Calculating a facade scaffold in Spain: a worked example

The arithmetic of a scaffold is the same in Málaga as in Manchester. What changes is how the quote is measured, when a written plan is required, who may inspect, and which Spanish documents the site will ask for. This example follows one 15 m facade through all of it.

· How the numbers are computed ·

Layher Allround scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Layher Allround around ScaFix's 11.4 × 5.3 m example house, as the app draws it in 3D.

How do you calculate a facade scaffold for a job in Spain?

Measure the facade at its most projecting line, divide the length by the system's bay and round up, allow one lift per 2 m frame, then add ties, access and base jacks. In Spain, add a plan check: above 6 m a prefabricated scaffold needs a written plan or a certified standard configuration.

How does Spanish practice differ from what you know?

Most of the logic carries over: both the UK and Spain work with the idea of a standard configuration, but Spain draws the lines elsewhere, with a written PMDM above 6 m, inspections without a fixed number of days, and quotes priced by the square metre of scaffold.

QuestionUK, as HSE describes itSpain
When is a design or plan needed?A scaffold is designed by bespoke calculation by a competent person unless it follows a recognised standard configuration such as NASC TG20 (HSE)A written assembly, use and dismantling plan (PMDM) for prefabricated scaffolds more than 6 m high or with spans over 8 m, unless a certified system is built to its standard configuration (RD 1215/1997, annex II, 4.3.3 b); VII agreement, art. 177.4)
How often is it inspected?Before first use, then at intervals of no more than 7 days, and after anything that could affect itBefore it is put into service, then periodically, and after any change, period out of use, bad weather or earthquake; no fixed number of days in the text (agreement, art. 179.1)
Who inspects?A competent person; CISRS is one way competence is assessedA person with a qualifying university or vocational qualification; where no plan is needed, someone with more than two years' experience certified by the employer and basic safety training (art. 179.1 and 179.2)
RecordsThe result is recorded and keptResults are documented and kept available for the labour authority (art. 179.3)
How is it priced?Not set by HSE guidanceAlmost always by the square metre of scaffold, with erection, dismantling, transport and hire as separate lines and a minimum area and hire period (Milandamios)

Two Spanish words you will meet at once: the plan is the «PMDM» (plan de montaje, utilización y desmontaje), and the frame scaffold everyone hires is the «andamio europeo»; its sizes and parts are in the European frame scaffold.

Planning a facade scaffold for a Spanish job in seven steps

The order matters: the plan check depends on the height, and the parts list on everything before it.

1. Measure as the quote will

Take the scaffold run at the facade's most projecting line times the maximum working height, the CYPE criterion. Here: 135 m² of facade becomes about 139 m² of scaffold.

2. Fix the kit first

Use the bay grid of the system that will actually arrive, and only one manufacturer. Here: Layher Blitz, 3.07 m bays, 0.73 m frames.

3. Count bays and lifts

15 ÷ 3.07 = 4.89, so five bays and a 15.35 m run; with 2 m frames, four decked lifts up to about 8 m.

4. Decide the PMDM route

Above 6 m (RD 1215/1997, annex II, 4.3.3 b), either build a certified system in its standard configuration or have a qualified person write the plan.

5. Check the inside edge

The collective agreement requires guardrails on every side more than 20 cm from the facade (art. 180.2 e).

6. Count ties, access and jacks

Follow the manufacturer's tie pattern (NTP 1016: rows no more than 4 m apart), one access bay per 30 m, two jacks per frame line clear of utility covers.

7. List the parts and the paperwork

Count frames, decks, rails, toe boards, braces and jacks, then gather the certificate, manual, plan or standard-configuration pages and the inspection record.

The example: a 15 m street facade with a 9 m cornice

A three-storey building on a city pavement: one straight facade, 15 m long, cornice at 9 m, no balconies. The work is painting and render repair. The INSST's NTP 1015 puts painting, cleaning and rendering without heavy stacking in load classes 2 and 3, so class 3 is enough.

The kit is Layher Blitz, which Layher's Spanish subsidiary markets as the frame system "also known as andamio europeo", with decks from 0.73 to 3.07 m long (Layher Ibérica). Its lightweight frame is 2.00 m high, 0.73 m wide and weighs 18.8 kg (Layher Info no. 111).

Close-up of the corner where the long wall and the gable wall meet, with Layher Blitz standards, decks, guardrails and toe boards in the ScaFix 3D model
A corner of the example house in Layher Blitz: the bays of the two facades meet on every lift.

What area will the Spanish quote show?

About 139 m², not the facade's 135 m²: the CYPE price generator, the cost database many Spanish quantity surveyors use, measures facade scaffold as the plan projection of the most projecting perimeter times the maximum working height. Whole bays make the run 15.35 m, and the top guardrail stands above the cornice.

If you are a homeowner comparing quotes, ask each firm which of the two figures it priced. The method for a whole house is in how to calculate scaffold area.

Bays and lifts

Bay lengthSumBaysRun
3.07 m15 ÷ 3.07 = 4.89515.35 m
2.57 m15 ÷ 2.57 = 5.84615.42 m

Five 3.07 m bays win: one frame line fewer on every lift. Mixing four 3.07 m bays with one 2.57 m bay gives 14.85 m and stops 15 cm short of the corner. Check the grid of the kit that will really turn up, because Spanish-made frame ranges are not on Layher's: Fermar's FER-48 uses round lengths of 1.0 to 3.0 m and 0.70 m frames (Fermar catalogue), and NTP 1016 forbids mixing makers in one scaffold.

With 2 m frames the decks sit at 2.05, 4.05, 6.05 and 8.05 m: 4 decked lifts, the top one within easy reach of the cornice.

Does it need a PMDM?

Yes. At about 9 m it is over the 6 m line in RD 1215/1997, annex II, 4.3.3 b), so either the manufacturer's instructions replace the plan, if the system is certified and built exactly to its standard configuration, or a qualified person writes a PMDM.

The two routes in detail:

  • The manufacturer's instructions replace the plan if the system holds a product certificate and is built exactly in the standard configuration of its manual (agreement, art. 177.4). Sheeting, a hoist or an odd geometry closes this route.
  • A written PMDM, prepared by a person with a university qualification that covers it (art. 177.1). Whether a home-country engineer qualifies is a question to settle with the client before mobilising; see scaffolding rules in Spain.

Erection itself is directed by a person with a qualifying university or vocational qualification and done by workers trained for it (art. 178.1, referring to RD 1215/1997, 4.3.7).

Gap to the wall: a stricter rule than you may expect

The 0.73 m frame clears the 60 cm minimum deck width. NTP 1015 treats a 20 to 30 cm gap to the wall as safe, with an inside guardrail or fall arrest beyond that. The collective agreement goes further: article 180.2 e) requires a 1 m metal guardrail, mid rail and 15 cm toe board on every side except those less than 20 cm from the facade. Plan the inside edge accordingly where render repair pushes the frames out.

Ties, sheeting and the base

Spain has no ties-per-square-metre rule. NTP 1016 refers to the standard configuration or a stability study and says tie rows are usually recommended no more than 4 m apart vertically. Following Blitz's pattern, the calculation gives 24 wall ties, four on each of the six frame lines. Netting or sheeting changes the number or type of ties, so recount if the job will be wrapped.

NTP 1015 recommends an access bay at least every 30 m; one bay of hatch decks is enough here. Two base jacks per frame line make 12, on compacted ground or sole boards and never on manhole covers, inspection chambers, bricks or drums (NTP 1016), which on a city pavement decides where the frame lines can go.

The parts list

Parts list: Layher Blitz, 15.35 m × 9 m

One straight wall, 15.35 m long and 9 m high, in 5 bays (5 × 3.07 m), 0.73 m deep, decks at 2.05 m, 4.05 m, 6.05 m, 8.05 m m: 139 m² of scaffold and 190 pieces in total, computed by ScaFix’s engine.

Parts list: Layher Blitz, 15.35 m × 9 m
PartLengthCount
Frames and standards
Frames2 m24
Top-lift guardrail posts4
Decks
Decks without ladder3.07 m17
Decks with ladder3.07 m4
Guardrails
Front guardrails3.07 m25
Toeboards
Toeboards3.07 m20
Diagonals
Diagonals3.07 m8
Diagonals3.07 m2
Ends
End guardrails8
End guardrail frames (top lift)2
End toeboards8
Wall ties and fittings
Wall ties24
Wall-anchor fittings24
Right-angle couplers for wall ties6
Base jacks and legs
Base jacks / legs12
Base transoms2

Fixed example computed by the app’s engine: no corners, openings, sheeting, hoists or loading bays. The manufacturer’s assembly instructions decide; this is planning, not structural approval.

Calculated with ScaFix, a scaffold planning app for browser and iPhone (115 scaffold systems from 57 manufacturers, checked 10 November 2026).

How do you read the list?

Read it line by line against the layout: the frames follow the six frame lines on four lifts, the decks include the hatch decks with ladders, the front guardrails add a stiffening row under the lowest deck, and the toe boards and diagonals follow the bays.

  • 24 frames: six frame lines times four lifts, plus four guardrail posts on top.
  • 21 decks, four of them hatch decks with ladders.
  • 25 front guardrails: one per bay on each decked lift, plus a row at first-frame height under the lowest deck, added for stiffness.
  • 20 toe boards and 10 diagonals in two lengths.

In total 190 pieces for about 139 m². The same facade in Layher Allround, a ringlock system, needs 355, because each bay is built from loose standards and ledgers. More wall sizes are in scaffold quantities by wall size, and Spanish hire rates in scaffolding cost.

Which documents will the site ask you for?

The site will ask for the system's product certificate and its assembly and maintenance manual, the PMDM or the manual pages showing the standard configuration, the inspection record before first use and after each change, and proof of your erectors' training (VII agreement, articles 179 and 180).

  • the system's product certificate and its assembly and maintenance manual (agreement, art. 180.2 a) and b)); how to check a certificate issued abroad is in certified scaffold in Spain;
  • the PMDM, or the manual pages showing the standard configuration you are building;
  • the inspection record before first use and after each change (art. 179.3);
  • proof of your erectors' training, plus the posting and contractor-register formalities if you send your own crew, covered in scaffolding rules in Spain.

This example is planning information, not structural approval. The manufacturer's assembly and use instructions, RD 1215/1997 (annex II, section 4.3) and the applicable collective agreement decide: outside the standard configuration you need a calculation and plan signed by a qualified person, and a person with a qualifying university or vocational qualification inspects the scaffold before it is put into service (4.3.8).

How ScaFix fits in

ScaFix is a planning tool. You enter the facades by their dimensions or import them from a PDF drawing, pick a system and get the scaffold in 3D with bays, lifts and a parts list like the one above; the iPhone app can also scan with LiDAR. It does not replace the calculation or the PMDM. To try your own facade, start with the scaffolding calculator.

Frequently asked questions

Is there a 7-day scaffold inspection rule in Spain?

No, not as a fixed number. The collective agreement (art. 179) requires inspection before first use, periodically, and after any change, period out of use, bad weather or other event that could affect stability, with the results documented. The inspector must hold a qualifying university or vocational qualification.

How do Spanish scaffold firms measure square metres?

As the scaffold run along the facade's most projecting line times the maximum working height, the CYPE measurement. Because bays come in whole units, the figure is a little above the facade area. A 15 × 9 m facade of 135 m² becomes about 139 m² of scaffold.

When does a scaffold in Spain need a plan de montaje?

When a prefabricated scaffold is more than 6 m from base to top or spans more than 8 m between supports (RD 1215/1997, annex II, 4.3.3 b). A certified system built to its standard configuration can use the manufacturer's instructions instead.

Can I use my own UK or German kit on a Spanish job?

Possibly. Under article 180.2 a) of Spain's construction collective agreement, a prefabricated system needs a conformity assessment by a competent body; without one it is limited to 6 m high and 8 m spans. Bring the certificate and the manual, and never mix it with another brand's components (NTP 1016).

Does TG20 count as a standard configuration in Spain?

Not as such: Spanish law speaks of a generally recognised standard configuration (RD 1215/1997, annex II, 4.3.2), which the INSST defines as a design matching a calculation note and tested by the manufacturer or an accredited laboratory. The safe route is the certified manufacturer's own configurations, which a Spanish coordinator can check against the manual.