Do you need scaffolding to replace windows?

Not always. Under the Work at Height Regulations a ladder may be used only where a risk assessment shows the risk is low and the task short, so heavy upstairs frames and sealed units usually come out from a scaffold or tower. The installer decides after a survey; a scaffold for one 9 m elevation is 3 bays.

In the UK, replacing ground-floor windows rarely needs a scaffold; first-floor windows often do, because the law lets a fitter work from a ladder only where a risk assessment shows the risk is low. For the front of a two-storey house, 9 m long with the eaves at 5.2 m, ScaFix plans 3 bays of Kwikstage with decks at 2.6 m and 4.6 m.

· How the numbers are computed ·

Layher Blitz scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Layher Blitz around the example house, as ScaFix draws it in 3D.

When can upstairs windows be fitted from a ladder?

Only where a risk assessment has shown the risk is low, and the use is short or the site leaves no better choice. The Work at Height Regulations 2005 make a ladder the last resort for work at height, and an employer must give collective protection measures priority over personal protection measures when choosing the equipment.

Regulation 7 sets that order, and Schedule 6 adds that an employer must ensure a ladder is used for work at height only if a risk assessment has demonstrated that the use of more suitable work equipment is not justified because of the low risk, and either the short duration of use or features on site that cannot be altered. The HSE puts it the same way: ladders can be a sensible and practical option for low-risk, short-duration tasks, but they should not automatically be the first choice. These regulations apply in England, Wales and Scotland; Northern Ireland has the Work at Height Regulations (Northern Ireland) 2005, which this page does not cover.

Taking out an old frame and lifting in a double-glazed unit at first-floor height is rarely a few minutes' work, and the fitter needs both hands. For upper floors that points to a scaffold or a tower, while ground-floor windows can be reached from the ground. Whether a frame goes in from inside or outside depends on the window and the installer; ask in writing whether the quote includes access equipment.

How much scaffolding does it take to replace the windows of a house?

For the front elevation of a two-storey detached house, 9 m long with the eaves at 5.2 m, ScaFix plans 3 bays of Kwikstage (2 × 3.05 m + 1 × 2.44 m), boarded at 2.6 m and 4.6 m, 48 m² of scaffold face and 129 parts. Replacing every window means every elevation, planned below as the whole house.

Both runs are Kwikstage at a system width of 0.76 m. The house in the second column is the same house all round, 9 × 7 m with a hipped roof, planned with its four real corners. Both runs use the same engine and set-up; the whole house can also be scaffolded one or two elevations at a time if the installer works round the house.

ScaFix count, KwikstageFront elevation only, 9 × 5.2 mWhole house, 9 × 7 m, eaves 5.2 m
System width0.76 m0.76 m
Bays316
Decked lifts2 (2.6 m and 4.6 m)2 (2.6 m and 4.6 m)
Scaffold face48 m²202 m²
Decks and boards733
Standards24120
Ties624
Parts in total129597

For your own wall, the scaffolding calculator gives the bays, lifts, decked levels and area of one wall in the browser; how much scaffolding do I need explains how a wall turns into bays and lifts.

Plettac SL 70/100 scaffolding around a house of 11.4 × 5.3 m with a gabled roof (eaves 4.5 m, ridge 6 m), drawn by the ScaFix 3D model
Plettac SL 70/100 around the example house, as ScaFix draws it in 3D.

Where should the boards sit for fitting windows?

A little below the sill of the window being fitted, so the fitter lifts the unit over the sill, not above the head. ScaFix places the decks on the system's own lift grid, here 2.6 m and 4.6 m; it does not move a deck to your sill heights, so compare the two before erection.

Measure the first-floor sills from the ground and give the heights to the scaffolder with the order. If the sill sits well above a lift, the scaffolder can set that lift higher or add a lift; settle it before erection, because changing a boarded lift later is a scaffold alteration that the scaffolder has to make.

Where do the ties go when the windows are being changed?

Into solid wall between the openings, never into the frames being replaced. ScaFix counts the ties by the system's tie pattern (6 on the front elevation) but does not know where the windows are, so the positions are for the scaffolder to set on site.

Ties fixed in a window opening would sit exactly where the old frame comes out and the new one goes in. Tell the scaffolder which openings are being replaced and in what order, so the ties are placed on the brickwork between them or moved by the scaffolder when the work reaches that window. The HSE says scaffolds must be altered only by competent people, and if a tie is removed to allow work to proceed, an equivalent tie must be provided nearby. More on tie patterns: scaffold ties and anchoring.

Which checks and permits apply?

The scaffold must have been inspected in that position within the previous 7 days before anyone works from it where they could fall 2 m or more, and again after anything that may have made it unsafe. A scaffold on the pavement needs a licence, which the builder or scaffolding company gets.

The 7-day rule is regulation 12(4); the HSE adds inspection before first use and after high winds. In England and Wales, a scaffold on the street needs a licence from the highway authority under section 169 of the Highways Act 1980. GOV.UK says it is the responsibility of the builder or scaffolding company to get a licence, and the householder's to check they have it and that it lasts until the work is finished.

How long will the scaffold stay up?

As long as the windows take, plus erecting and striking the scaffold, and the installer's programme sets that number. Scaffold hire is quoted per week, so the quote should state the weeks included and the rate for each extra week if fitting is delayed, for example because the new frames arrive late.

Ask who books the scaffold: when the window company arranges it, ask whether the hire and the licence are inside its price; when you hire the scaffolder yourself, you also agree the start date with the installer. Bad weather can push glazing back, so ask how lost days are charged before you sign.

ScaFix is a planning aid for the quantities of a scaffold; it is no structural calculation, no design and no compliance check. Lift heights against your sills, tie positions between the openings, loads and the ground under the base plates are for the scaffolder to set, under the regulations and the maker's instructions.

Frequently asked questions

Do I need scaffolding to replace first-floor windows?

Yes, often. The regulations allow a ladder only where a risk assessment shows the risk is low and the task short, which fitting a sealed unit upstairs rarely is. The installer decides after a survey; for a 9 m front ScaFix plans 3 bays with decks at 2.6 m and 4.6 m.

Can window fitters work from a ladder?

Yes, but only for low-risk, short-duration tasks: Schedule 6 of the Work at Height Regulations requires a risk assessment showing that more suitable equipment is not justified because of the low risk, and either the short duration or site features that cannot be changed. The HSE adds that a ladder should not automatically be the first choice.

Who arranges the scaffolding for new windows?

Usually the window company, as part of its quote, or the homeowner hires a scaffolder directly. Either way the builder or scaffolding company gets the pavement licence where one is needed, GOV.UK says, and the householder checks it exists. Ask in writing whether access equipment is included and how extra weeks are charged.

Will the scaffold ties get in the way of the new windows?

They can, if they are fixed in the openings being replaced. Tell the scaffolder which windows are changing so the ties go into solid wall between the openings. ScaFix counts ties by the system's tie pattern but does not know where your windows are, so the positions are set by the scaffolder on site.