Parts list
Kwikstage parts list for a two-storey house
ScaFix counts 759 Kwikstage parts to scaffold a whole two-storey house, 12 × 9 m on plan with 6 m eaves and gables rising to 8.5 m: 156 standards, 124 ledgers, 78 transoms and 45 decks. The complete list follows, then what the corners and gables add and which Australian rules apply on top.
By Ole Emil Frikstad Urstad · Checked against Waco Kwikform PPM51 (August 2013), pp. 2–6; SafeWork NSW Scaffolding Industry Safety Standard (2022), pp. 30 and 40 (printed) (24 November 2026) · How the numbers are computed ·

What goes into Kwikstage scaffolding for a two-storey house?
For a house 12 × 9 m on plan with eaves at 6 m and gables to 8.5 m, ScaFix plans Kwikstage round all four walls in 18 bays and 759 pieces: 156 standards, 124 ledgers, 78 transoms, 45 decks, 124 guardrails, 44 toe boards, 24 braces and 26 ties. The gable walls reach 4 decked lifts.
Before you rely on this guide
This guide summarises published rules to help you plan and is not legal advice. It has not been reviewed by a qualified scaffold designer or engineer. ScaFix is a planning aid, not structural approval: the manufacturer's instructions, the scaffold design and a competent person's inspection decide what is built and used on site. How these guides are written, sourced and corrected: editorial and review policy.
How does a whole house differ from one wall?
Three ways. The four walls meet at corners, so the runs close round the house: each wall’s run includes one short bay of 0.76 m, the scaffold’s own width. The gable walls climb to the ridge and get an extra lift. And every wall is tied and braced by the system’s rules for its own length and height.
Drawn as a rectangle with a gabled roof, the house gets scaffold on all four sides: the long sides stop under the eaves, the gable ends follow the roof up to a highest deck of 8.5 m. Lifts are 2 m apart, the Waco Kwikform maximum between a new lift and the ledgers and transoms under it (PPM51, p. 3), which puts decks at 2.5 m, 4.5 m, 6.5 m and 8.5 m.
Bays on the long sides: 4 × 3.05 m + 1 × 0.76 m. Standards are 0.76 m apart across the scaffold, and every lift has a hatch deck for the internal ladder.
ScaFix parts list: Kwikstage around a 12 × 9 m two-storey house
ScaFix plans all four walls, 18 bays in all, with the long walls in 4 × 3.05 m + 1 × 0.76 m, decked lifts at 2.5 m, 4.5 m, 6.5 m and 8.5 m: 300 m² of scaffold and 759 pieces.
| Part | Length | Count |
|---|---|---|
| Frames and standards | ||
| Standards | 2 m | 112 |
| Standards | 1 m | 44 |
| Ledgers and beams | ||
| Ledgers | 3.05 m | 100 |
| Ledgers | 0.76 m | 24 |
| Transoms | 78 | |
| Decks | ||
| Decks without ladder | 3.05 m | 31 |
| Decks without ladder | 0.76 m | 8 |
| Decks with ladder | 3.05 m | 6 |
| Guardrails | ||
| Front guardrails | 3.05 m | 100 |
| Front guardrails | 0.76 m | 24 |
| Toeboards | ||
| Toeboards | 3.05 m | 36 |
| Toeboards | 0.76 m | 8 |
| Diagonals | ||
| Diagonals | 3.05 m | 16 |
| Diagonals | 0.76 m | 8 |
| Ends | ||
| End guardrails | 16 | |
| Wall ties and fittings | ||
| Wall ties | 26 | |
| Wall-anchor fittings | 26 | |
| Right-angle couplers for wall ties | 52 | |
| Base jacks and legs | ||
| Base jacks / legs | 44 | |
Computed by ScaFix’s engine for exactly this job, with the system’s own bay lengths and rules. Corners are in the list only where the job is a whole house; openings, sheeting, hoists and loading bays are not. The manufacturer’s instructions decide: this is a planning aid, not structural approval.
Calculated with ScaFix, a scaffold planning app for browser and iPhone (115 scaffold systems from 57 manufacturers, checked 10 November 2026).

How do the corners and gables change the counts?
The corners add a short bay to each wall and the gables add lifts. Round this house, ScaFix counts 156 standards for 18 bays on four walls. The gable walls reach 4 decked lifts, the top one at 8.5 m, with their own decks, guardrails and toe boards.
A flat-roofed version, all four sides stopping at the 6 m eaves, takes 655 pieces; the gables bring it to 759, as the table further down shows. Decks and ties both rise with the gables: 37 decks flat against 45 with gables, and 24 ties against 26, because the gable walls are taller and carry more lifts and tie rows.
What each line of the list is made of, house-wide (the Kwikstage scaffold calculator works the same arithmetic for one wall):
- Standards (156): two per standard line, in 2 m lengths topped by a 1 m length that holds the top guardrail clear of the highest deck.
- Ledgers (124) and transoms (78): ledgers along both faces, transoms across every standard line, at the base and at each decked lift.
- Decks (45): a deck per bay per lift, plus the deck each ladder starts from; 6 are hatch decks.
- Guardrails (124) and toe boards (44): top rail and mid-rail on every working lift and on the stiffening row at the base; a toe board per bay per lift.
- Braces (24): PPM51 asks for face bracing in the end bays and in every third bay, plus braces across each end (PPM51, p. 2).
- Ties (26) and couplers (52): two couplers a tie, since PPM51 clamps each tube tie to the inner and the outer standard (PPM51, p. 4).
Where do the tie and bracing rules come from?
From one supplier’s guide, Waco Kwikform’s guidelines for safe use of Wedgelok and Kwikstage scaffold. Up to 20 m it ties the end standards, then no more than three standards apart, starting no higher than 4.0 m and then at most 4.0 m up between rows, staggered if possible. ScaFix uses every second standard, which is denser.
The same guide sets a minimum tie capacity of 600 kg in push and pull and forbids reveal ties (PPM51, p. 5). Its bay load, 6.6 kN or 675 kg, assumes bays of 2.44 m or less, while the long sides of this house use 3.05 m bays, so check that bay’s rating with your supplier (PPM51, p. 6). Other Kwikstage suppliers publish their own guides, and theirs may need more ties or braces.
Other two-storey houses, and the same house in Acrow QUICKSTAGE
Same engine, same rules: each row is a whole house with all four walls and its corners.
| House | Walls | Bays | Decked lifts | Standards | Ledgers | Transoms | Decks | Ties | Pieces |
|---|---|---|---|---|---|---|---|---|---|
| Kwikstage, 10 × 8 m, eaves 5.5 m, ridge 7.5 m | 4 | 16 | 3 | 136 | 108 | 68 | 39 | 20 | 663 |
| Kwikstage, 12 × 9 m, eaves 6 m, ridge 8.5 m | 4 | 18 | 4 | 156 | 124 | 78 | 45 | 26 | 759 |
| Kwikstage, 12 × 9 m, eaves 6 m, flat roof | 4 | 18 | 2 | 132 | 108 | 66 | 37 | 24 | 655 |
| Kwikstage, 14 × 10 m, eaves 6 m, ridge 9 m | 4 | 22 | 4 | 188 | 156 | 94 | 58 | 32 | 934 |
| Acrow QUICKSTAGE, 12 × 9 m, eaves 6 m, ridge 8.5 m | 4 | 18 | 4 | 156 | 124 | 78 | 45 | 24 | 713 |
Which Australian rules sit on top of the list?
Four rules apply to a house like this. The decks pass 4 m, so erection is licensed high risk work; a competent person inspects at handover and every 30 days or sooner; the duty class fixes the load each bay may carry; and fully planked lifts stay within 2 m of each other unless designed otherwise.
- Licence. Erecting or dismantling where someone could fall over 4 m is high risk work; Kwikstage, as a modular system, falls under the basic scaffolding class (Safe Work Australia; Schedule 3 of the model regulation).
- Handover and inspections. Before first use the scaffold needs written confirmation that it is complete, and a competent person inspects it then, after any incident or repair, and within every 30 days (regulation 225, Queensland text).
- Duty. Light 225 kg, medium 450 kg and heavy 675 kg per bay (NSW standard, p. 40); the scaffolder chooses the class for the work.
- Lifts. No more than 2 m between fully planked lifts, never more than 3 m (NSW standard, p. 30).
State by state, with sources, the rules are set out in the AS/NZS 1576 planning reference.
What is not on the list?
Whatever the site adds: hop-ups at the eaves, a loading bay or stair tower, shade cloth and the extra tying it calls for, sole boards and freight. Add those by hand, or draw them in the app, because each one changes the total:
- Hop-up brackets and the planks they carry.
- A loading bay, a ladder tower or a stair tower.
- Shade cloth or sheeting, with a tie design to suit.
- Sole boards and delivery.
In the ScaFix app a house of your own, in Kwikstage or Acrow QUICKSTAGE, gives the 3D model and the complete list under the same rules.
ScaFix is a planning aid. This list is neither a scaffold design nor an AS/NZS 1576 compliance check; the supplier’s guide, a licensed scaffolder and a competent person’s inspection govern the erected scaffold.
Frequently asked questions
How many standards does a Kwikstage scaffold for a two-storey house need?
156 standards, by ScaFix’s count, for the 12 × 9 m house with 6 m eaves and gables to 8.5 m, made up from 2 m and 1 m lengths, two per standard line. The bigger 14 × 10 m house in the table takes 188, the smaller 10 × 8 m one 136.
How many Kwikstage decks for a two-storey house?
45 decks for the 12 × 9 m gabled house in ScaFix’s count: a deck in every bay of every working lift and one where each ladder starts, 6 of them hatch decks. Give the same house a flat roof, so every side stops at the 6 m eaves, and the figure drops to 37.
How many ties does a Kwikstage house scaffold need?
26 wall ties on the 12 × 9 m gabled house, as ScaFix counts them: every second standard, rows no more than 4 m apart, which is tighter than Waco Kwikform’s every third standard and 4.0 m. Every tie takes two couplers, on the inner and the outer standard.
Does a two-storey house scaffold need a licensed scaffolder in Australia?
Yes. Its top decks sit above 4 m, the height from which a fall makes scaffolding work high risk, so erecting, altering or taking it down needs a high risk work licence; the basic scaffolding class covers modular systems such as Kwikstage. Once up, a competent person inspects it within every 30 days.
Sources
Primary sources used for this article, with the date each was read.
- Waco Kwikform, Guidelines for the safe use of Wedgelok / Kwikstage scaffold (PPM51, August 2013) (read 24 November 2026)
- SafeWork NSW, Scaffolding Industry Safety Standard (2022) (read 24 November 2026)
- Safe Work Australia, scaffolding (safety topic) (read 24 November 2026)
- Work Health and Safety Regulation 2011 (Qld), model text: Schedule 3 and regulation 225 (read 24 November 2026)