For estimators
Scaffold take-off for a tender or bid: from the drawings to the quantities
ScaFix does the scaffold take-off for a tender from the wall measurements alone: for a 30 × 12 m façade with Layher Blitz it counts 339 m² of scaffold, 10 bays on 5 decked lifts and 382 parts. The guide covers what to measure, what to count and what to list beside the area.
By Ole Emil Frikstad Urstad · How the numbers are computed ·

How do you do a scaffold quantity take-off for a tender?
Take each elevation’s length and its height to the eaves from the drawings, turn every wall into bays and lifts in the chosen system’s own bay lengths, and add up scaffold area, hire weeks and extras. ScaFix counts this per wall: 339 m², 10 bays and 382 parts for a 30 × 12 m façade with Layher Blitz.
What does a tender ask for: an area, a period or a parts list?
The tender documents decide. A scaffold item is priced as a lump sum, as an area in m² with a hire period, or from an itemised schedule, and the documents say which. The take-off must produce the unit the bill asks for, with the measuring rule the contract names.
Whatever the unit, the same three quantities sit underneath: how much scaffold (area, or bays × lifts), for how long (weeks), and which extras. An estimator who has all three can answer any of the bill formats, and can see what a lump sum covers.
Where a national rule exists, it sets the method. In Germany the ATV DIN 18451 of VOB/C bills façade scaffolds in m², separately by type, purpose, load class and width class, and the hire per started week (Bauprofessor). The English summary of those rules is in scaffold measurement under DIN 18451.
Which measurements do you read off the drawings?
Per elevation: the length of the wall, the height from the ground to the eaves or to the highest working level, and the ground levels where the site slopes. Then everything that breaks the plain wall: balconies, bays, lower roofs to bridge, entrances that must stay open, and the edge of the roof if work goes on above the eaves.
The HSE’s list of what a user should give a scaffold contractor is a good checklist for the take-off sheet. It names the «period of time the scaffold is required to be in place», the «height and length and any critical dimensions which may affect the scaffold», the «number of boarded lifts», the «maximum working loads», the «type of access», and «whether there is a requirement for sheeting, netting or brickguards» (HSE: Scaffolding).
With a PDF floor plan, the wall lengths do not need to be typed: in ScaFix’s PDF import you choose the page, set the scale, trace the wall line and set the heights.

How do wall measurements become scaffold quantities?
ScaFix turns every wall into bays, lifts and parts in the bay lengths of the chosen system. For a 30 × 12 m façade it places 10 bays of 3.07 m with Layher Blitz, 5 decked lifts and 339 m² of scaffold; a 12 × 12 m gable takes 4 bays and 136 m².
By hand the steps are the same. Divide the wall length by the bay length and round up to whole bays, using the shorter bay lengths of the system to close the remainder. Set the lifts from the working heights. Multiply the scaffold length by the scaffold height for the area. Then count the parts per bay and lift from the manufacturer’s instructions.
| Counted by ScaFix | 30 × 12 m façade | 12 × 12 m gable | Block 30 × 12 m on plan, four sides |
|---|---|---|---|
| Bays, Layher Blitz | 10 | 4 | 28 |
| Scaffold area, Layher Blitz, m² | 339 | 136 | 950 |
| Parts, Layher Blitz | 382 | 178 | 1120 |
| Parts, Layher Allround | 763 | 338 | 2202 |
The four sides are counted as four separate straight walls, each with a ladder bay and without corner parts. The whole example, with a third system and the cost method, is in scaffolding for a block of flats.
How does the measuring rule change the area?
It can change it, so the rule belongs on the take-off sheet. ScaFix measures the scaffold itself: the bays it places times the scaffold height. A contract may measure the wall instead, or the outer faces of the scaffold, and may or may not deduct openings. The figure in the bid must follow the contract’s rule.
The German rule shows how much is in the wording. The 2023-09 edition of DIN 18451 takes the technically required dimensions at the outer faces of the scaffold, measures through openings such as windows and gateways whatever their size, and sets a single-bay scaffold at a length of at least 2.5 m (Bauprofessor).
For the area method wall by wall, with the difference between wall area and scaffold area, see how to calculate scaffold area.
What belongs in the take-off besides the area?
Everything the plain wall does not show: the hire period, access, loading, brackets, protection, ties and alterations. List each as its own line with a quantity, so that the bid and the later quote from the scaffold contractor can be compared line by line:
- Hire period. The weeks included with erection, and the number of weeks after that.
- Access. Ladder bays or stair towers, and how many.
- Loading. The load class the trades need, and any loading bay or hoist.
- Brackets and bridging. Inside-board brackets at balconies, beams over entrances and lower roofs.
- Protection. Sheeting or netting, a roof-edge lift, a pedestrian tunnel or fan over a pavement.
- Ties. The number the system’s tie pattern gives for the wall, as a quantity; the pattern itself is set by the manufacturer’s instructions.
- Alterations. Lifts moved or added during the job, counted per event.
The HSE names the same kind of items as «details of additional elements such as beamed bridges, fans, loading bays etc».
How do you check the take-off before the bid goes in?
Count it a second way. An area per m² and a parts list are two views of the same scaffold: if the list ScaFix gives for the walls holds 382 parts for the 30 × 12 m façade with Layher Blitz, an area of half or double 339 m² in the bid is a typing error, not a judgement.
Three checks to run: every elevation is on the sheet, including returns and courtyards; the height is the scaffold’s, not the storey count times a round number; and every extra has a quantity. Where take-offs go wrong, and how far a per-m² rule can be off, is covered in how accurate is a scaffold take-off.
For a bid in feet and inches the method is the same. ScaFix counts 10 Layher Blitz bays and 334 parts for a three-storey façade 100 ft (30.48 m) long and 9 m high, and the scaffolding calculator in feet takes the wall in imperial units.
Where does ScaFix fit in an estimator’s work?
ScaFix covers the quantity side: walls in, scaffold in 3D and a counted parts list out, for the systems in its catalogue, with the numbers computed by the same engine as the ScaFix web app. ScaFix Pro turns the list into a quote from your own price book, and the PDF report can be filed with the bid.
It does not write the bill of quantities, apply a contract’s measuring rule or design the scaffold. Tools that do other parts of the estimator’s job are compared in scaffolding estimating software.
This is a planning aid, not a structural calculation and not contract advice. ScaFix counts the scaffold in the set-up shown and checks no loads. The tender documents decide the unit and the measuring rule, and the manufacturer’s assembly instructions and a competent person decide how the scaffold is built and tied.
Frequently asked questions
Is a scaffold take-off measured on the wall or on the scaffold?
The contract decides. ScaFix measures the scaffold: for a 30 × 12 m façade with Layher Blitz the scaffold area is 339 m², against 360 m² of wall: the bays reach past the wall end, and the scaffold is measured to its own top, not to the eaves.
Germany’s DIN 18451 also measures at the outer faces of the scaffold. State the rule beside the figure in the bid.
Do windows and doors reduce the scaffold area?
Not in ScaFix’s count, and not under Germany’s DIN 18451, which measures through openings such as windows and gateways whatever their size. The scaffold stands in front of the opening all the same. If the tender documents set another rule for deductions, that rule decides the billed area, so check before pricing.
How many scaffold parts does a 30 m façade take?
ScaFix counts 382 parts with Layher Blitz and 763 with Layher Allround for a façade 30 m long and 12 m high, with a deck on every lift and a ladder bay. The difference comes from the build of the system: one frame in Blitz does the job of two standards, ledgers and transoms in a modular scaffold.
Can the take-off be done from a PDF drawing?
Yes. In ScaFix you open the PDF floor plan, choose the page, set the scale and trace the wall line; ScaFix suggests the scale and the outline when the drawing allows it. The scaffold and the parts list follow from those walls. A floor plan shows no heights, so the height is set per wall.
Sources
Primary sources used for this article, with the date each was read.
- HSE: Scaffolding (scaffold design: the information to supply, and what the designer should provide) (read 12 November 2026)
- Bauprofessor: Gerüste (Abrechnung nach ATV DIN 18451, Gebrauchsüberlassung, Nebenleistungen) (read 25 October 2026)
- Bauprofessor: Gerüstarbeiten (Auszüge ATV DIN 18451, Ausgaben 2016-09 und 2023-09) (read 25 October 2026)
- DIN Media: DIN 18451:2023-09, VOB Vergabe- und Vertragsordnung für Bauleistungen, Teil C: ATV Gerüstarbeiten (read 25 October 2026)