Types of scaffolding
Temporary roof scaffold: what the roof adds to the scaffold under it
A temporary roof keeps rain and snow off a re-roof or a new build by setting a roof structure, usually aluminium beams with sheeting, on top of a scaffold. In the UK, HSE lists temporary roofs among the scaffolds that normally need a bespoke design.
The roof brings wind, snow and uplift into the scaffold below it. This page sets out what changes under the roof, with ScaFix's engine figures for the sheeted support scaffold, and says plainly what ScaFix does not plan.
By Ole Emil Frikstad Urstad · How the numbers are computed ·

What does a temporary roof add to a scaffold?
Wind, snow and uplift loads that standard scaffold configurations do not cover; HSE lists temporary roofs among the scaffolds that normally need a bespoke design by calculation. The sheeted sides tighten the ties as well: on one 10 × 7 m wall in SGB Cuplok, ScaFix's engine goes from 12 ties unclad to 18 under sheeting.
Why does a temporary roof need its own design?
Because it sits outside the configurations a system's manual covers. HSE says strength and stability calculations must be carried out for scaffolding unless a note of calculations exists or the scaffold follows a generally recognised standard configuration, and it names temporary roofs and temporary buildings among the structures that normally need bespoke design by a competent person (HSE).
The same page asks that design information says whether sheeting, netting or brickguards are needed, and warns never to sheet or net a scaffold without informing those involved in its design. NASC's TG09:18 is the trade guide on the design and construction of temporary roofs and buildings; its product page says it covers loadings, weather effects, structural stability and the safe sequence of works. We read the product page, not the paid guide.
What does the roof put into the scaffold below?
Three loads the scaffold would not carry on its own: wind on a closed roof and closed sides, snow lying on the roof, and uplift when the wind gets under it. The makers' own pages show the scale, from spans of 30 m and more to snow loads of about 1.0 kN/m².
| What the roof brings | What the makers say | Source |
|---|---|---|
| Span | Keder Roof XL up to 30 m, depending on local weather (Layher UK's page also cites up to 40 m); HAKITEC up to 32 m | Layher; HAKI |
| Snow | Keder Roof XL: snow loads up to about 1.0 kN/m² on medium spans | Layher UK |
| Uplift | Before sheeting starts, the shelter must be prevented from lifting with anchors or kentledge | HAKI user's guide |
| Design help | Load calculations, drawings and calculation reports offered with the roof | HAKI |
| Moving roofs | Apex structures on nylon wheels running on beams fixed to a suitable support scaffold | Layher UK Mobile Roof |
None of these figures is a design value for your job. They show why the roof and the scaffold under it are designed together, for the site's own wind and snow.
The support scaffold: one 10 × 7 m wall in two UK systems
| System | Wall | Bays | Decked lifts | Parts |
|---|---|---|---|---|
| SGB Cuplok | 10 m × 7 m | 4 × 2.5 m | 3 | 232 |
| Layher Allround | 10 m × 7 m | 3 × 3.07 m | 3 | 182 |
What the example shows
Cuplok runs at 4 × 2.5 m with decks at 2.6 / 4.6 / 6.6 m; Layher Allround at 3 × 3.07 m (9.21 m of scaffold on the 10 m wall) with decks at 2.25 / 4.25 / 6.25 m. This is the scaffold before the roof goes on; the roof's design decides what is added to it.

How much does sheeting change the scaffold's ties?
Noticeably: under sheeting the tie rows close from 4 m to 2 m apart, so on the 10 × 7 m wall ScaFix counts 18 ties instead of 12 for SGB Cuplok and 15 instead of 10 for Layher Allround. A roofed scaffold is normally closed in at the sides, which is why the engine sheets the face here.
| System | Ties unclad | Ties sheeted | Tie rows apart | Parts unclad → sheeted | Sheeting in the maker's documents |
|---|---|---|---|---|---|
| SGB Cuplok | 12 | 18 | 4 m → 2 m | 232 → 256 | Outside the maker's standard configuration: design first |
| Layher Allround | 10 | 15 | 4 m → 2 m | 182 → 193 | Outside the maker's standard configuration: design first |
For both systems the maker leaves sheeting outside the standard configuration (SGB's Cuplok manual covers unsheeted scaffolds only), so the sheeted counts are ScaFix's provisional minimum under the tighter pattern, not a design. The real tie pattern and tie loads come from the design that also carries the roof.
What can ScaFix plan for a roofed scaffold, and what not?
ScaFix plans the scaffold under the roof: bays, lifts, decks, ties and the parts list, from each maker's rules. In ScaFix Pro you can set netting or sheeting on the scaffold; the tie rule tightens and the tie count and parts list are worked out again.
ScaFix does not plan the roof. It has no roof beams, keder rails, sheets or ballast, does not work out wind, snow or uplift on a roof, and makes no structural calculation. It is a planning aid for the scaffold, not a design or approval.
Who inspects a roofed scaffold, and how often?
Like any working platform, and again after storms. For construction work with a fall of 2 m or more, a platform must have been inspected in position within the previous 7 days, and again each time exceptional circumstances may have affected its safety (WAHR 2005 reg. 12); HSE gives high winds as the example.
HAKI's user's guide for its shelter lists inspection on completion, every seven days, after adverse weather and after adaptations or movement.
Questions and answers
Does a temporary roof scaffold need a design?
Yes, normally. HSE names temporary roofs and temporary buildings among the scaffolds that need bespoke design by calculation from a competent person, because they fall outside the standard configurations. The design covers the roof and the scaffold under it together, including the sheeting, the ties and the ballast or anchors against uplift.
How wide can a temporary roof span?
Up to about 30 m for Layher's Keder Roof XL (its UK page also cites up to 40 m) and up to 32 m for HAKI's HAKITEC, depending on the site's wind and snow. Wider spans and heavier snow need stronger beams or more supports, which the roof's design decides.
Can ScaFix design a temporary roof?
No. ScaFix plans the scaffold under the roof, with bays, lifts, ties and parts list, and in ScaFix Pro it can add netting or sheeting to the scaffold and tighten the tie rule. It has no roof components and makes no structural calculation, so the roof and its loads stay with the designer.
How often is a temporary roof scaffold inspected?
At least every 7 days for construction work where a person could fall 2 m or more, and after exceptional circumstances such as high winds, under regulation 12 of the Work at Height Regulations 2005. HAKI's shelter guide adds inspections on completion, after adverse weather and after any adaptation or movement.
Sources
Each document was read on 24 November 2026. Makers' figures describe their own products and are not design values for a job.
- HSE: Scaffolding (design, sheeting and inspection)
- The Work at Height Regulations 2005, regulation 12 (inspection)
- NASC: TG09:18 Guide to the Design and Construction of Temporary Roofs and Buildings (product page)
- Layher UK: Keder Roof System
- Layher UK: Mobile Roof
- Layher: Keder Roof XL
- HAKI: HAKITEC weather protection system
- HAKI: User's guide for HAKITEC 750 System Shelter (2009, pdf)
Limits
- The number of wall ties follows the system's tie rule. Their positions must be checked against the manufacturer's assembly instructions.
- Round corners, silos and hanging scaffolds are in Pro. A round scaffold is not a standard configuration and needs a calculation or the supplier's documentation. A hanging scaffold (Layher Allround and HAKI Universal) always needs a structural calculation from the supplier or an engineer.