Scaffolding for rendering a house: duty, wall gap and quantities

Rendering a two-storey house in the UK needs a scaffold on every elevation you render, boarded at each lift, at a duty rating the scaffolder agrees with you. For a detached house of 10 × 8 m, ScaFix plans 16 bays and 3 decked lifts in Kwikstage, about 254 m² of scaffold face.

· How the numbers are computed ·

Layher Blitz scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Layher Blitz around the example house, as ScaFix draws it in 3D.

What scaffolding do you need to render a house?

An independent scaffold round every elevation that gets render, boarded at each lift so the renderer can reach the whole face, with guard-rails, toe boards and a gap to the wall agreed for the finished coat. Tell the scaffolder the loads you will put on the boards; the HSE default is general purpose.

Which duty rating does a rendering scaffold need?

Unless your scaffolder tells you otherwise, the HSE says to assume a scaffold is general purpose, with a maximum load of 2 kN/m², about 200 kg per square metre. Bags of render, a mixer or a pump on the boards add to the load the scaffold has to carry, so state them when you order.

The HSE's scaffolds page sets out three ratings as examples: an inspection and very light duty scaffold at 0.75 kN/m² for access, inspection or light cleaning, the general purpose default, and a heavy duty scaffold for heavy masonry and cladding at 3.0 kN/m². It names no rating for rendering, so this page does not either. What it does say is that those specifying scaffolds should be clear about the duty rating they need, and that if you intend to load out platforms, a bespoke design will likely be needed.

Rating (HSE example)Maximum loadTypical use the HSE names
Inspection and very light duty0.75 kN/m²Access, inspection, light cleaning
General purpose (the default)2 kN/m²Assumed unless the provider says otherwise
Heavy duty3.0 kN/m²Heavy masonry and cladding

The HSE adds that boards should cover the whole platform, which must suit both the work and passing people, usually at least 600 mm wide. A renderer working from a spot board needs room to pass behind it; settle the number of boards with the scaffolder. Background on the classes is in scaffold load classes.

How far from the wall should the boards be for rendering?

Close enough that nobody can fall through the gap, measured to the face being worked on. The Work at Height Regulations require a working platform with no gap through which a person could fall, or through which material could fall and injure someone, unless other measures protect against it.

That is Schedule 3, paragraph 5 of the regulations; it gives no figure. The NASC's guide to appointing a scaffolding contractor says internal edge protection should conform to NASC SG29, which is sold, not published. The one published figure we could open is the Jersey inspectorate's leaflet based on SG29: an inside gap under 225 mm with no door or window openings normally needs no inner protection, and where full inner rails would block work on the face, a risk-assessed safe system of work may replace some of it (Jersey HSI; Jersey guidance, not UK law; NASC guide, §6.7).

Rendering moves the face. A base coat, insulation boards or a beading line all bring the wall closer to the boards, and hacking off old render takes it further away. Tell the scaffolder the finished thickness so the gap and any inside boards or brackets are set for every stage. The ScaFix figures below are the scaffold as planned along the wall; they include no inside brackets. More on the gap: scaffold gap to the wall.

Kwikstage scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Kwikstage around the example house, as ScaFix draws it in 3D.

How much scaffolding does it take to render a house?

ScaFix counts 663 parts in Kwikstage for a detached two-storey house of 10 × 8 m with the eaves at 5.5 m and gables to 8 m, scaffolded all round: 16 bays, decks at 2.6 m, 4.6 m and 6.6 m, and 254 m² of scaffold face.

The two runs below are the same engine and set-up: the whole house for a full re-render, and the front elevation alone for a job that renders one face. ScaFix runs every wall as a straight run, decked at each lift, with ladder access through decks with a ladder: one ladder bay on the front elevation alone, and ladder decks on both gables when the whole house is scaffolded (4 of the 39 decks). The gables carry the extra top lift.

ScaFix count, KwikstageWhole house, all four elevationsFront elevation only, 10 × 5.5 m
Bays164
Decked lifts3 (2.6 m, 4.6 m and 6.6 m)2 (2.6 m and 4.6 m)
Scaffold face254 m²55 m²
Decks and boards399
Standards13630
Parts in total663160

The whole-house figure is the one a full re-render or a colour change needs: the scaffold has to reach every face you render, at once or in sections planned with the renderer. For your own walls, the scaffolding calculator sizes a wall in the browser (bays, lifts, decked levels and area), and the Kwikstage parts list for a two-storey house shows a full list for a larger house.

How long will the scaffold be up, and how does that affect the price?

Hire is counted in weeks, so the number of weeks is the figure to agree before the job starts. The quote should say how many weeks are included and the rate for each extra week; the weeks themselves depend on the preparation, the number of coats and the waiting times the render system needs.

Treat weeks as the variable: hire cost = weeks on site × the weekly rate quoted, whether that rate is per elevation, per square metre of scaffold face or for the whole job. The NASC guide names the duration of scaffold hire among the points a client weighs when the access to a scaffold is chosen, and wants full information given to the scaffolding contractor at design and tender stage (NASC guide, §6.6). Ask how weeks lost to bad weather are charged. The scaffolding quote template has a line for each of these.

Which checks and permits apply while the house is rendered?

The scaffold must have been inspected in that position within the previous 7 days before anyone works from it, where a person could fall 2 m or more, and after anything that may have made it unsafe, such as high winds. A scaffold on the pavement needs a council licence, which the scaffolder applies for.

The 7-day rule sits in regulation 12(4); the HSE adds inspection before first use and after high winds, and puts the duty on the scaffold user or hirer. Schedule 2 puts the top rail at least 950 mm over the edge, and no space between rails may exceed 470 mm.

In England and Wales, a scaffold on the street needs a licence from the highway authority under section 169, the 1980 Act's rule for structures over the highway. Per GOV.UK, the builder or scaffolding company gets the licence; as the householder you check it exists and does not run out before the work is finished. Render work often comes with sheeting against weather: the HSE says to tell those who designed and erected the scaffold before sheeting or netting a scaffold, because it must be designed for the extra wind load.

ScaFix is a planning aid for the quantities of a rendering job; it is no structural calculation, no design and no compliance check. Loads, ties, the ground under the base plates and the gap to the render are outside what it counts. How this scaffold is designed, built, tied and inspected is for the scaffolder, the maker's instructions and the law to decide.

Frequently asked questions

Do I need scaffolding to render a two-storey house?

Yes, for the upper storey in practice: rendering is hours of work across the whole face, and a boarded scaffold gives a guarded working platform at each lift, inspected every 7 days. For a detached two-storey house of 10 × 8 m ScaFix plans 3 decked lifts in Kwikstage, with 16 bays all round.

How far should scaffold boards be from the wall for rendering?

The regulations ask for no gap a person could fall through and give no figure. The Jersey inspectorate's SG29-based leaflet says an inside gap under 225 mm normally needs no inner protection. Agree the gap with the scaffolder for the finished render thickness, because the face moves as coats go on.

Which duty rating does the HSE assume for a rendering scaffold?

General purpose: the HSE treats general purpose, 2 kN/m², as the default unless the provider says otherwise, and names heavy duty, 3.0 kN/m², for heavy masonry and cladding. Rendering is not named. Tell the scaffolder what you will store on the boards; loading out platforms will likely need a bespoke design, the HSE says.

How often must a rendering scaffold be inspected?

Before first use, at least every 7 days while people can fall 2 m or more from it, and after anything that may have made it unsafe, such as high winds. The duty sits with the scaffold user or hirer, and the NASC guide treats the scaffolder's handover certificate as that first inspection.