Rules and safety

AS/NZS 1576 and AS 4576: ties, bays and lifts for scaffold planners

In Australia, scaffolding work where a person or object could fall more than 4 m needs a high risk work licence, and such a scaffold is inspected before use and at least every 30 days. Platforms are rated light, medium or heavy duty (225, 450 or 675 kg per bay), and ties and lifts follow the supplier's instructions.

· How the numbers are computed ·

Acrow QUICKSTAGE scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Acrow QUICKSTAGE around the example house, as ScaFix draws it in 3D.

Which standards and rules apply to scaffolding in Australia?

Three layers apply: the state work health and safety regulations, which set the 4 m licence and inspection duties; the AS/NZS 1576 series, which sets design and performance requirements for scaffolds and their equipment; and AS 4576:2020, the guidelines for erecting, inspecting and using them. The supplier's instructions decide the ties and bracing of a given system.

Before you rely on this guide

This guide summarises published rules to help you plan and is not legal advice. It has not been reviewed by a qualified scaffold designer or engineer. ScaFix is a planning aid, not structural approval: the manufacturer's instructions, the scaffold design and a competent person's inspection decide what is built and used on site. How these guides are written, sourced and corrected: editorial and review policy.

What do AS/NZS 1576 and AS 4576 cover?

AS/NZS 1576.1:2019 sets out design and operational requirements for scaffolding systems, equipment and scaffolds, including catch platforms and temporary stairways. AS 1576.3:2015 covers prefabricated and tube-and-coupler scaffolding. AS 4576:2020, now an Australian-only standard, gives practical guidance on selecting, erecting, inspecting and using scaffolds as the companion to the 1576 series.

DocumentWhat its scope coversEdition (Standards Australia store)
AS/NZS 1576.1Design and operational requirements for scaffolding systems, equipment and scaffolds2019, current; replaced the 2010 edition
AS 1576.3Product information, test and performance requirements for prefabricated and tube-and-coupler scaffolding2015 with Amendment 1 (2017), current
AS 4576Guidance on training, site preparation, selection, supply, erection, inspection and use2020, current; replaced AS/NZS 4576:1995

The standards are sold through the Standards Australia store, so this page does not quote them: it states what a planner checks and links the store pages. Suppliers' guides refer to the editions they were written against; Acrow's QUICKSTAGE guide of October 2026, for example, still cites AS/NZS 1576.1:2010.

When does scaffolding work need a licence?

Scaffolding work needs a high risk work licence when a person or object could fall more than 4 m from the platform or the structure. There are three classes: basic for modular or prefabricated scaffolds such as Kwikstage, intermediate adding cantilevered, spur and tube-and-coupler scaffolds, and advanced adding hung and suspended scaffolds.

Safe Work Australia's scaffolding page states the 4 m rule and the three classes, and adds that work where a fall of more than 2 m is possible is high risk construction work that needs a safe work method statement. The class contents above are from Schedule 3 of the work health and safety regulation, read in the Queensland version of the model text; the NSW industry standard says a basic (SB) licence is the minimum to erect prefabricated modular scaffolding (NSW standard, p. 24).

Kwikstage scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Kwikstage around the example house, as ScaFix draws it in 3D.

How often must a scaffold be inspected?

A scaffold from which a person or thing could fall more than 4 m is inspected by a competent person before it is first used, after an incident, after repairs, and at least every 30 days. Before first use, the person in control needs written confirmation that the scaffold is complete, the handover certificate.

These duties are in regulation 225 of the model work health and safety regulations (Queensland text). The NSW industry standard calls the written confirmation the handover certificate and repeats the 30-day interval (NSW standard, pp. 31 and 43), and SafeWork NSW's handover certificate template asks for the duty rating, the number of loaded platforms and the bay sizes.

What duty class does a platform need?

A light duty platform takes up to 225 kg per bay, medium duty 450 kg and heavy duty 675 kg, each with a concentrated load inside that total. The duty class also sets the minimum platform width, and the two national documents and the Victorian standard print the same three loads.

DutyLoad per platform per bayMinimum width, WorkSafe VictoriaTypical width, Safe Work Australia guide
Light225 kg, 120 kg of it concentrated450 mmabout 450 mm
Medium450 kg, 150 kg concentrated675 mmabout 900 mm
Heavy675 kg, 200 kg concentrated900 mmat least 1,000 mm

The loads are the same in the Safe Work Australia general guide («Working platforms»), the NSW standard (p. 40) and the WorkSafe Victoria standard (p. 26, Table 1); the widths differ between the documents, so use the one your state applies. A system's own rating decides what one of its bays carries: Waco Kwikform's Kwikstage guide gives 6.6 kN (675 kg) for bays up to 1.27 m × 2.44 m, with no more than two working platforms loaded per bay at a time (PPM51, p. 6).

How far apart are the ties on an Australian scaffold?

Ties follow the manufacturer's, designer's or supplier's instructions first. Where a supplier gives none, WorkSafe Victoria's industry standard sets a general rule: the first tie level no higher than three times the least base width and 4 m at most, no more than 4 m between tie levels, and no more than three bays between ties along a level.

That general rule is on p. 31 of the Victorian standard, which points to AS 1576.6:2020 for the background; p. 32 gives the typical pattern for an unsheeted 1.2 m wide scaffold as every third bay, every second lift and the ends. The NSW standard asks for the tie design to be determined before erection, with vertical spacing not over 4 m (pp. 18 and 55), and the Safe Work Australia guide puts the supplier's instructions first («Tying and anchoring»).

For Kwikstage, Waco Kwikform's guidelines tie a scaffold up to 20 m at the first standard at each end and then at intervals of no more than every third standard, the first tie no more than 4.0 m above the foundation and then no more than 4.0 m apart in height; above 20 m the end zones tie at every standard, and above 30 m engineering advice must be sought (PPM51, p. 5). On a straight Kwikstage wall 12 m long and 8 m high, ScaFix places 7 ties: it keeps a denser grid inside that rule, every second standard with alternate rows staggered. Victoria's typical pattern is for a scaffold without sheeting, so one clad in shade cloth or sheeting needs its own tie design.

How high is a lift, and how are bays braced?

Fully planked lifts should be no more than 2 m apart and must never be more than 3 m apart, says the NSW industry standard. For Kwikstage, Waco Kwikform limits each new lift to 2 m above the last ledgers and transoms and braces the outside face at each end bay and every third bay.

The lift limits are on p. 30 of the NSW standard; the Kwikstage lift and bracing rules on pp. 2 and 3 of PPM51. Acrow's QUICKSTAGE guide shows at most three bays unbraced. ScaFix plans Kwikstage in 2 m lifts, so a wall 8 m high gets 3 decked lifts, and on a 12 m wall it uses 4 bays from Kwikstage's ledger lengths.

How do New Zealand's scaffold rules differ?

New Zealand shares AS/NZS 1576.1, a joint standard, but has its own regulations. The erection or dismantling of scaffolding from which a person may fall 5 m or more is notifiable work in New Zealand, and the regulator must be told in writing at least 24 hours before it starts, under the Health and Safety in Employment Regulations 1995.

The definition is in regulation 2 and the notice in regulation 26 of the 1995 regulations, in force as at 20 October 2025. AS 4576:2020 is an Australian-only standard; the joint AS/NZS 4576:1995 it replaced is listed as superseded. A New Zealand planner reads the supplier's instructions the same way, and checks the local guidance on top.

What does ScaFix check, and what not?

ScaFix applies each system's published tie, bracing and lift rules when it lays out and counts a scaffold, for Kwikstage Waco Kwikform's guidelines. It makes no AS/NZS 1576 or AS 4576 compliance check, sets no duty class, and replaces neither a licensed scaffolder nor the competent person's inspection and handover certificate.

A planner uses it to see the bays, lifts and parts before ordering: the Kwikstage scaffold calculator sizes one wall, and the Kwikstage parts list for a two-storey house works a whole house. The rules for 14 other countries are compared in scaffolding rules by country.

Frequently asked questions

Do you need a licence to erect scaffolding in Australia?

Yes, when a person or object could fall more than 4 m from the platform or the structure: that work needs a high risk work licence. The basic class covers modular and prefabricated scaffolds such as Kwikstage; intermediate adds cantilevered, spur and tube-and-coupler scaffolds, and advanced adds hung and suspended scaffolds, according to Safe Work Australia and the model regulation.

How often does a scaffold have to be inspected in Australia?

At least every 30 days, and also before first use, after an incident and after repairs, for a scaffold from which a person or thing could fall more than 4 m. A competent person inspects it, and written confirmation that it is complete, the handover certificate, comes before first use.

How many kilograms can a scaffold bay hold?

225 kg per platform per bay for light duty, 450 kg for medium duty and 675 kg for heavy duty, each including a concentrated load of 120, 150 or 200 kg, per the Safe Work Australia guide. A system's own rating applies on top: Waco Kwikform rates Kwikstage bays up to 1.27 m × 2.44 m at 675 kg.

Is AS/NZS 4576 still current?

No. AS/NZS 4576:1995 is listed as superseded on the Standards Australia store; its successor is AS 4576:2020, Guidelines for scaffolding, an Australian-only standard published on 21 August 2020. It gives guidance on training, site preparation, selection, erection, inspection and use, as the companion to the AS/NZS 1576 series.