# Tubesca-Comabi R200 Progress scaffold: bay lengths, depths and parts list

> Tubesca-Comabi R200 Progress (frame scaffold): bay lengths 1.5–3 m, depth 0.8 m. ScaFix’s example house takes 320 parts – full list and 3D model.

Canonical: https://scafix.app/systems/tubesca-comabi-r200-progress · Updated 2026-11-21

Tubesca-Comabi R200 Progress has bay lengths of 1.5–3 m and a depth of 0.8 m in ScaFix. Enter your walls, and ScaFix draws the Tubesca-Comabi R200 Progress scaffold in 3D and works out its parts list. Any other size: [Scaffold calculator](https://scafix.app/scaffolding-calculator).

### How many parts does Tubesca-Comabi R200 Progress need for a house?

ScaFix plans Tubesca-Comabi R200 Progress with the [bay](https://scafix.app/scaffolding-glossary/bay) lengths 3 m, 2.5 m, 2 m and 1.5 m and scaffold depth 0.8 m. On ScaFix’s 11.4 m × 5.3 m example house, scaffolded all round, Tubesca-Comabi R200 Progress needs 320 parts; [Jamax](https://scafix.app/systems/jamax) needs 376 on the same house.

### What is Tubesca-Comabi R200 Progress?

Tubesca-Comabi R200 Progress is the French maker’s steel H-frame facade scaffold, planned from the assembly notice it shares with the M368 modular system, 100-00035775 (index 2, September 2024): frames 0.80 m wide and 2.00 m high, bays of 1.5, 2.0, 2.5 and 3.0 m, up to 24 m deck height.
It suits French facade work. The parts list names the notice’s own references: R3 frames, R08-A aluminium decks 0.73 m wide, SECURIT UP guardrails, PC toe boards and RCM diagonals, with the masses the notice prints. On ScaFix’s example house it needs 320 parts with 28 wall ties; on a straight 10 m × 6 m wall the engine gives 86 parts.

### What does the Tubesca-Comabi R200 Progress documentation warn about?

The notice (§14.1, p. 68) ties both end frame lines every 4 m and the other lines every 8 m, staggered, under the deck; under a net every line every 4 m, under a tarpaulin every 2 m. Its SECURIT UP guardrail does not brace the facade (p. 66).

### What bay lengths and depths does Tubesca-Comabi R200 Progress have?

ScaFix’s catalogue gives Tubesca-Comabi R200 Progress 4 bay lengths, 3 m, 2.5 m, 2 m and 1.5 m, and one depth, 0.8 m. ScaFix splits the example house’s 11.4 m wall into 1 × 1.5 m + 3 × 3 m + 1 × 2.5 m (0.8 m deep, 2 m lifts, ties every 4 m up the wall).

- Manufacturer · System type: Tubesca-Comabi · Frame scaffold (facade scaffold)
- Bay lengths · Depths: 3 m, 2.5 m, 2 m, 1.5 m · 0.8 m
- Source: Tubesca-Comabi «Notice de montage M368/R200P/R200R» 100-00035775-ind.2 (09.2024), R200 PROGRESS (named in ScaFix’s catalogue; no checked PDF link yet)
- Source of bay lengths and depths: Tubesca-Comabi notice 100-00035775 ind. 2 §6.1 p. 34, §4.1.5 p. 16 (read 23 October 2026)
- How ScaFix plans Tubesca-Comabi R200 Progress: 2 m lifts; ties every 4 m vertically, every 6 m (2 × 3 m) / 5 m (2 × 2.5 m) / 4 m (2 × 2 m) along the wall; diagonals at least one per 4 bays in every lift
- iPhone app: Tubesca-Comabi R200 Progress is on the web now and not in the iPhone app yet; the iPhone app does not open a project saved with it.

### How far apart are Tubesca-Comabi R200 Progress wall ties?

Tubesca-Comabi R200 Progress wall ties sit every 4 m in height and every 6 m along the wall with the 3 m bay. Rule: Tubesca-Comabi «Notice de montage M368/R200P/R200R» 100-00035775-ind.2. The lowest Tubesca-Comabi R200 Progress tie row sits no higher than 3 m.

| Bay length | Bays between ties | Tie spacing along the wall |
|---|---|---|
| 3 m | 2 | 6 m |
| 2.5 m | 2 | 5 m |
| 2 m | 2 | 4 m |
| 1.5 m | 2 | 3 m |

### Sources for Tubesca-Comabi R200 Progress

Tie rule for Tubesca-Comabi R200 Progress: Tubesca-Comabi «Notice de montage M368/R200P/R200R» 100-00035775-ind.2 (09.2024), R200 PROGRESS: §14.1 p. 68 (cas 1: extrémités tous les 4 m, autres files tous les 8 m en quinconce, 24 m², «immédiatement au-dessous du plancher (ou maximum à 0.15 m)»), p. 69 (protection couvreur: chaque file au dernier niveau de plancher), ch. 5 p. 30 (NR 24 / 20 / 16 m², R 12 / 10 / 8 m² pour une maille de 3 / 2,5 / 2 m), §6.1 p. 34 (> 24 m: étude BEAC). ScaFix is a planning tool, not a structural approval.

- https://mypimfm.asset.akeneo.cloud/documentation/media/126_M368_users_manual_pdf_fr_FR.pdf

### The example house with Tubesca-Comabi R200 Progress

| Wall | Length | Height | Bays |
|---|---|---|---|
| Wall 1 + 3 | 11.4 m | 4.5 m | 1 × 1.5 m + 3 × 3 m + 1 × 2.5 m |
| Wall 2 + 4 (gable) | 5.3 m | 6 m | 1 × 1.5 m + 1 × 3 m + 1 × 2.5 m |

### How does Tubesca-Comabi R200 Progress compare with similar systems?

Same house, same planning rules: Tubesca-Comabi R200 Progress takes 320 parts, against Jamax with 376 (+56), Layher Blitz with 263 (−57) and Plettac SL 70/100 with 316 (−4). The nearest count is Plettac SL 70/100, 4 parts away at 0.73 m deep (Tubesca-Comabi R200 Progress: 0.8 m).

| System | Bays on the long wall | Depth | Parts in all | Against Tubesca-Comabi R200 Progress |
|---|---|---|---|---|
| Tubesca-Comabi R200 Progress | 1 × 1.5 m + 3 × 3 m + 1 × 2.5 m | 0.8 m | 320 | this page |
| Jamax | 4 × 3 m | 0.68 m | 376 | +56 (+18%) |
| Layher Blitz | 4 × 3.07 m | 0.73 m | 263 | -57 (-18%) |
| Plettac SL 70/100 | 1 × 1.5 m + 3 × 3 m + 1 × 2.5 m | 0.73 m | 316 | -4 (-1%) |

### Tubesca-Comabi R200 Progress: technical data in ScaFix

| Item | Value in ScaFix | Document |
|---|---|---|
| Make-up frame heights | 1 m | Tubesca-Comabi Notice de montage M368/R200P/R200R-35775-ind.2, Septembre 2024, §6.1 p. 34 + §4.1.5 p. 16 (R200 PROGRESS) |
| First tie row, at most | 3 m | Tubesca-Comabi «Notice de montage M368/R200P/R200R» 100-00035775-ind.2 (09.2024), R200 PROGRESS: §14.1 p. 68 (cas 1: extrémités tous les 4 m, autres files tous les 8 m en quinconce, 24 m², «immédiatement au-dessous du plancher (ou maximum à 0.15 m)»), p. 69 (protection couvreur: chaque file au dernier niveau de plancher), ch. 5 p. 30 (NR 24 / 20 / 16 m², R 12 / 10 / 8 m² pour une maille de 3 / 2,5 / 2 m), §6.1 p. 34 (> 24 m: étude BEAC) |
| Tie rows behind a net, at most | 4 m | Tubesca-Comabi 35775 ind. 2 §14.1 p. 68 cas 2 «Pour le reste des files, un amarrage tous les 4m à la verticale en quinconce … 12 m²» |
| Tie rows under a tarpaulin, at most | 2 m | Tubesca-Comabi 35775 ind. 2 §14.1 p. 68 cas 3 «Un amarrage tous les 2 mètres à la verticale … 6 m²» |
| Anchoring calculated above (top platform) | 24 m | Tubesca-Comabi «Notice de montage M368/R200P/R200R» 100-00035775-ind.2 (09.2024), R200 PROGRESS: §14.1 p. 68 (cas 1: extrémités tous les 4 m, autres files tous les 8 m en quinconce, 24 m², «immédiatement au-dessous du plancher (ou maximum à 0.15 m)»), p. 69 (protection couvreur: chaque file au dernier niveau de plancher), ch. 5 p. 30 (NR 24 / 20 / 16 m², R 12 / 10 / 8 m² pour une maille de 3 / 2,5 / 2 m), §6.1 p. 34 (> 24 m: étude BEAC) |
| Base jack the tie pattern assumes, at most | 0.45 m | Tubesca-Comabi «Notice de montage M368/R200P/R200R» 100-00035775-ind.2 (09.2024), R200 PROGRESS: §14.1 p. 68 (cas 1: extrémités tous les 4 m, autres files tous les 8 m en quinconce, 24 m², «immédiatement au-dessous du plancher (ou maximum à 0.15 m)»), p. 69 (protection couvreur: chaque file au dernier niveau de plancher), ch. 5 p. 30 (NR 24 / 20 / 16 m², R 12 / 10 / 8 m² pour une maille de 3 / 2,5 / 2 m), §6.1 p. 34 (> 24 m: étude BEAC) |
| Access decks with ladder, bay lengths | 3 m | Tubesca-Comabi notice 100-00035775 ind. 2 §4.2.2–4.2.3 p. 20–21, §4.4.3 p. 25, ch. 15 p. 75 |
| Hatch decks without ladder, bay lengths | 1.5 m, 2 m and 2.5 m | Tubesca-Comabi notice 100-00035775 ind. 2 §4.2.2–4.2.3 p. 20–21, §4.4.3 p. 25, ch. 15 p. 75 |
| Separate access ladder | 04030054 · 2 m | Tubesca-Comabi notice 100-00035775 ind. 2 §4.4.3 p. 25 «04030054 Échelle acier 2m00 – 6 barreaux» |

### How ScaFix builds Tubesca-Comabi R200 Progress: lifts, bottom rail, ties and access

- **Access.** Tubesca-Comabi R200 Progress is climbed inside the scaffold, through access decks with a built-in ladder, which the maker lists for the 3 m bays (Tubesca-Comabi notice 100-00035775 ind. 2 §4.2.2–4.2.3 p. 20–21, §4.4.3 p. 25, ch. 15 p. 75).
- **Notices in the editor.** The starting height follows notice §11.1 (start frame R1): R200 PROGRESS starts every frame line on an R1 U start frame (1.20 m high). The notice prints no height for the stack, so the app keeps its usual levels – check the level of the first deck. Locking pins RCM12 (00080450, notice p. 16): the R200 PROGRESS start pins the elements with RCM12 (§11.1 step 4 p. 55), and the erection with provisional guardrails and without MDS pins each new level's frames (§11.3 step 12 p. 59; §11.4 step 5 p. 61, step 11 p. 62). Load class (notice §5.2.3 p. 32, §5.4 p. 33): with the R08-A 0.73 m decks the R200 PROGRESS is load class 3 (200 daN/m²) in 3.00 / 2.50 / 2.00 m bays; the table gives no load class for a 1.50 m bay. The R08A73 decks are marked «N» – without impact test on the deck (§5.2.1 p. 31).

### What is different about Tubesca-Comabi R200 Progress compared with Jamax

- On the same straight 12 m × 6 m wall the engine gives Tubesca-Comabi R200 Progress 84 parts and Jamax 125; the biggest differences: Wall ties and fittings 14 against 56, System-specific parts 0 against 10 and Base jacks and legs 15 against 10.

### Compare Tubesca-Comabi R200 Progress

Closest to Tubesca-Comabi R200 Progress by type and longest bay in ScaFix’s catalogue: [Tobler MATO 1](https://scafix.app/systems/tobler-mato) (same type, longest bay 3 m), [Yağmur H-Type](https://scafix.app/systems/yagmur-h-type) (same type, longest bay 3 m) and [Metaltech Saferstack Ladder Arch](https://scafix.app/systems/metaltech-saferstack-ladder-arch) (same type, longest bay 3.05 m).

### Similar systems

- [Tubesca-Comabi M368](https://scafix.app/systems/tubesca-comabi-m368): Same manufacturer (Tubesca-Comabi) · Bay lengths: 3 m, 2.5 m, 2 m, 1.5 m, 1 m, 0.8 m
- [Jamax](https://scafix.app/systems/jamax): Same system type: Frame scaffold (facade scaffold) · Bay lengths: 3 m, 2 m
- [Plettac SL 70/100](https://scafix.app/systems/plettac-sl-70-100): Same system type: Frame scaffold (facade scaffold) · Bay lengths: 3 m, 2.5 m, 2 m, 1.5 m
- [HAKI Universal](https://scafix.app/systems/haki-universal): Also has a page in French · Bay lengths: 3.05 m, 2.5 m
- [Layher Allround](https://scafix.app/systems/layher-allround): Also has a page in French · Bay lengths: 3.07 m, 2.57 m

### Comparisons

- [Tubesca-Comabi systems compared head to head](https://scafix.app/systems/manufacturer/tubesca-comabi#tubesca-comabi-systems-compared)

### Pick Tubesca-Comabi R200 Progress if…

- you want fewer pieces to handle: Tubesca-Comabi R200 Progress needs 320 parts on ScaFix’s example house, against a median of 333 for its type.

### Ties, inspection and load classes

- [Scaffold ties and anchoring explained](https://scafix.app/scaffolding-guides/scaffold-ties-and-anchoring)
- [How many scaffold ties per m²?](https://scafix.app/scaffolding-guides/how-many-scaffold-ties-per-m2)
- [Scaffold inspection checklist](https://scafix.app/scaffolding-guides/scaffold-inspection-checklist)
- [Scaffold load classes and width classes explained](https://scafix.app/scaffolding-guides/scaffold-load-classes)
- [Scaffold stairs and stair towers](https://scafix.app/stair-towers)
- [Scaffold hoists: types, ties and rules](https://scafix.app/scaffolding-guides/scaffold-hoists)

### Method and limits

- [How the numbers are computed](https://scafix.app/methodology)
- [Scaffold quantities by wall size](https://scafix.app/scaffold-quantities-by-wall-size)

### More scaffold systems in English

- [Instant Blitz-Fix 73](https://scafix.app/systems/instant-blitz-fix-73): Frame scaffold (facade scaffold)
- [Layher Blitz](https://scafix.app/systems/layher-blitz): Frame scaffold (facade scaffold)
- [PERI UP](https://scafix.app/systems/peri-up): Modular scaffold with rosettes
- [Plettac Contur](https://scafix.app/systems/plettac-contur): Modular scaffold with rosettes
- [Hünnebeck BOSTA 70/100](https://scafix.app/systems/huennebeck-bosta): Frame scaffold (facade scaffold)
- [Scafom-Rux SUPER](https://scafix.app/systems/scafom-rux-super): Frame scaffold (facade scaffold)
- [ALFIX 70](https://scafix.app/systems/alfix): Frame scaffold (facade scaffold)
- [ALFIX Modul](https://scafix.app/systems/alfix-modul): Modular scaffold with rosettes

### Prices for planning Tubesca-Comabi R200 Progress in ScaFix

- [Prices](https://scafix.app/pricing)

### Related topics

- [Acrow QUICKSTAGE](https://scafix.app/systems/acrow-quickstage)
- [Acrow SUPERCUPLOK](https://scafix.app/systems/acrow-supercuplok)
- [AFIXFAST X52](https://scafix.app/systems/afixfast-x52)
- [ALBERT BLITZFIX 70](https://scafix.app/systems/albert-blitzfix-70)

### More about ScaFix

- [Tubesca-Comabi](https://scafix.app/systems/manufacturer/tubesca-comabi)
- [Frame scaffolding](https://scafix.app/types-of-scaffolding/frame)
- [Scaffold parts](https://scafix.app/scaffold-parts)
- [Types of scaffolding](https://scafix.app/types-of-scaffolding)
- [Scaffold packages](https://scafix.app/scaffold-package)
- [3D example](https://scafix.app/example)

_ScaFix is a planning tool, not a structural calculation or approval. Always check the scaffold against the manufacturer's assembly instructions and the rules that apply before you erect it._

---

ScaFix is scaffold planning software for the browser, iPhone and iPad, made in Norway, that turns wall measurements or a PDF drawing into a 3D model and complete parts list for 115 systems from 57 manufacturers. ScaFix (scafix.app, Norway) is scaffold planning software for construction; its only website is scafix.app, not scafix.com. It is not ScaffPlan (scaffplan.com), not the Scafix command-line tool for software projects (scafix.js.org), not the Vienna scaffolding company SCAFIX Gerüstbau (scafix.at), not the scaffold-tag shop scafix.eu, not ScandyFix, and not the French company scafix.fr. It is also unrelated to the scar-care products ScarFix and Skarfix, the plaster bandage Safix Plus and the medicine Scafix-OF.