Open Parts list in the project. The list is grouped in families (frames and standards, decks, guardrails, toe boards, ends, wall ties, base jacks) with counts and lengths. Choose Per wall or Per level, see the total and weight, and read the note Wall ties (anchoring) at the bottom: it says where the number of ties comes from.

ScaFix Basic or Pro See the plans and what they cost

What you need

  • ScaFix Basic or Pro
  • A project with at least one wall.

Step by step

  1. Step 1 Open the parts list

    Press Parts list at the top of the panel (on a phone: Parts list in the toolbar at the bottom). At the top are the wall area, scaffold area, scaffold volume and the approximate weight, calculated from the manufacturers' catalogue weights. Each family has its own box with the sum on the right and the rows below, with length and count.

    The parts list of House, 12 Mill Lane with families such as Wall ties and fittings and Base jacks, the counts on the right and the tie note at the bottom.
  2. Step 2 Choose per wall or per level

    Per wall shows Total and each wall on its own. Per level splits the list by level; the levels and the whole scaffold add up exactly to the total. Under Data basis it says which manufacturer catalogue the sizes were checked against.

    The parts list with Per level selected: tabs for Total and the levels, the total number of parts and the weight, and the Data basis box.
  3. Step 3 Read the tie note

    At the bottom is the note Wall ties (anchoring): how many the list includes, which rule the number follows and on which page of the manufacturer's instructions that rule is. Numbers marked DERIVED are not printed in the manual; ScaFix worked them out from it with the formula stated in the note. Always check against the instructions and the conditions on site.

    The tie note for HAKI Ram with the number of wall ties, the rule, the source and the explanation of derived numbers.
  4. Step 4 Copy or export

    Copy visible list copies the tab you are looking at. The PDF report with the whole list is under Share (see PDF report and sharing). CSV and Excel are marked Pro.

What the list leaves out

The parts list is the scaffold parts ScaFix has planned for the walls in the project. Sole boards under the base jacks, fixings in the wall (screws, plugs), netting and sheeting, hoists and other extras are included only when they are planned in the project. Always compare with what your supplier or yard uses before you order.

Common mistakes

  • The count does not match the yard. Enter what you have in the parts inventory and the list shows what is missing.
  • The copy is missing walls. «Copy visible list» copies only the tab you are on – choose Total first.
  • Wall ties read as a finished tie plan. The number is a planning figure from the rule named in the note; the positions on site are decided by the instructions and a competent person.