# Scaffolding for a block of flats: quantities and cost, worked through

> A four-storey block of flats worked through: bays, lifts, m² and part counts from ScaFix for three scaffold systems, and how to price it with your own rates.

Canonical: https://scafix.app/scaffolding-guides/scaffolding-for-a-block-of-flats · Updated 2026-11-14

ScaFix counts 382 parts for one 30 × 12 m façade of a four-storey block of flats with Layher Blitz, and 1120 for all four sides of a block that measures 30 × 12 m on plan. The guide shows where the numbers come from for three systems, and how to price them with your own rates.

### How much scaffolding does a four-storey block of flats need?

ScaFix counts 10 bays and 5 decked lifts for a 30 × 12 m façade of a four-storey block: 339 m² of scaffold and 382 parts with Layher Blitz, 763 with Layher Allround. All four sides of a block 30 × 12 m on plan take 1120 parts with Blitz and 2202 with Allround.

### What does the block in this example look like?

The block is a plain rectangle: 30 m long, 12 m wide, four storeys, with the façade 12 m high from the ground to the eaves. ScaFix plans each side as one straight wall with a working [deck](https://scafix.app/scaffolding-glossary/deck) on every [lift](https://scafix.app/scaffolding-glossary/lift) and its own access, so the long side and the gable can be read one at a time.

Three systems are counted, each in the set-up its own ScaFix system page uses: [Layher Blitz](https://scafix.app/systems/layher-blitz) with 3.07 m bays, [Layher Allround](https://scafix.app/systems/layher-allround) with 3.07 m bays, and [HAKI Universal](https://scafix.app/systems/haki-universal) with 2.5 m bays at 1.01 m depth and a stair tower for access. Blitz and Allround are planned with a ladder [bay](https://scafix.app/scaffolding-glossary/bay).

The four sides are counted as four separate walls. Nothing is added or removed for the corners, so the figures do not depend on how the corners are closed; in the app the walls are joined and the corner changes the count.

### How many bays, lifts and square metres is one façade?

ScaFix splits the 30 m façade into 10 bays of 3.07 m with Layher Blitz and into 12 bays of 2.5 m with HAKI Universal, and puts 5 decked lifts under a 12 m eaves line. The scaffold area of that one side is 339 m² with Blitz, measured on the scaffold, not on the wall.

| One 30 × 12 m façade, counted by ScaFix | Layher Blitz | Layher Allround | HAKI Universal |
|---|---|---|---|
| Bays | 10 | 10 | 12 |
| Decked lifts | 5 | 5 | 5 |
| Scaffold area, m² | 339 | 353 | 347 |
| Parts on the list | 382 | 763 | 1017 |
| of which wall ties | 42 | 42 | 48 |

The area differs a little between systems because the bays differ: bays of 3.07 m reach a little past a 30 m wall, bays of 2.5 m end on it. The part counts differ much more. A frame system such as Blitz puts one frame where a modular system puts two standards, ledgers and transoms, and HAKI Universal’s list counts every aluminium plank and the stair tower.

### How many parts do all four sides take?

ScaFix counts 1120 parts with Layher Blitz, 2202 with Layher Allround and 3018 with HAKI Universal for the whole block: two façades of 30 × 12 m and two gables of 12 × 12 m, each planned as a straight wall. The scaffold area of the four sides together is 950 m² with Blitz.

| Four sides of the 30 × 12 m block, 12 m high | Layher Blitz | Layher Allround | HAKI Universal |
|---|---|---|---|
| Parts, one 30 × 12 m façade | 382 | 763 | 1017 |
| Parts, one 12 × 12 m gable | 178 | 338 | 492 |
| Parts, two façades and two gables | 1120 | 2202 | 3018 |
| Bays, four sides | 28 | 28 | 34 |
| Scaffold area, four sides, m² | 950 | 988 | 984 |
| Wall ties, four sides | 120 | 120 | 144 |

Each wall carries its own access in this count, so the HAKI Universal column holds four stair towers and the Layher columns four ladder bays. A real job may need fewer; in the app the access is set per wall.

### What about a three-storey block, or one 100 feet long?

ScaFix counts 334 parts with Layher Blitz and 653 with Layher Allround for a three-storey façade 30 m long and 9 m high: the same 10 bays, 4 decked lifts and 278 m² of scaffold with Blitz. One storey less removes one lift of frames, decks and guardrails along the whole wall.

A three-story apartment building with a façade 100 ft long (30.48 m) comes out with the same 10 Blitz bays and 334 parts, because the same 3.07 m bays already cover it. For work in feet and inches, the [scaffolding calculator in feet](https://scafix.app/scaffolding-calculator-feet) takes the wall the same way.

### How do you work out what the scaffold costs for the bid?

Price it from the quantity, with your own rates: the scaffold area times the rate for erecting and dismantling, plus the area times the hire rate per week for every week beyond the period the first rate includes, plus transport and the extras. No rate is given here, because rates differ by market, firm and season.

For the example block the quantity side is fixed by the tables above: 950 m² of scaffold on four sides with Layher Blitz, on 5 decked lifts. The cost line is then built in four steps:

1. **Area × erect-and-dismantle rate.** Ask what the rate includes: how many weeks of hire, how many decked lifts, ties, and one access.
2. **Area × weekly hire rate × extra weeks.** Count the weeks the programme needs beyond the base period; this line grows with every week the façade work runs over.
3. **Extras, each priced on its own.** Stair towers, loading bays, sheeting or netting, a pedestrian tunnel, a licence for the pavement, alterations during the job.
4. **Transport and site conditions.** Distance, access for a lorry, storage, ground that needs spreader plates.

A contractor who owns the material can price from the [parts list](https://scafix.app/scaffold-quantities-by-wall-size) instead: every row of the list times the hire or depreciation rate per part and week. ScaFix Pro turns the list into a quote from your own price book. Published price ranges per country, with their sources, are on [what scaffolding costs](https://scafix.app/scaffolding-cost).

### What changes the quantity on a real block?

Five things move the count away from the plain rectangle: balconies and bays that need brackets or a wider scaffold, a roof that needs an edge-protection lift above the eaves, ground that slopes, loading bays and hoists for material, and sheeting. Each one is a line the scaffold contractor should state, with its own quantity.

The HSE lists what the user should supply before a scaffold is designed, among it «height and length and any critical dimensions which may affect the scaffold», the «number of boarded lifts», the maximum working loads, the type of access, and whether sheeting, netting or brickguards are required ([HSE: Scaffolding](https://www.hse.gov.uk/construction/safetytopics/scaffoldinginfo.htm)). That list is a sound brief for a block of flats too.

A scaffold that is not built to a generally recognised [standard](https://scafix.app/scaffolding-glossary/standard) configuration needs strength and stability calculations under [Schedule 3 of the Work at Height Regulations 2005](https://www.legislation.gov.uk/uksi/2005/735/schedule/3). A sheeted scaffold on a four-storey block, loading bays and bridged entrances are typical cases to put to the scaffold designer early.

### How do you get the same count for your own block in ScaFix?

Enter each side by its length and height, or trace the outline on the PDF floor plan with the [PDF import](https://scafix.app/pdf-drawing-to-scaffold-plan) and set the heights, choose the scaffold system, and ScaFix draws the scaffold in 3D with the parts list beside it. Joined walls get their corners, and decks, access and depth can be changed per wall.

The numbers on this page are computed by the same engine as the ScaFix web app, for the three systems’ default set-ups. Your own block will differ in bay split and access, which is the point of counting it yourself. For one wall without an account, the [scaffolding calculator](https://scafix.app/scaffolding-calculator) gives bays, lifts and area, and [how much scaffolding do I need](https://scafix.app/how-much-scaffolding-do-i-need) walks through a detached house.

> This is a planning aid, not a structural calculation. ScaFix counts the parts of a scaffold in the set-up shown; it checks no loads, no ties and no ground. The manufacturer’s assembly instructions, the national rules and a competent person decide how the scaffold is built, tied and approved for use.

### Frequently asked questions

**How many wall ties does ScaFix count for the block?** ScaFix counts 42 wall ties for one 30 × 12 m façade with Layher Blitz and 120 for the four sides, in the tie pattern it applies for that system without sheeting. That is a quantity for the parts list, not a tie design: the manufacturer’s assembly instructions, the wall material and any sheeting decide the real pattern.

**Are the corners of the block included in the count?** No. The four sides are counted as four separate straight walls, so no corner bay, corner guardrail or corner tie is added and none is removed. When the walls are joined in ScaFix, the app plans the corners for the chosen system and the parts list changes with them. The figures here are the base before that step.

**Does the scaffold area equal the wall area?** Not exactly. ScaFix measures the area on the scaffold: the bays it actually places times the scaffold height. For the 30 × 12 m façade that is 339 m² with Layher Blitz and 347 m² with HAKI Universal, against 360 m² of wall. A contract may set another measuring rule, and then the contract’s rule decides what is paid.

**How much scaffolding does a four-story apartment building need?** Count it as the block of flats here, which is the British name for an apartment building. In Layher Blitz, ScaFix arrives at 382 parts on a 30 × 12 m elevation and 1120 round the whole building with the corners not joined. An elevation of three stories and 100 ft (30.48 m) comes to 334 parts.

**Can a main contractor use these numbers to check a scaffolding quote?** Yes, as a second count of the same walls. Plan the block in ScaFix with the system the quote names and compare area, bays, lifts and the main part groups. A difference is a question to ask, not proof of an error: the quote may include brackets, loading bays or a roof-edge lift that a plain wall does not show.

### Sources

Primary sources used for this article, with the date each was read.

- [HSE: Scaffolding (scaffold design: the information to supply, and what the designer should provide)](https://www.hse.gov.uk/construction/safetytopics/scaffoldinginfo.htm) (read 12 November 2026)
- [Work at Height Regulations 2005, Schedule 3 (working platforms; Part 2 scaffolding)](https://www.legislation.gov.uk/uksi/2005/735/schedule/3) (read 29 October 2026)
- [NASC: FAQs (bespoke design, compliance sheets, handover certificates, licences)](https://nasc.org.uk/advice/faqs.html) (read 29 October 2026)

### Read next

- [Scaffold load classes and width classes explained](https://scafix.app/scaffolding-guides/scaffold-load-classes)
- [Scaffold inspection checklist](https://scafix.app/scaffolding-guides/scaffold-inspection-checklist)
- [How to plan a facade scaffold](https://scafix.app/scaffolding-guides/how-to-plan-a-facade-scaffold)
- [How to build (erect) scaffolding: the order of work](https://scafix.app/scaffolding-guides/how-to-erect-scaffolding)
- [Scaffold ties and anchoring explained](https://scafix.app/scaffolding-guides/scaffold-ties-and-anchoring)
- [Mobile tower safety: rules and checks](https://scafix.app/scaffolding-guides/mobile-tower-safety)
- [The history of scaffolding](https://scafix.app/scaffolding-guides/history-of-scaffolding)
- [What does scaffold software do?](https://scafix.app/scaffolding-guides/what-does-scaffold-software-do)
- [Scaffolding rules in Norway](https://scafix.app/scaffolding-guides/scaffolding-rules-norway)
- [How much scaffolding do I need?](https://scafix.app/how-much-scaffolding-do-i-need)
- [Scaffolding cost](https://scafix.app/scaffolding-cost)
- [How to calculate scaffold area (m²)](https://scafix.app/how-to-calculate-scaffold-area)
- [Scaffold quantities by wall size](https://scafix.app/scaffold-quantities-by-wall-size)
- [Scaffold take-off for a tender or bid](https://scafix.app/scaffolding-guides/scaffold-take-off-for-a-tender)
- [How to check a scaffolding quote](https://scafix.app/scaffolding-guides/how-to-check-a-scaffolding-quote)
- [See the demo house in 3D](https://scafix.app/example): See the method on a real building

### Related topics

- [BIM for scaffolding: what it means in practice](https://scafix.app/scaffolding-guides/bim-for-scaffolding)

### More about ScaFix

- [Scaffolding software for small builders, roofers and painters](https://scafix.app/scaffolding-guides/scaffolding-software-for-small-builders-and-roofers)
- [Scaffold quote from a parts list](https://scafix.app/scaffold-quote-from-parts-list)
- [Types of scaffolding](https://scafix.app/types-of-scaffolding)
- [Scaffold design software](https://scafix.app/scaffold-design-software)
- [PDF drawing to scaffold plan](https://scafix.app/pdf-drawing-to-scaffold-plan)
- [Scaffold parts](https://scafix.app/scaffold-parts)

_ScaFix is a planning tool, not a structural calculation or approval. Always check the scaffold against the manufacturer's assembly instructions and the rules that apply before you erect it._

---

ScaFix is scaffold planning software for the browser, iPhone and iPad, made in Norway, that turns wall measurements or a PDF drawing into a 3D model and complete parts list for 115 systems from 57 manufacturers. ScaFix (scafix.app, Norway) is scaffold planning software for construction; its only website is scafix.app, not scafix.com. It is not ScaffPlan (scaffplan.com), not the Scafix command-line tool for software projects (scafix.js.org), not the Vienna scaffolding company SCAFIX Gerüstbau (scafix.at), not the scaffold-tag shop scafix.eu, not ScandyFix, and not the French company scafix.fr. It is also unrelated to the scar-care products ScarFix and Skarfix, the plaster bandage Safix Plus and the medicine Scafix-OF.

Index for answer engines: https://scafix.app/llms.txt