Every council sets its own fee for scaffolding on the pavement or road, in its own units: per licence, per street, per week, per month or per pole. This page lists ten councils in England, Wales and Scotland, each with the fee as the council publishes it, the date it prints and a link to the page.
By Ole Emil Frikstad Urstad · Checked against Highways Act 1980, s. 169 (1), (4), (5), (6); Roads (Scotland) Act 1984, s. 58 (1), (2) (24 November 2026) · How the numbers are computed ·

How much is a scaffold licence?
Each council sets its own fee. On 24 Nov 2026 Torfaen charged £64 per week, Bristol £90 for up to one month, Birmingham £133 plus £240 for up to 28 days and the City of London £720 per street for the first month. The fees come in different units and change, usually each April.
Ten councils at a glance
The basic fee for a scaffold on the highway as each council publishes it. Deposits, extensions and penalties are in the sections below.
| Council | Nation | Basic fee | Unit | Date the council prints |
|---|---|---|---|---|
| Birmingham | England | £133 + £240 | application + licence, up to 28 days, per street, developments up to £1 million | Charges 2026/27 |
| Bristol | England | £90 | licence up to one calendar month | none printed |
| City of London | England | £720 | per street, up to one month | 1 April 2026 |
| Hammersmith & Fulham | England | £660 | per month (single frontage or site up to 15 m) | from 1 April 2026 |
| Islington | England | £540 | management fee, Level 1, up to three months, per street | none printed |
| Sheffield | England | £77 | permit, domestic property | none printed |
| Gwynedd | Wales | £116 | per month, up to 10 m per scaffold | none printed |
| Torfaen | Wales | £64 | per week or part of a week | none printed |
| Edinburgh | Scotland | £294 | per 28 days (materials and scaffolding) | 1 April 2026 to 31 March 2027 |
| Highland | Scotland | £122 | first week, scaffolding under 15 m | page modified 31 March 2026 |
Who issues the licence, and under which law?
The highway authority, which for most roads is the council. In England and Wales, section 169 of the Highways Act 1980 says no one may erect or retain scaffolding on or over a highway that obstructs it unless authorised by a licence in writing from the highway authority.
The licence may contain such terms as the authority thinks fit. Erecting or keeping scaffolding there without a licence, or breaking its terms, is an offence punishable by a fine.
The licence holder must also see that the structure is adequately lit from half an hour after sunset to half an hour before sunrise and follow the authority's directions on traffic signs, unless the scaffold keeps the clearances in subsection (6). Section 169 sets no fee: each council charges under its own schedule of fees and charges.
In Scotland the rule is section 58 of the Roads (Scotland) Act 1984: erecting staging or scaffolding which projects over a part of a road needs the written permission of the roads authority, and councils there call it a road occupation permit. In Northern Ireland, Article 72 of the Roads (Northern Ireland) Order 1993 requires the consent of the Department, not a council; this page has no Northern Ireland fees.
What does each council charge?
The fees below are copied from each council's own page or fee schedule, in the council's own units. A dash in the date column means the page prints no fee year; read those rows as «as shown on 24 Nov 2026».
| Council | Fee as published | What it covers | Date printed | Source |
|---|---|---|---|---|
| Birmingham | £133 application fee + £240 | scaffolding up to 28 days, one street, developments up to £1 million | Charges 2026/27 | fee schedule |
| Birmingham | £133 application fee + £575 | scaffolding from 29 days, developments up to £1 million, plus a bond and £133 bond administration | Charges 2026/27 | guidance note |
| Bristol | £90 / £144 / £214 / £856 | up to 1, 2, 3 months / 9 to 12 months | – | council page |
| City of London | £620 / £720 / £725 | per street: up to 7 days / up to one month / each month after | 1 April 2026 | charges |
| Hammersmith & Fulham | £660 / £1,170 | per month: single frontage or site up to 15 m / site over 15 m | from 1 April 2026 | fees page |
| Islington | £540 to £1,520, then 40 % of the deposit | management fee by deposit level (Levels 1–4, then Level 5), up to three months, per street | – | council page |
| Sheffield | £77 / £118.50 / £202 | domestic / commercial under 10 m per street / commercial over 10 m per street | – | council page |
| Gwynedd | £116 / £135 / £153 | per month: up to 10 m / 10 to 50 m / over 50 m per scaffold | – | council page |
| Torfaen | £64 | per week or part of a week, paid in advance | – | council page |
| Edinburgh | £294 | per 28 days, materials and scaffolding or hoarding | 1 April 2026 to 31 March 2027 | schedule |
| Highland | £122 then £74 / £187 then £142 | first week then each extra week: under 15 m / over 15 m | page modified 31 March 2026 | council page |

Why can't the fees be compared as one number?
Because they are charged for different things. Bristol and the City of London price by duration, Gwynedd and Sheffield by size, Hammersmith & Fulham by month and site size, Islington by the number of standards on the highway, and Edinburgh and Highland by 28-day or weekly periods.
A scaffold that turns a corner can count as two streets: Birmingham charges £133 per additional street frontage (fee schedule).
Deposits and bonds come on top in several places. Islington takes a deposit of £50 per pole placed on the highway, and the deposit level sets the management fee (Islington). Hammersmith & Fulham states «a minimum of £750» for the damage deposit in its text and «£1000+» in its value column (fees page). Birmingham requires a bond for every licence of 29 days or more (guidance note).
What does a late or missing licence cost?
More than an ordinary one. Birmingham charges a retrospective licence at twice the equivalent pre-approved value (fee schedule), and Bristol charges £103 for an emergency licence applied for fewer than 3 working days ahead and £157 for every month a scaffold stood without a licence (Bristol).
Torfaen sets an initial charge of £209 for non-compliance, and a minimum removal fee of £160 where the authority considers it appropriate (Torfaen). Edinburgh adds 25 % to applications received within its minimum notice periods (schedule).
How much notice do councils want?
From 24 hours to 20 working days. Torfaen asks for at least 24 hours, Bristol and Gwynedd for 5 working days, Islington for 10 working days and Edinburgh for 20 working days for scaffolding, where an application made inside the notice period costs 25 % more (schedule). The table gives each council's own wording.
| Council | Minimum notice | Source |
|---|---|---|
| Bristol | 5 working days | council page |
| Islington | 10 working days | council page |
| Gwynedd | 5 working days | council page |
| Torfaen | 24 hours | council page |
| Edinburgh | 20 working days for scaffolding | schedule |
How big is a typical scaffold on the pavement?
A worked example from ScaFix: a 15 m house or shop elevation, 10 m high, in Kwikstage. ScaFix plans 5 bays with a run of 14.64 m along the pavement and a system width of 0.76 m, so the standards stand on about 11.2 m² of footway before any fans, barriers or walkway the council asks for.
That run is what decides a size band. In Gwynedd, whose fees are by metres per scaffold, it falls in the 10 to 50 m band (Gwynedd). Other councils band by «site» or «property», so ask which measure they use before you apply. ScaFix gives you the run of every elevation and the system width for the plan you send with the application; it is a planning aid, not an application, a licence or a structural approval.
Which councils are not on the list, and why?
Only councils whose own page could be opened and read on 24 Nov 2026 are listed. Camden, Manchester, Glasgow, Cardiff, Swansea, Newport and Kensington & Chelsea blocked automated reading that day, Westminster's scaffolding page states no fee, and Liverpool's fee page was last updated in 2023, so it is left out as possibly out of date.
Edinburgh shows two figures: its directory page still gives £190 for the first 28 days, while its dated schedule for 2026/27 gives £294 per 28 days. The table uses the dated schedule, and the schedule itself warns that fees and charges may change, typically on 1 April each year (schedule). Check the council's page on the day you apply; for the wider question of when a licence is needed at all, see do I need a scaffolding permit.
Frequently asked questions
Do I need a licence for scaffolding on the pavement?
Yes, in England and Wales, if it is on or over a highway and obstructs it: section 169 of the Highways Act 1980 requires a written licence from the highway authority, usually the council. In Scotland section 58 of the Roads (Scotland) Act 1984 requires the roads authority's written permission, and in Northern Ireland the Department's consent.
Which council on this page charges the least?
No single council is the cheapest for every job, because the units differ and the scaffold's duration and size decide the fee. On 24 Nov 2026 Torfaen charged £64 per week, Sheffield £77 per domestic permit and Bristol £90 for up to one calendar month.
For a scaffold standing many months, compare each council's whole ladder, deposits and extensions, not the first figure.
Do scaffold licence fees change every year?
Usually, yes. Most councils set their fees and charges for a financial year, and Edinburgh's 2026/27 schedule says fees may change, typically on 1 April each year. Some council pages print no year at all, so check the fee on the day you apply rather than relying on a figure from an older quote.
Does a scaffold round a corner need two licences?
Yes, at councils that charge per street. Birmingham adds £133 per additional street frontage, and the City of London and Islington price their licences per street, so a corner scaffold on two roads counts as two frontages there. Other councils word it differently, so ask the council before you apply.
Sources
Primary sources used for this article, with the date each was read.
- Highways Act 1980, section 169 (read 24 November 2026)
- Roads (Scotland) Act 1984, section 58 (read 24 November 2026)
- Roads (Northern Ireland) Order 1993, Article 72 (read 24 November 2026)
- Birmingham City Council: Highways Specified Licence Charges 2026/27 (PDF) (read 24 November 2026)
- Birmingham City Council: Fees and Charges – Applicant Guidance note (PDF) (read 24 November 2026)
- Bristol City Council: Apply for a scaffolding licence (read 24 November 2026)
- City of London: Charges for Activities on the Public Highway, 1 April 2026 (PDF) (read 24 November 2026)
- Hammersmith & Fulham: Highways licensing fees and charges (read 24 November 2026)
- Islington Council: Scaffolding or gantry (read 24 November 2026)
- Sheffield City Council: Apply to occupy the road during building work (read 24 November 2026)
- Gwynedd Council: Scaffolding (read 24 November 2026)
- Torfaen County Borough Council: Scaffolding and Hoarding Permits (read 24 November 2026)
- City of Edinburgh Council: Road services schedule of charges 2026/27 (PDF) (read 24 November 2026)
- The Highland Council: Permit to occupy a public road (read 24 November 2026)