Scaffolding rules in Ireland: the HSA code of practice and the regulations

In Ireland, a scaffold platform from which a worker could fall 2 m or more must have been inspected within the previous 7 days, and the report is kept for 5 years. Only CSCS-carded basic or advanced scaffolders erect it, and the HSA's code of practice, in force since 1 January 2019, sets out the detail.

· How the numbers are computed ·

Kwikstage scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Kwikstage around the example house, as ScaFix draws it in 3D.

Which rules apply to scaffolding in Ireland?

Two sets of regulations and one code apply: Part 4 of the General Application Regulations 2007 (S.I. No. 299 of 2007) for work at height, the Construction Regulations 2013 (S.I. No. 291 of 2013) for CSCS cards, and the Health and Safety Authority's Code of Practice for Access and Working Scaffolds, which explains both.

Before you rely on this guide

This guide summarises published rules to help you plan and is not legal advice. It has not been reviewed by a qualified scaffold designer or engineer. ScaFix is a planning aid, not structural approval: the manufacturer's instructions, the scaffold design and a competent person's inspection decide what is built and used on site. How these guides are written, sourced and corrected: editorial and review policy.

What is the HSA Code of Practice for Access and Working Scaffolds?

It is the Health and Safety Authority's guidance on the scaffold duties in the regulations, for erectors, contractors and users. It came into effect on 1 January 2019, replaced the 2009 code, and can be used as evidence in criminal proceedings, so a planner treats its figures as the yardstick an inspector will apply.

The HSA's page for the code lists it under the year 2018; the file served there today is dated March 2023 and runs to 104 pages. Its foreword (p. 1) says it covers Part 4 of the General Application Regulations 2007, regulations 94 to 119 on work at height, and the Construction Regulations 2013; p. 2 quotes section 61 of the 2005 Act: «the code of practice shall be admissible in evidence». This page covers the Republic of Ireland, not Northern Ireland.

When does an Irish scaffold need a design and calculations?

Strength and stability calculations are required unless a record of calculations for the arrangement exists or the scaffold is assembled to a generally recognised configuration. In practice that means the maker's design, a competent designer's design or TG20; anything outside those, such as a sheeted system scaffold, needs its own design.

That is regulation 107(b) of S.I. 299/2007; regulation 107(c) adds an assembly, use and dismantling plan drawn up by a competent person, scaled to the scaffold's complexity. The HSA code (section 2.3.2, pp. 23–24) asks the scaffolding contractor to name the system in use and hand over the maker's guidelines, and lists typical cases that may need design and calculations:

  • a sheeted system scaffold, or one exceeding the maker's height, tie spacing, loads, bay width or number of working lifts;
  • ties or anchors with a capacity under 6.1 kN (621 kg);
  • tube and fitting above 50 m unsheeted or 25 m sheeted;
  • bottom transoms or ledgers left out for a walkway, or a first tie line more than 4 m above the base.
Layher Allround scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Layher Allround around the example house, as ScaFix draws it in 3D.

Who may erect a scaffold in Ireland?

Only basic or advanced scaffolders trained and experienced in that kind of work, or trainees under the direct supervision of a competent scaffolder, may erect, substantially alter or dismantle a scaffold. The minimum is the Construction Skills Certification Scheme (CSCS) card for basic scaffolding, run by SOLAS, and the contractor must ask to see it.

The card duty is regulation 25 of the Construction Regulations 2013, whose Schedule 5 lists «Scaffolding — basic», «Scaffolding — advanced» and «Mobile tower scaffold»; the HSA's CSCS page names the same three. The code (section 7.1, pp. 65–67) splits the work: a basic scaffolder handles proprietary or system scaffolds and loading bays up to 7 m high, while sheeted system scaffolds, bespoke designs and loading bays over 7 m need an advanced scaffolder. Basic entry asks for age 16, nine months' experience, a Safe Pass card and the CSCS assessment.

How often must a scaffold be inspected in Ireland?

At least every 7 days (regulation 119): a construction working platform from which a worker could fall 2 m or more may not be used unless it was inspected in that position within the previous 7 days. The inspector reports within 24 hours, the report stays on site until the work ends, and the result is kept for 5 years.

Those figures are regulation 119 of S.I. 299/2007, and Schedule 5 lists the eight particulars every report holds, from the location and a description of the scaffold to the action taken and the name of the person reporting. The HSA code (section 5.4, p. 63) adds an inspection before first use and after any modification, a period without use, bad weather, damage or digging near the base, and suggests form GA3 (Appendix C), which the HSA says is not a statutory form.

DutyWhat it asksWhere it is written
InspectionWithin the previous 7 days for a platform with a fall of 2 m or moreS.I. 299/2007, reg. 119(1)(c)
ReportWithin 24 hours, kept on site, results kept 5 yearsreg. 119(2)–(4)
Guard-railTop rail at least 950 mm, no gap over 470 mmreg. 103(2)(d)
Toe-boardAt least 150 mmHSA code, p. 44
Gap to the buildingAt most 225 mmHSA code, p. 45
Ties on ledgersWithin 300 mm of a standardHSA code, p. 33

The table puts the figures a planner meets most often beside the text that sets them; the regulations bind, the code explains.

What goes into the handover to the user?

A good handover names the parts of the scaffold handed over, states the maximum load of the working platforms and loading bays and the tie spacing, inspects the whole scaffold, swaps «scaffold incomplete» notices for «scaffold complete» signs and records the inspection, for example on form GA3, with the person responsible for later changes.

That list is section 4 of the HSA code (p. 60), which calls a scaffold tag system «very beneficial» without making it law. Appendix B (p. 79) is a model «Handover of Scaffolding to User» certificate with the maximum load in kg per bay, the number of working platforms, and the type and spacing of ties and bracing, so that another competent person can inspect the scaffold during use.

What guard-rail, toe-board and tie figures apply?

The top guard-rail stands at least 950 mm above the edge (regulation 103), with no gap between rails or above the toe-board over 470 mm. The HSA code adds a toe-board of at least 150 mm, at most 225 mm between scaffold and building, and ledger ties within 300 mm of a standard.

The rail figures are law, in regulation 103(2)(d) of S.I. 299/2007; the other three are the HSA code (pp. 33, 44 and 45). For ties, the code tells a planner to follow the maker's characteristic tie pattern for a system scaffold unless calculations prove a variation safe (p. 38), to add ties when the scaffold is sheeted or netted, and not to let a 1.25 m wide scaffold rise more than 4 m above its highest tie line without a specific design (p. 33).

What does ScaFix plan for an Irish house elevation?

On a straight wall 12 m long and 9 m high in Layher Allround, ScaFix plans 4 bays and 4 decked levels, and counts 289 parts and 18 wall ties for it in the app, from the maker's own tie and bracing rules.

Layher's Irish company, Layher System Scaffolding Ltd in Ardee, Co. Louth, lists Allround on its site; PERI's Irish company in Dublin 12 offers the PERI UP facade scaffold (PERI Ireland). A wall like this one stands inside the maker's standard configuration only while it stays within the maker's limits: sheeting it, for instance, would move it into the code's design list above.

What does ScaFix do, and what not?

ScaFix is a planning aid: it lays out bays, lifts and ties by the maker's published rules and counts the parts before you order or quote. It is not a structural calculation, an approval or an inspection, and it checks nothing against S.I. 299/2007 or the HSA code. It replaces neither the competent person nor the CSCS-carded scaffolder.

To size a wall in the browser, the scaffolding calculator gives the bays, lifts, decked levels and area. The scaffold inspection checklist helps with the 7-day round, the UK rules and TG20 explain the guidance the Irish code accepts as a standard configuration, and roof-edge protection by scaffold covers roof work at the eaves. Other countries are listed in scaffolding rules by country.

Frequently asked questions

How often does a scaffold have to be inspected in Ireland?

At least every 7 days where a worker could fall 2 m or more from the platform, under regulation 119 of S.I. 299/2007. The HSA code also asks for an inspection before first use and after any change, bad weather, damage or a period without use. The report is given within 24 hours and the result kept for 5 years.

Do you need a CSCS card to erect scaffolding in Ireland?

Yes. The Construction Regulations 2013 require a valid construction skills registration card for «Scaffolding — basic», «Scaffolding — advanced» and mobile tower scaffolds, and the contractor must ask to see it. Trainees may work under the supervision of a competent person while carrying identification as a trainee.

Is TG20 accepted in Ireland?

Yes. The HSA code accepts TG20 as one of the standard configurations: bespoke drawings, designs and calculations are needed unless the scaffold follows the maker's design, a competent designer's design or TG20. A scaffold outside those, such as a sheeted system scaffold, needs its own design.

What is form GA3?

GA3 is the HSA's template for recording a scaffold inspection under regulation 119, printed in Appendix C of the code of practice. The HSA says it is not an approved or statutory form, so another format is allowed as long as it holds the eight particulars of Schedule 5.