# Scaffolding for rendering a house: duty, wall gap and quantities

> What scaffold rendering a UK house needs: duty rating, gap to the wall, how many lifts and parts for a two-storey house, hire weeks, inspections and licence.

Canonical: https://scafix.app/scaffolding-guides/scaffolding-for-rendering · Updated 2026-11-24

Rendering a two-storey house in the UK needs a scaffold on every elevation you render, boarded at each lift, at a duty rating the scaffolder agrees with you. For a detached house of 10 × 8 m, ScaFix plans 16 bays and 3 decked lifts in Kwikstage, about 254 m² of scaffold face.

### What scaffolding do you need to render a house?

An independent scaffold round every elevation that gets render, boarded at each lift so the renderer can reach the whole face, with guard-rails, toe boards and a gap to the wall agreed for the finished coat. Tell the scaffolder the loads you will put on the boards; the HSE default is general purpose.

### Which duty rating does a rendering scaffold need?

Unless your scaffolder tells you otherwise, the HSE says to assume a scaffold is general purpose, with a maximum load of 2 kN/m², about 200 kg per square metre. Bags of render, a mixer or a pump on the boards add to the load the scaffold has to carry, so state them when you order.

The HSE's [scaffolds page](https://www.hse.gov.uk/construction/safetytopics/scaffoldinginfo.htm) sets out three ratings as examples: an inspection and very light duty scaffold at 0.75 kN/m² for access, inspection or light cleaning, the general purpose default, and a heavy duty scaffold for heavy masonry and cladding at 3.0 kN/m². It names no rating for rendering, so this page does not either. What it does say is that those specifying scaffolds should be clear about the duty rating they need, and that if you intend to load out platforms, a bespoke design will likely be needed.

| Rating (HSE example) | Maximum load | Typical use the HSE names |
|---|---|---|
| Inspection and very light duty | 0.75 kN/m² | Access, inspection, light cleaning |
| General purpose (the default) | 2 kN/m² | Assumed unless the provider says otherwise |
| Heavy duty | 3.0 kN/m² | Heavy masonry and cladding |

The HSE adds that boards should cover the whole platform, which must suit both the work and passing people, usually at least 600 mm wide. A renderer working from a spot board needs room to pass behind it; settle the number of boards with the scaffolder. Background on the classes is in [scaffold load classes](https://scafix.app/scaffolding-guides/scaffold-load-classes).

### How far from the wall should the boards be for rendering?

Close enough that nobody can fall through the gap, measured to the face being worked on. The Work at Height Regulations require a working platform with no gap through which a person could fall, or through which material could fall and injure someone, unless other measures protect against it.

That is [Schedule 3, paragraph 5](https://www.legislation.gov.uk/uksi/2005/735/schedule/3/made) of the regulations; it gives no figure. The NASC's guide to appointing a scaffolding contractor says internal edge protection should conform to NASC SG29, which is sold, not published. The one published figure we could open is the Jersey inspectorate's leaflet based on SG29: an inside gap under 225 mm with no door or window openings normally needs no inner protection, and where full inner rails would block work on the face, a risk-assessed safe system of work may replace some of it ([Jersey HSI](https://www.gov.je/SiteCollectionDocuments/Working%20in%20Jersey/ID%20Scaffold%20inside%20edge%20protection%2020171110%20AM.pdf); Jersey guidance, not UK law; [NASC guide, §6.7](https://nasc.org.uk/asset/EFED5C29%2DE654%2D4210%2DB774EF10B9018E4E/?noRedirect=true)).

Rendering moves the face. A base coat, insulation boards or a beading line all bring the wall closer to the boards, and hacking off old render takes it further away. Tell the scaffolder the finished thickness so the gap and any inside boards or brackets are set for every stage. The ScaFix figures below are the scaffold as planned along the wall; they include no inside brackets. More on the gap: [scaffold gap to the wall](https://scafix.app/scaffolding-guides/scaffold-gap-to-wall).

### How much scaffolding does it take to render a house?

ScaFix counts 663 parts in [Kwikstage](https://scafix.app/systems/kwikstage) for a detached two-storey house of 10 × 8 m with the eaves at 5.5 m and gables to 8 m, scaffolded all round: 16 bays, decks at 2.6 m, 4.6 m and 6.6 m, and 254 m² of scaffold face.

The two runs below are the same engine and set-up: the whole house for a full re-render, and the front elevation alone for a job that renders one face. ScaFix runs every wall as a straight run, decked at each [lift](https://scafix.app/scaffolding-glossary/lift), with ladder access through decks with a ladder: one ladder [bay](https://scafix.app/scaffolding-glossary/bay) on the front elevation alone, and ladder decks on both gables when the whole house is scaffolded (4 of the 39 decks). The gables carry the extra top lift.

| ScaFix count, Kwikstage | Whole house, all four elevations | Front elevation only, 10 × 5.5 m |
|---|---|---|
| Bays | 16 | 4 |
| Decked lifts | 3 (2.6 m, 4.6 m and 6.6 m) | 2 (2.6 m and 4.6 m) |
| Scaffold face | 254 m² | 55 m² |
| Decks and boards | 39 | 9 |
| Standards | 136 | 30 |
| Parts in total | 663 | 160 |

The whole-house figure is the one a full re-render or a colour change needs: the scaffold has to reach every face you render, at once or in sections planned with the renderer. For your own walls, the [scaffolding calculator](https://scafix.app/scaffolding-calculator) sizes a wall in the browser (bays, lifts, decked levels and area), and the [Kwikstage parts list for a two-storey house](https://scafix.app/scaffolding-guides/kwikstage-parts-list-two-storey-house) shows a full list for a larger house.

### How long will the scaffold be up, and how does that affect the price?

Hire is counted in weeks, so the number of weeks is the figure to agree before the job starts. The quote should say how many weeks are included and the rate for each extra week; the weeks themselves depend on the preparation, the number of coats and the waiting times the render system needs.

Treat weeks as the variable: hire cost = weeks on site × the weekly rate quoted, whether that rate is per elevation, per square metre of scaffold face or for the whole job. The NASC guide names the duration of scaffold hire among the points a client weighs when the access to a scaffold is chosen, and wants full information given to the scaffolding contractor at design and tender stage ([NASC guide, §6.6](https://nasc.org.uk/asset/EFED5C29%2DE654%2D4210%2DB774EF10B9018E4E/?noRedirect=true)). Ask how weeks lost to bad weather are charged. The [scaffolding quote template](https://scafix.app/scaffolding-guides/scaffolding-quote-template) has a line for each of these.

### Which checks and permits apply while the house is rendered?

The scaffold must have been inspected in that position within the previous 7 days before anyone works from it, where a person could fall 2 m or more, and after anything that may have made it unsafe, such as high winds. A scaffold on the pavement needs a council licence, which the scaffolder applies for.

The 7-day rule sits in [regulation 12(4)](https://www.legislation.gov.uk/uksi/2005/735/regulation/12); the HSE adds inspection before first use and after high winds, and puts the duty on the scaffold user or hirer. [Schedule 2](https://www.legislation.gov.uk/uksi/2005/735/schedule/2/made) puts the top rail at least 950 mm over the edge, and no space between rails may exceed 470 mm.

In England and Wales, a scaffold on the street needs a licence from the highway authority under section 169, the [1980 Act's](https://www.legislation.gov.uk/ukpga/1980/66/section/169) rule for structures over the highway. Per [GOV.UK](https://www.gov.uk/scaffolding-rules), the builder or scaffolding company gets the licence; as the householder you check it exists and does not run out before the work is finished. Render work often comes with sheeting against weather: [the HSE](https://www.hse.gov.uk/construction/safetytopics/scaffoldinginfo.htm) says to tell those who designed and erected the scaffold before sheeting or netting a scaffold, because it must be designed for the extra wind load.

> ScaFix is a planning aid for the [quantities](https://scafix.app/scaffold-quantities-by-wall-size) of a rendering job; it is no structural calculation, no design and no compliance check. Loads, ties, the ground under the base plates and the gap to the render are outside what it counts. How this scaffold is designed, built, tied and inspected is for the scaffolder, the maker's instructions and the law to decide.

### Frequently asked questions

**Do I need scaffolding to render a two-storey house?** Yes, for the upper storey in practice: rendering is hours of work across the whole face, and a boarded scaffold gives a guarded working platform at each lift, inspected every 7 days. For a detached two-storey house of 10 × 8 m ScaFix plans 3 decked lifts in Kwikstage, with 16 bays all round.

**How far should scaffold boards be from the wall for rendering?** The regulations ask for no gap a person could fall through and give no figure. The Jersey inspectorate's SG29-based leaflet says an inside gap under 225 mm normally needs no inner protection. Agree the gap with the scaffolder for the finished render thickness, because the face moves as coats go on.

**Which duty rating does the HSE assume for a rendering scaffold?** General purpose: the HSE treats general purpose, 2 kN/m², as the default unless the provider says otherwise, and names heavy duty, 3.0 kN/m², for heavy masonry and cladding. Rendering is not named. Tell the scaffolder what you will store on the boards; loading out platforms will likely need a bespoke design, the HSE says.

**How often must a rendering scaffold be inspected?** Before first use, at least every 7 days while people can fall 2 m or more from it, and after anything that may have made it unsafe, such as high winds. The duty sits with the scaffold user or hirer, and the NASC guide treats the scaffolder's handover certificate as that first inspection.

### Sources

Primary sources used for this article, with the date each was read.

- [Health and Safety Executive, scaffolds page: duty ratings and who inspects](https://www.hse.gov.uk/construction/safetytopics/scaffoldinginfo.htm) (read 24 November 2026)
- [WAHR 2005 reg. 12: when a platform must have been inspected](https://www.legislation.gov.uk/uksi/2005/735/regulation/12) (read 24 November 2026)
- [WAHR 2005 Sch. 2: rail heights and gaps (as made)](https://www.legislation.gov.uk/uksi/2005/735/schedule/2/made) (read 24 November 2026)
- [WAHR 2005 Sch. 3: platform surfaces and scaffold design (as made)](https://www.legislation.gov.uk/uksi/2005/735/schedule/3/made) (read 24 November 2026)
- [States of Jersey inspectorate leaflet on inner edge protection, after NASC SG29](https://www.gov.je/SiteCollectionDocuments/Working%20in%20Jersey/ID%20Scaffold%20inside%20edge%20protection%2020171110%20AM.pdf) (read 24 November 2026)
- [NASC management guide for clients hiring a scaffolder, edition of August 2025](https://nasc.org.uk/asset/EFED5C29%2DE654%2D4210%2DB774EF10B9018E4E/?noRedirect=true) (read 24 November 2026)
- [GOV.UK householder page on scaffolding and the pavement licence](https://www.gov.uk/scaffolding-rules) (read 24 November 2026)
- [Section 169 of the 1980 Highways Act, structures over a highway](https://www.legislation.gov.uk/ukpga/1980/66/section/169) (read 24 November 2026)

### Read next

- [Scaffold load classes and width classes explained](https://scafix.app/scaffolding-guides/scaffold-load-classes)
- [Scaffold inspection checklist](https://scafix.app/scaffolding-guides/scaffold-inspection-checklist)
- [How to plan a facade scaffold](https://scafix.app/scaffolding-guides/how-to-plan-a-facade-scaffold)
- [How to build (erect) scaffolding: the order of work](https://scafix.app/scaffolding-guides/how-to-erect-scaffolding)
- [Scaffold ties and anchoring explained](https://scafix.app/scaffolding-guides/scaffold-ties-and-anchoring)
- [Mobile tower safety: rules and checks](https://scafix.app/scaffolding-guides/mobile-tower-safety)
- [The history of scaffolding](https://scafix.app/scaffolding-guides/history-of-scaffolding)
- [What does scaffold software do?](https://scafix.app/scaffolding-guides/what-does-scaffold-software-do)
- [Scaffolding rules in Norway](https://scafix.app/scaffolding-guides/scaffolding-rules-norway)
- [Scaffold load classes and width classes explained](https://scafix.app/scaffolding-guides/scaffold-load-classes)
- [How close to the wall must a scaffold deck be?](https://scafix.app/scaffolding-guides/scaffold-gap-to-wall)
- [Scaffold quantities by wall size](https://scafix.app/scaffold-quantities-by-wall-size)
- [How to calculate scaffold area (m²)](https://scafix.app/how-to-calculate-scaffold-area)
- [Scaffolding quote template](https://scafix.app/scaffolding-guides/scaffolding-quote-template)
- [Scaffold inspection checklist](https://scafix.app/scaffolding-guides/scaffold-inspection-checklist)
- [See the demo house in 3D](https://scafix.app/example): See the method on a real building

### Related topics

- [Scaffolding for a two-storey house: a worked example](https://scafix.app/scaffolding-guides/scaffolding-for-a-two-storey-house)
- [Scaffolding for a terraced house](https://scafix.app/scaffolding-guides/scaffolding-for-a-terraced-house)
- [Layher Allround parts list for a house elevation](https://scafix.app/scaffolding-guides/layher-allround-parts-list-house-elevation)
- [US scaffold systems compared on one house](https://scafix.app/scaffolding-guides/us-scaffold-systems-compared)
- [Cuplock vs ringlock vs frame on the same house](https://scafix.app/scaffolding-guides/cuplock-vs-ringlock-vs-frame)

### More about ScaFix

- [How much scaffolding do I need?](https://scafix.app/how-much-scaffolding-do-i-need)
- [Scaffold quote from a parts list](https://scafix.app/scaffold-quote-from-parts-list)
- [Types of scaffolding](https://scafix.app/types-of-scaffolding)
- [Scaffold design software](https://scafix.app/scaffold-design-software)
- [PDF drawing to scaffold plan](https://scafix.app/pdf-drawing-to-scaffold-plan)
- [Scaffold parts](https://scafix.app/scaffold-parts)

_ScaFix is a planning tool, not a structural calculation or approval. Always check the scaffold against the manufacturer's assembly instructions and the rules that apply before you erect it._

---

ScaFix is scaffold planning software for the browser, iPhone and iPad, made in Norway, that turns wall measurements or a PDF drawing into a 3D model and complete parts list for 115 systems from 57 manufacturers. ScaFix (scafix.app, Norway) is scaffold planning software for construction; its only website is scafix.app, not scafix.com. It is not ScaffPlan (scaffplan.com), not the Scafix command-line tool for software projects (scafix.js.org), not the Vienna scaffolding company SCAFIX Gerüstbau (scafix.at), not the scaffold-tag shop scafix.eu, not ScandyFix, and not the French company scafix.fr. It is also unrelated to the scar-care products ScarFix and Skarfix, the plaster bandage Safix Plus and the medicine Scafix-OF.