Scaffold parts list template

A parts list follows the bays and lifts: wall length over bay length gives the bays, a decked lift goes every 2 m, and each bay and lift takes its decks, guardrails and toe boards. For a 10 m × 8 m two-storey house, ScaFix lists 430 pieces of Layher Blitz: 132 frames and standards and 36 base jacks.

A worked scaffold parts list for one house in three systems, Layher Allround, HAKI Universal and Plettac SL, computed by ScaFix's planning engine. Each list gives every part by group, length and quantity. Use the tables or the CSV as the template for your own list, order or quote.

· How the numbers are computed ·

Layher Allround scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Layher Allround around the example house, as ScaFix draws it in 3D.

What goes into a scaffold parts list?

A scaffold parts list names every component by type and length with its quantity: base jacks, standards or frames, ledgers and transoms, decks, guardrails and toe boards, diagonals, wall ties and the access. The lengths follow the system's own bay grid, so the same house gives a different list in each system, as the three lists below show.

How the template was made

The house is ScaFix's reference building: 11.4 × 5.3 m, eaves at 4.5 m and ridge at 6 m, scaffolded on all four walls, the two gables up to the roof. Each system is planned at its own default depth with its own bay lengths, and the engine counts every part the plan needs.

On this house the engine gives 515 pieces in Layher Allround, 652 in HAKI Universal and 316 in Plettac SL. The lists are generated when the site is built, from the same engine and catalogue the ScaFix web app plans with, so they change only when the catalogue does.

Download the three lists as one file: CSV (UTF-8, comma-separated, one row per system, group, part and length) or JSON.

Common sizes by system, counted by ScaFix

Common sizes by system, counted by the ScaFix engine
Wall or houseLayher Blitz: Decks / boardsLayher Blitz: GuardrailsLayher Blitz: Pieces in allLayher Allround: Decks / boardsLayher Allround: GuardrailsLayher Allround: Pieces in allTube & coupler: Decks / boardsTube & coupler: GuardrailsTube & coupler: Pieces in all
8 × 6 m, 1 storey172821317564152484730
10 × 8 m, 1 storey2136247217248730104888
12 × 8 m, 1 storey2340267238053330104888
8 × 6 m, 2 storeys33443513388663441241,102
10 × 8 m, 2 storeys505243037104819561561,350
12 × 8 m, 2 storeys565846841116901561561,350

Counted by the ScaFix engine, the same one the app plans with (How the numbers are computed). Assumptions: level ground; a decked lift every 2 m, so a wall with 1, 2 or 3 decked lifts is 4, 6 or 8 m high; houses are 3 m (one storey) or 5.5 m (two storeys) to the eaves, with a gabled roof rising 3 m, scaffolded all round as one connected ring; guardrails and toe boards where the system’s rules put them, on every decked lift and at the open ends; access by the system’s ladder decks or stair. Weights are the app’s estimate (±10 % on catalogue figures, ±20 % on generic ones; «–» where the catalogue has no weight for every part). A planning count, not a structural calculation: check it against the manufacturer’s instructions. Calculated with ScaFix, a scaffold planning app for browser and iPhone (115 scaffold systems from 57 manufacturers, checked 10 November 2026).

Layher Allround: 515 pieces

GroupPartLengthQuantity
Frames and standardsStandards2 m64
Frames and standardsStandards1 m32
Ledgers and beamsLedgers3.07 m72
Ledgers and beamsTransoms–48
DecksDecks without ladder3.07 m23
DecksDecks with ladder3.07 m2
DecksU-lift-off preventers0.73 m34
GuardrailsFront guardrails3.07 m72
ToeboardsToeboards3.07 m24
DiagonalsDiagonals3.07 m8
EndsEnd guardrails–8
EndsEnd toeboards–8
Wall ties and fittingsWall ties–24
Wall ties and fittingsWall-anchor fittings–24
Wall ties and fittingsRight-angle couplers for wall ties–8
Base jacks and legsBase jacks / legs–32
Base jacks and legsBase collars–32
Total515

HAKI Universal: 652 pieces

GroupPartLengthQuantity
Frames and standardsStandards2 m80
Frames and standardsStandards1 m40
Ledgers and beamsLedgers2.5 m96
Ledgers and beamsTransoms–60
GuardrailsFront guardrails2.5 m48
ToeboardsToeboards2.5 m32
DiagonalsDiagonals2.5 m16
DiagonalsDiagonals2.7 m8
EndsEnd guardrails–12
EndsEnd toeboards1.01 m12
Wall ties and fittingsWall ties–18
Wall ties and fittingsWall-anchor fittings–18
Wall ties and fittingsRight-angle couplers for wall ties–18
Base jacks and legsBase jacks / legs–40
Stair towerUTV stairs–2
Stair towerStair-tower standards–4
Stair towerStair-tower ledgers–1
Stair towerStair-tower transoms–6
Stair towerStair-tower base jacks–2
Stair towerInterior UTV handrails–2
Stair towerExterior UTV handrails–2
Stair tower700 mm guardrail frames–2
Stair tower700 mm toeboards–2
Stair towerStair-tower top frame–1
Stair towerTop guardrail post–1
Stair towerTop-exit toeboard–1
System-specific partsAluminium planks2.5 m128
Total652

Plettac SL 70/100: 316 pieces

GroupPartLengthQuantity
Frames and standardsFrames2 m40
Frames and standardsFrames1 m4
Frames and standardsTop-lift guardrail posts–16
DecksDecks without ladder3 m14
DecksDecks without ladder2.5 m8
DecksDecks without ladder1.5 m8
DecksDecks with ladder3 m2
GuardrailsFront guardrails3 m24
GuardrailsFront guardrails2.5 m12
GuardrailsFront guardrails1.5 m12
ToeboardsToeboards3 m16
ToeboardsToeboards2.5 m8
ToeboardsToeboards1.5 m8
DiagonalsDiagonals1.5 m8
EndsEnd guardrails–8
Wall ties and fittingsWall ties–40
Wall ties and fittingsWall-anchor fittings–40
Wall ties and fittingsRight-angle couplers for wall ties–8
Base jacks and legsBase jacks / legs–40
Total316

How to adapt the template to your job

  1. Change the wall lengths by recalculating, not by scaling: a wall is built from the system's own bay lengths, so 10 m and 11 m walls can need different bays. The scaffolding calculator gives the bays and parts for your walls.
  2. A higher scaffold adds lifts: standards, ledgers, diagonals and wall ties grow with the number of lifts, decks and guardrails with the number of decked levels.
  3. Wall ties follow each system's tie rule. Where ScaFix has not yet checked a rule against the manufacturer's document, the system page marks the tie count as an estimate; the verification status lists the source of every rule.
  4. Add what the template leaves out: your yard's spare parts, sheeting or netting, a loading bay, and the weight or hire price of each part from your own price list.
  5. Check every quantity against the manufacturer's instructions before you order or build. ScaFix is a planning aid, not a structural approval.

Limits

  • The number of wall ties follows the system's tie rule. Their positions must be checked against the manufacturer's assembly instructions.
  • Round corners, silos and hanging scaffolds are in Pro. A round scaffold is not a standard configuration and needs a calculation or the supplier's documentation. A hanging scaffold (Layher Allround and HAKI Universal) always needs a structural calculation from the supplier or an engineer.

Cite as

ScaFix, «Scaffold parts list template: one house in three systems», version 3b8b05577910, 2026-11-20, https://scafix.app/scaffold-parts-list-template

Questions and answers

Can I open the parts list template in Excel?

Yes. The CSV is UTF-8 with a comma between the columns; open or import it in Excel, Numbers or Google Sheets, then change the quantities or add columns such as weight or hire price. The JSON file has the same rows for scripts.

Why do the three systems need different quantities?

Each system has its own bay lengths and parts. A frame system such as Plettac SL replaces the standards, ledgers and transoms of a modular bay with frames, and longer bays mean fewer bays. On this house the engine gives 515 pieces in Layher Allround, 652 in HAKI Universal and 316 in Plettac SL.

How do I get a parts list for my own building?

Enter your walls in ScaFix on the web or on iPhone, pick your scaffold system and the app plans the bays, lifts and ties and lists every part, with the 3D model of the same plan. The plans and prices are on the ScaFix pricing page.

Sources

ScaFix plans each scaffold system from the documents that system's page names (the manufacturer's manual or approval, where one is on file); the rules come from EN 12811-1 and the national authority. Read 10 November 2026. The documents, not this page, decide how the scaffold is built: ScaFix plans, it does not approve.