podczas wykonywania robót budowlanych, Dz.U. 2003 nr 47 poz. 401 (ELI, pdf) (read 23 October 2026)
- Sejm ELI API: status aktu Dz.U. 2003 poz. 401 (read 23 October 2026)
- Rozporządzenie Ministra Gospodarki z 20 września 2001 r. w sprawie bhp podczas eksploatacji maszyn i innych urządzeń technicznych do robót ziemnych, budowlanych i drogowych, Dz.U. 2001 nr 118 poz. 1263 (ELI, pdf) (read 23 October 2026)
- Sejm ELI API: status aktu Dz.U. 2001 nr 118 poz. 1263 i akty zmieniające (read 23 October 2026)
- Rozporządzenie Ministra Rozwoju i Technologii z 8 lutego 2023 r., Dz.U. 2023 poz. 291 (ELI, pdf) (read 23 October 2026)
- Ustawa z 7 lipca 1994 r. Prawo budowlane, tekst jednolity Dz.U. 2026 poz. 524 (ELI, pdf) (read 23 October 2026)
- Rozporządzenie Ministra Infrastruktury z 23 czerwca 2003 r. w sprawie informacji dotyczącej bioz oraz planu bioz, Dz.U. 2003 nr 120 poz. 1126 (ELI, pdf) (read 23 October 2026)
- Rozporządzenie Rady Ministrów z 7 grudnia 2012 r. w sprawie rodzajów urządzeń technicznych podlegających dozorowi technicznemu, Dz.U. 2012 poz. 1468 (ELI, pdf) (read 23 October 2026)
- Sieć Badawcza Łukasiewicz – WIT: Wykaz norm do zakresu akredytacji AC 002 (pdf) (read 23 October 2026)
- PIP, kampania Budowa. Stop wypadkom!: Kontrole na małych budowach – podsumowanie 2022 r. (read 23 October 2026)