Short answer

Does the bottom lift of a scaffold need ledgers without a deck?

On many facade systems, yes. The German approvals for MJ UNI 70, MJ UNI-CONNECT and Scafom-rux SUPER require a longitudinal ledger at base level in every lowest bay where a diagonal connects (Z-8.1-184, §3.3.3.6), and ALFIX asks for horizontal struts there. The rule does not depend on a deck.

The bottom lift is the field between the base jacks and the first working level. It often carries no deck, and that is exactly where several system approvals ask for a member people tend to leave out.

· How the numbers are computed ·

Close-up of the corner where the long wall and the gable wall meet, with Jamax standards, decks, guardrails and toe boards in the ScaFix 3D model
The corner: the bays of the two walls meet, with deck, guardrail and toe board on each lift.

Before you rely on this guide

This guide summarises published rules to help you plan and is not legal advice. It has not been reviewed by a qualified scaffold designer or engineer. ScaFix is a planning aid, not structural approval: the manufacturer's instructions, the scaffold design and a competent person's inspection decide what is built and used on site. How these guides are written, sourced and corrected: editorial and review policy.

What exactly do the approvals require?

Each document ties the member to the braced bays of the lowest lift, not to a deck. Where a vertical diagonal lands in the bottom field, a horizontal member runs along the facade at the foot of that bay. The wording differs a little between documents, and the table keeps each one's own terms:

SystemDocumentClauseWhat it requires in the bottom lift
MJ UNI 70DIBt Z-8.1-184, 21 June 2019§3.3.3.6 (p. 15); Annex B §B.4In every lowest bay where a diagonal connects, a longitudinal ledger just above the base-jack nut
MJ UNI-CONNECT 70 DUODIBt Z-8.1-872, 16 March 2022§3.3.3.6 (p. 33); Annex B p. 4At least in the bays where a diagonal connects, longitudinal ledgers at base-jack height
Scafom-rux SUPERDIBt Z-8.1-185.1, 2023§3.3.3.6 (p. 20); Annex B §B.4In every bay where a diagonal connects, a longitudinal ledger at the level of the lower transoms
ALFIX FassadeALFIX assembly and use instructions, June 2023p. 16; §4.3 (p. 20)In every lowest braced bay, horizontal struts at the level of the lower transoms

The German text of the MJ UNI 70 approval reads: «In jedem untersten Gerüstfeld, in dem eine Diagonale anschließt, ist ein Längsriegel … einzubauen». The approvals for MJ UNI 70 and Scafom-rux SUPER name the guardrail beam (Geländerholm) as the part to use; ALFIX and MJ UNI-CONNECT also allow a separate horizontal strut.

Why does an empty bottom lift need a horizontal member at all?

The approvals state the rule, not the reason. Read with their bracing clauses, the member completes the braced bay at its foot: the outer diagonal carries forces along the facade down to the base, and the base-level ledger holds that bay's frames together. Leaving it out because the lift has no deck changes the structure the approval describes.

The Norwegian Jamax user guide makes the same point in plainer words for its frames: the frames of the lowest level are joined with guardrails (Jamax user guide, §6.2.2).

HAKI Ram scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
HAKI Ram around the example house, as ScaFix draws it in 3D.

Does a deck in the bottom lift replace the ledger?

No. The clauses above attach the member to every lowest braced bay, whether or not that lift is decked, so a planner cannot trade one for the other. The rails of a decked lift protect the people on the deck; the foot ledger belongs to the bracing.

The base itself still follows the general rule: every standard on a base plate and a firm foundation that does not settle, as 29 CFR 1926.451(c)(2) puts it in the US and as the inspection checklist lists for the walk-round.

What does ScaFix put in the bottom lift?

Since 16 October 2026, ScaFix places rails in the bottom lift of every facade system, also without a deck, and counts them in the parts list. The user chooses the outside face, the inside face or both, with the outside face as the default, and the app never builds fewer faces than the manufacturer requires.

  • Where an approval names a foot member in the braced bays, as in the table above, ScaFix adds that member at foot height in those bays, in the 3D model and the parts list.
  • For a few frame systems with no manual on file, ScaFix adds the same member as its own planning rule, taken from the approvals above rather than from that system's documents.
  • Shoring towers are the exception: their manuals stiffen the base with ledgers and bracing, not with side protection, so ScaFix bills those instead.

Each system's tie pattern comes from the same kind of document; see scaffold ties and anchoring. None of this is a structural check: the approval or manual decides, and a competent person inspects the scaffold before use.

Planning information, not structural approval. The system's approval or assembly instructions decide which members the bottom lift needs, and a competent person must inspect the scaffold before it is used.

Frequently asked questions

What is the bottom lift of a scaffold?

The field between the base jacks and the first working level. On a facade scaffold it often carries no deck, but it still carries the lowest frames, diagonals and, on many systems, a ledger at base level. The MJ UNI 70 approval requires that ledger in every lowest bay where a diagonal connects (§3.3.3.6).

Can I leave the bottom ledger out if nobody works on the first lift?

Not on systems whose approval requires it. MJ UNI 70, MJ UNI-CONNECT and Scafom-rux SUPER tie the ledger to every lowest bay where a diagonal connects, with or without a deck. ALFIX asks for horizontal struts there too; the member belongs to the bracing, so a deck does not replace it.

Which part is used as the bottom ledger?

The approvals for MJ UNI 70 and Scafom-rux SUPER name the guardrail beam (Geländerholm). ALFIX and MJ UNI-CONNECT also allow a horizontal strut at the level of the lower transoms. The Norwegian Jamax user guide joins the frames of the lowest level with guardrails.

Does ScaFix add the bottom rails automatically?

Yes. Every facade system gets rails in the bottom lift on the faces you choose, outside by default, and never fewer than the manufacturer requires; they appear in the 3D model and the parts list. Shoring towers are the exception: their manuals stiffen the base with ledgers and bracing, so ScaFix bills those instead.

Sources

Primary sources used for this article, with the date each was read.