Skip to content

Guide · 9 of 24

How to plan on sloping and stepped ground

Select the wall and switch on Sloping ground under Measurements. Type the ground height at the left and right end, for example 0 and 1.2 m. ScaFix sets the scaffold on the ground and recalculates the parts list. Read the notes under Scaffold: where ScaFix has the manufacturer's limit, they show the base jack height and what the source allows.

ScaFix Basic or Pro See the plans and what they cost

What you need

  • ScaFix Basic or Pro
  • The height difference along the wall (measured with a laser, a level or from a drawing).

Step by step

  1. Step 1 Open Measurements for the wall

    Select the wall. Under Measurements you find Sloping ground with the fields for the ground at the left and at the right.

    The Measurements tab of wall 1 with Sloping ground and the fields Ground at left and Ground at right.
  2. Step 2 Enter the ground height

    Switch on Sloping ground and type the height at each end, here 0 m on the left and 1.2 m on the right. The scaffold in the 3D picture follows the ground, and the parts list is recalculated.

    Sloping ground switched on with ground at left 0 and ground at right 1.2, and the house with its scaffold in 3D.
  3. Step 3 Read the notes

    Under Scaffold ScaFix shows how high the scaffold stands on its base jack and what the source allows, for HAKI Ram in the example «the source allows at most 0.57 m (RISE C900627 condition 5)». The figure applies to this system. Read the note and check the set-up against the manufacturer's instructions.

Common mistakes

  • The heights entered the wrong way round. Left and right are as you see the wall from outside, with its number in the 3D picture.
  • Stepped ground along one wall. Split the wall into two connected walls, each with its own ground height.
  • The base jack note is ignored. It says what the system allows; a higher build-up must follow the manufacturer's instructions.