Scaffold job packing checklist – how to load without leaving parts behind

The parts that stay behind in the yard are rarely standards and boards. They are the items needed in only a few places: end guardrails, wall ties and their fittings, base jacks and the last pieces of a stair tower. This checklist is built on the ScaFix engine's parts list for a real example house in three systems, with what the list does not count and a loading order that follows the build.

· How the numbers are computed ·

Layher Allround scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Layher Allround around the example house, as ScaFix draws it in 3D.

How do you avoid forgetting parts when packing scaffolding for a job?

Pack from a parts list for this job, not from memory, and tick it off group by group and length by length. Check the usual misses: end guardrails, wall ties, base jacks and ladder decks. The example house, 11.4 m × 5.3 m, takes 515 pieces in Layher Allround, including 16 end pieces, 56 tie parts and 64 base pieces.

Why parts get left behind

A list from memory covers the bulk: standards or frames, ledgers, boards and guardrails. What goes missing are the parts that follow the shape of the job – how many open ends the scaffold has, how many tie points the wall gets, and whether access is a ladder deck or a stair tower. None of these grow in step with run length, which is why an estimate per metre misses exactly there.

The example house shows it. In Layher Allround, access is 2 ladder decks, but the system needs 34 lift-off preventers and 32 base collars that the other two systems in the table do not use. In HAKI Universal the same house gets a stair tower of 26 pieces in 12 different part types, every one of them needed before the stair can be used. In Kwikstage the walls are made up of mixed bays – 1 × 0.76 m + 3 × 3.05 m + 1 × 2.44 m on the long wall – so boards, guardrails and toe boards come in 3 lengths instead of one.

The checklist group by group – one house, three systems

The figures are the ScaFix engine's parts list for one detached house: 11.4 m × 5.3 m, eaves 4.5 m and ridge 6 m, scaffolded on all four walls with working lifts at 2.5 m and 4.5 m. The «Check at loading» column is what you count against as the kit goes on the lorry.

Pieces per group for the example house, calculated by ScaFix
Part groupCheck at loadingLayher AllroundHAKI UniversalKwikstage
Frames and standardsCount per length; the short standards for the top lift are the easiest to miss.96120120
Ledgers and beamsLedgers per bay length, and transoms for every pair of standards per lift.120156156
DecksBoards or decks per bay length, ladder decks counted apart, and the locks the system uses.5912833
GuardrailsGuardrails per bay length on every working lift.724896
ToeboardsToe boards per bay length on every working lift.243232
DiagonalsBraces in the right bay length and lift height.8248
EndsEnd guardrails and end toe boards for every open end and corner.16248
Wall ties and fittingsWall ties, fittings and couplers – plus anchors that suit the wall.565440
Base jacks and legsBase jacks and base collars; sole boards come on top.644040
Stair towerEvery stair-tower part: flights, handrails, landing frames and the top exit.–26–
Bays on the long wall (11.4 m)4 × 3.07 m5 × 2.5 m1 × 0.76 m + 3 × 3.05 m + 1 × 2.44 m
Bays on the gable wall (5.3 m)2 × 3.07 m3 × 2.5 m1 × 0.76 m + 1 × 3.05 m + 1 × 2.44 m
Pieces in total515652533

The items most often left behind

Run through these before the lorry leaves. Figures are for the example house in Layher Allround unless stated.

  • Ends: 8 end guardrails and 8 end toe boards. Each open end needs its own set, and one missing end guardrail keeps a lift out of use.
  • Wall ties: 24 ties, 24 anchor fittings and 8 couplers. What goes into the wall itself depends on the substrate, so check the anchors suit concrete, brick or timber before you set off.
  • Base pieces: 32 base jacks and 32 base collars. Pack a sole board for every one where the ground is not firm and level.
  • Lift-off preventers: 34 on the example house. They are small, they come in the scaffold width, and the decks cannot be secured without them.
  • The stair tower top: of the 26 stair-tower pieces in HAKI Universal, the top frame, the top guardrail post and the top-exit toe board come one of each (1 + 1 + 1), and they are easily lost in a full load.
  • Lengths: Kwikstage needs boards in 3 lengths on this house (1 × 0.76 m + 1 × 3.05 m + 1 × 2.44 m on the gable). Count each length, not just the total.

What the parts list does not count – but you still need

The parts list counts the scaffold components. These depend on the site and the work and go on the packing list as well:

  • Sole boards under the base jacks, chosen for the ground. HSE expects a firm, level foundation and warns about basements, drains and soft ground (HSE).
  • Anchors for the wall ties, chosen for the wall material – ties must be fitted as the scaffold goes up and in line with the manufacturer's instructions (HSE).
  • Barriers and signs to keep people out while the scaffold is incomplete; HSE says scaffolds should never be erected or dismantled over people or busy pavements.
  • The scaffold design or TG20:21 compliance sheet and a handover certificate (see TG20 compliance sheets and handover certificates), plus a scaffold tag.
  • PPE for erecting and the tools the gang needs.
  • Lifting gear to get the kit up, from a gin wheel to a scaffold hoist.

Loading order: what goes up first comes off first

A scaffold is built from the ground up: sole boards and base jacks, the first lift of standards, ledgers and transoms, boards, then guardrails and toe boards before the next lift, with ties added as it rises (how to erect scaffolding). Load in reverse and the kit comes off the lorry roughly when the gang needs it:

  1. Furthest in or at the bottom: top-lift parts – short standards, end guardrails for the top and the stair tower's top frame.
  2. Guardrails, toe boards and ends for every lift, bundled by length.
  3. Boards and decks sorted by bay length, ladder decks kept apart.
  4. Ledgers, transoms and braces, bundled by length.
  5. Standards or frames for the lower lifts.
  6. Nearest the tail or on top: sole boards, base jacks, base collars, wall ties with fittings and barriers – the first things needed on site.

Tick off each group as it is loaded, and count the same list when the scaffold comes back. Losses and damaged parts then show up in the yard, not on the next job.

What the rules expect you to bring

In Great Britain the Work at Height Regulations 2005 set the requirements for scaffolds: strength and stability calculations unless the scaffold is a recognised standard configuration, an assembly plan by a competent person, and warning signs while it is not ready for use (Schedule 3). The scaffold must be inspected after installation and before first use, then at least every 7 days and after anything that could affect its safety (regulation 12, HSE).

Country-by-country rules are in scaffolding regulations and the UK detail in UK scaffolding regulations and TG20. This checklist and its figures are a planning aid, not structural approval of the scaffold.

How to make the packing list in ScaFix

  1. Draw the walls with their measurements, or import a PDF drawing of the building (Basic and Pro).
  2. Pick the system in your yard; ScaFix covers 108 systems from 56 manufacturers.
  3. See the 3D model and the parts list group by group, with counts per length.
  4. Enter your stock in the parts inventory and ScaFix shows what the job is short of before you load.
  5. Take the list on your phone – the same parts list is in the browser and the iPhone app. A PDF report for the yard comes with Basic and Pro (pricing).

Questions and answers

How many spare parts should you take?

No regulation sets a spare allowance. ScaFix gives the exact count for the job, and how much you add for parts that are easily damaged or lost, such as toe boards and couplers, is your firm's call. Write the allowance on the packing list so it is counted back in as well.

Does the parts list include sole boards and anchors?

No. ScaFix counts the scaffold components: standards or frames, ledgers, decks, guardrails, toe boards, braces, ends, wall ties with fittings and base jacks, and a stair tower where access is by stair. Sole boards and the anchors in the wall are chosen for the ground and the wall on site.

Why do the counts differ so much between systems?

The systems are built differently. On the example house Layher Allround needs 515 pieces, HAKI Universal 652 and Kwikstage 533. Bay lengths, separate transoms, deck locks and the type of access all change the count, so always pack from the list for the system you actually use.

Can I reuse a packing list for another job?

Only when the dimensions are the same. Length sets the number of bays, height the number of lifts, and corners and ends set the end guardrails and ties. Make a parts list per job; in ScaFix it updates when you change the measurements.

What should I check on the parts before loading?

Damaged components do not belong on a scaffold. Look for bent tubes, cracked welds, damaged boards and locks that do not work, and set them aside before loading. The checks for the finished scaffold are in the scaffold inspection checklist.

Sources

Work at Height Regulations 2005 (SI 2005/735) on legislation.gov.uk and the HSE scaffolding page, read 25 Oct 2026. Part counts: the ScaFix engine, the same example house as the system pages.

  1. legislation.gov.uk/uksi/2005/735/schedule/3
  2. legislation.gov.uk/uksi/2005/735/regulation/12
  3. hse.gov.uk/construction/safetytopics/scaffoldinginfo.htm

Limits

  • The number of wall ties follows the system's tie rule. Their positions must be checked against the manufacturer's assembly instructions.
  • Round corners, silos and hanging scaffolds are in Pro. A round scaffold is not a standard configuration and needs a calculation or the supplier's documentation. A hanging scaffold (Layher Allround and HAKI Universal) always needs a structural calculation from the supplier or an engineer.