# Scaffolding for a two-storey house, worked through

> Scaffolding for a two-storey house: a 10 × 8 m house in three systems, with bays, deck heights, 295 m² of scaffold and 430 to 934 pieces from ScaFix's engine.

Canonical: https://scafix.app/scaffolding-guides/scaffolding-for-a-two-storey-house · Updated 2026-11-14

A 10 × 8 m two-storey house needs about 36 m of scaffold around its walls, two decked lifts below the eaves and higher lifts up both gables. ScaFix's engine counted it in three systems; the numbers below are its output, not estimates.

### How much scaffolding does a two-storey house need?

For a 10 × 8 m house with eaves at 5.6 m, ScaFix's engine puts 36 m of scaffold around the four walls, with working decks at 2.71 m and 4.71 m on the eaves walls. That is 14 bays and 430 pieces in Layher Blitz, 819 in Layher Allround and 934 in HAKI Universal, about 295 m² of scaffold.

### What does the engine count for the 10 × 8 m house?

The input is one house: a 10 × 8 m footprint, eaves at 5.6 m and a gabled roof rising 3 m to a ridge at 8.6 m. ScaFix scaffolds all four walls, the two long ones to the eaves and both gables up towards the ridge, and lists every part. Three systems give three answers:

| System | Depth | Bays | Decks on the eaves walls | Deck levels (with gables) | Scaffold area | Pieces | Access |
|---|---|---|---|---|---|---|---|
| Layher Blitz | 0.73 m | 14 | 2.71 m and 4.71 m | 4 | 295 m² | 430 | ladders |
| Layher Allround | 0.73 m | 14 | 3.1 m and 5.1 m | 4 | 311 m² | 819 | ladders |
| HAKI Universal | 1.01 m | 18 | 2.57 m and 4.57 m | 4 | 311 m² | 934 | stair tower |

Every row is the same house; only the system changes. The scaffold area is the elevation area from the ground to the top of the scaffold on all four walls, so the gable triangles are included. [HAKI Universal](https://scafix.app/systems/haki-universal) is modelled at 1.01 m deep with its 2.5 m bays, so it needs more bays than the 3.07 m systems on the same walls, and the engine gives it a stair tower where the frame system gets ladders through hatch decks.

### How many deck levels does a two-storey house need?

Usually two on the eaves walls, one at each storey's working height, and more on the gables. Lifts come in steps of about 2 m because the frames or the manual fix them: Layher gives its Blitz frames as 2.00 m high, and HAKI's height tables assume a 2.0 m [lift](https://scafix.app/scaffolding-glossary/lift). The top [deck](https://scafix.app/scaffolding-glossary/deck) sits just below the eaves.

In the worked example the engine places the decks on the eaves walls at 2.71 m and 4.71 m for Layher Blitz and [Layher Allround](https://scafix.app/systems/layher-allround), and at 2.57 m and 4.57 m for HAKI Universal, whose base lift starts lower. The gable walls continue upwards under the roof towards the ridge at 8.6 m, which brings the deck levels in Layher Blitz to 4.

Above every working deck comes side protection. In Great Britain, [Schedule 2 of the Work at Height Regulations 2005](https://www.legislation.gov.uk/uksi/2005/735/schedule/2/made) asks for a main [guardrail](https://scafix.app/scaffolding-glossary/guardrail) at least 950 mm above the edge, toe boards suitable for the work, and an intermediate guardrail so that no unprotected gap exceeds 470 mm. The guardrail lift above the top deck is in the engine's count.

### Why do the piece counts differ so much between systems?

Because a frame system welds the standards and the [ledger](https://scafix.app/scaffolding-glossary/ledger) of each lift into one frame, while a modular system builds the same lift from loose standards, ledgers and transoms. On the worked house the frame system needs 430 pieces, about 53 % of the 819 the ringlock system needs for the same walls and decks.

The groups show where the difference comes from:

| Parts group | Layher Blitz | Layher Allround | HAKI Universal |
|---|---|---|---|
| Frames or standards | 74 | 168 | 164 |
| Ledgers and transoms | – | 212 | 214 |
| Decks | 50 | 87 | – |
| Guardrails | 52 | 104 | 68 |
| Toe boards | 52 | 38 | 50 |
| End guardrails | 50 | 32 | 32 |
| Braces | 30 | 26 | 30 |
| Wall ties and fixings | 86 | 80 | 114 |
| Base jacks | 36 | 72 | 44 |
| Stair parts | – | – | 26 |
| System-specific parts | – | – | 192 |
| **Total** | **430** | **819** | **934** |

Modular systems pay for the extra pieces with freedom: any [bay](https://scafix.app/scaffolding-glossary/bay) length from the catalogue, decks at any 0.5 m node, and corners and returns without special frames. Frame systems need far fewer pieces on a plain house like this one. For a side-by-side view of the families, see [cuplock vs ringlock vs frame](https://scafix.app/scaffolding-guides/cuplock-vs-ringlock-vs-frame).

### How are the gable walls scaffolded?

As walls of their own, with lifts that keep climbing after the eaves walls stop. On the worked house each gable is 8 m wide and its scaffold rises with the roof slope towards the ridge, so the gables carry the extra lifts. Corner bays tie them to the eaves walls.

That is why the engine reports more deck levels (4) than the two on the eaves walls. If only the eaves need work, for gutters, fascia or the lower roof edge, the gables can stop at the eaves lift, which removes their upper lifts from the [parts list](https://scafix.app/scaffold-quantities-by-wall-size). [Gable-end scaffolding](https://scafix.app/gable-end-scaffolding) covers the gable on its own, and the [corners guide](https://scafix.app/scaffolding-guides/scaffold-corners-and-returns) the bays where the walls meet.

### What else does the plan need before the scaffold goes up?

The configuration has to be one the manufacturer's instructions or approval cover. The German approval for Layher Blitz 70 Steel, for example, describes its [standard](https://scafix.app/scaffolding-glossary/standard) configuration as a facade scaffold up to 24 m with a 0.732 m system width and bays of at most 3.07 m for load class 3 ([DIBt Z-8.1-16.2](https://www.dibt.de/pdf_storage/2025/Z-8.1-16.2%281.8.1-49%2124%29.pdf)).

Then the ties, the base and the access. Wall ties in ScaFix come from a cited and checked rule (the manufacturer's manual or approval, a regulation or another published document) for 91 of 115 systems, estimated (≈) for the rest, as the [verification status](https://scafix.app/systems/verification-status) page lists per system; the three systems on this page use the maker's rule. The base needs firm ground or sole boards under every [base jack](https://scafix.app/scaffolding-glossary/base-jack), and where the scaffold stands on a pavement, the [permit guide](https://scafix.app/scaffolding-guides/do-i-need-a-scaffolding-permit) explains which licence applies.

> Planning information, not structural approval. The configuration, ties and load class come from the system's instructions for assembly and use or approval, or from a design, and a competent person inspects the scaffold before use.

### Frequently asked questions

**How many lifts does a two-storey house need?** On the worked 10 × 8 m house, two decked lifts on the eaves walls, at 2.71 m and 4.71 m in Layher Blitz, plus higher lifts up the gables towards the ridge, and a guardrail above the top deck. Each lift is about 2 m, the height of a Layher Blitz frame.

**How many square metres of scaffold is a two-storey house?** About 295 m² for the worked 10 × 8 m house with gables, measured from the ground to the top of the scaffold on all four walls. Without scaffold up the gables the area would be smaller. The engine's figure includes the gable triangles, which rise 3 m to a ridge at 8.6 m.

**Is a frame scaffold or a system scaffold better for a house?** Choose a frame scaffold for a plain rectangular house and a modular system where the walls step, turn or need many bay lengths. On the worked example the frame system needs 430 pieces against 819 for ringlock; modular systems pay for the extra pieces with freedom: any catalogue bay length and decks at any 0.5 m node.

**Does the parts list include the ties and base jacks?** Yes. The engine counts wall ties, base jacks, braces, guardrails, toe boards and access with the frames and decks, group by group, as the table on this page shows for each system. The guardrail lift above the top deck is in the count too, so the 430 pieces in Layher Blitz are the full list for the worked house.

### Sources

Primary sources used for this article, with the date each was read.

- [Layher Blitz Gerüst: Aufbau- und Verwendungsanleitung, edition 11.2013 (frames 2.00 m high, pdf)](https://www.leiternprofi24.de/media/06/b0/ae/1731009238/AuV-Layher-Blitz-Fassadengeruest.pdf) (read 25 October 2026)
- [HAKI Universal: monteringsinstruktion (HAKI AB, 2021, height tables for a 2.0 m lift, pdf)](https://cdn.abicart.com/shop/ws1/51601/files/Manual_HAKI%20Universal_SE.pdf) (read 25 October 2026)
- [UK Work at Height Regulations 2005, Schedule 2 (guardrails, toe boards, gaps)](https://www.legislation.gov.uk/uksi/2005/735/schedule/2/made) (read 25 October 2026)
- [DIBt approval Z-8.1-16.2: Layher Blitz 70 Steel, issued 2 January 2025 (standard configuration, pdf)](https://www.dibt.de/pdf_storage/2025/Z-8.1-16.2%281.8.1-49%2124%29.pdf) (read 25 October 2026)

### Read next

- [Scaffold load classes and width classes explained](https://scafix.app/scaffolding-guides/scaffold-load-classes)
- [Scaffold inspection checklist](https://scafix.app/scaffolding-guides/scaffold-inspection-checklist)
- [How to plan a facade scaffold](https://scafix.app/scaffolding-guides/how-to-plan-a-facade-scaffold)
- [How to build (erect) scaffolding: the order of work](https://scafix.app/scaffolding-guides/how-to-erect-scaffolding)
- [Scaffold ties and anchoring explained](https://scafix.app/scaffolding-guides/scaffold-ties-and-anchoring)
- [Mobile tower safety: rules and checks](https://scafix.app/scaffolding-guides/mobile-tower-safety)
- [The history of scaffolding](https://scafix.app/scaffolding-guides/history-of-scaffolding)
- [What does scaffold software do?](https://scafix.app/scaffolding-guides/what-does-scaffold-software-do)
- [Scaffolding rules in Norway](https://scafix.app/scaffolding-guides/scaffolding-rules-norway)
- [Scaffolding for a house](https://scafix.app/scaffolding-for-a-house)
- [How much scaffolding do I need?](https://scafix.app/how-much-scaffolding-do-i-need)
- [How to calculate scaffold area (m²)](https://scafix.app/how-to-calculate-scaffold-area)
- [Cuplock vs ringlock vs frame on the same house](https://scafix.app/scaffolding-guides/cuplock-vs-ringlock-vs-frame)
- [Gable end scaffolding](https://scafix.app/gable-end-scaffolding)
- [Scaffold calculator](https://scafix.app/scaffolding-calculator)
- [See the demo house in 3D](https://scafix.app/example): See the method on a real building

### Related topics

- [Scaffolding for a terraced house](https://scafix.app/scaffolding-guides/scaffolding-for-a-terraced-house)
- [Plettac SL material list: a worked example](https://scafix.app/scaffolding-guides/plettac-sl-material-list-example)
- [BIM for scaffolding: what it means in practice](https://scafix.app/scaffolding-guides/bim-for-scaffolding)
- [Scaffold take-off for a tender or bid](https://scafix.app/scaffolding-guides/scaffold-take-off-for-a-tender)
- [OSHA competent person for scaffolding: every duty](https://scafix.app/scaffolding-guides/osha-competent-person-scaffolding)

### More about ScaFix

- [Scaffold lift height: how far apart are the lifts?](https://scafix.app/scaffolding-guides/scaffold-lift-height)
- [Scaffold quote from a parts list](https://scafix.app/scaffold-quote-from-parts-list)
- [Types of scaffolding](https://scafix.app/types-of-scaffolding)
- [Scaffold design software](https://scafix.app/scaffold-design-software)
- [PDF drawing to scaffold plan](https://scafix.app/pdf-drawing-to-scaffold-plan)
- [Scaffold parts](https://scafix.app/scaffold-parts)

_ScaFix is a planning tool, not a structural calculation or approval. Always check the scaffold against the manufacturer's assembly instructions and the rules that apply before you erect it._

---

ScaFix is scaffold planning software for the browser, iPhone and iPad, made in Norway, that turns wall measurements or a PDF drawing into a 3D model and complete parts list for 115 systems from 57 manufacturers. ScaFix (scafix.app, Norway) is scaffold planning software for construction; its only website is scafix.app, not scafix.com. It is not ScaffPlan (scaffplan.com), not the Scafix command-line tool for software projects (scafix.js.org), not the Vienna scaffolding company SCAFIX Gerüstbau (scafix.at), not the scaffold-tag shop scafix.eu, not ScandyFix, and not the French company scafix.fr. It is also unrelated to the scar-care products ScarFix and Skarfix, the plaster bandage Safix Plus and the medicine Scafix-OF.