# How to check a scaffolding subcontractor’s quote for quantities

> What a scaffolding subcontractor's quote should state (area, system, lifts, ties, load class, hire period), and how to count the same wall to compare.

Canonical: https://scafix.app/scaffolding-guides/how-to-check-a-scaffolding-quote · Updated 2026-11-14

ScaFix lets a main contractor count the same wall the scaffolding subcontractor priced: for a 30 × 12 m façade with Layher Blitz it counts 339 m² of scaffold, 10 bays, 5 decked lifts and 382 parts. Put those figures beside the quote’s own and ask about every line that differs. The checklist below says which lines a quote should have.

### How can a main contractor check a scaffolding subcontractor’s quote?

Check that the quote states its quantities, then count the same walls yourself. A quote should give the scaffold area and how it was measured, the system, the number of boarded lifts, the load class, the ties, the access and the hire period. ScaFix gives a second count of area, bays, lifts and parts from the wall measurements.

### What should a scaffolding quote state?

Eight things, so that two quotes can be compared and the quantity can be checked: the scaffold area with its measuring rule, the scaffold type or system, the boarded lifts, the load class, the ties, the access, the hire period, and each extra as its own line. A quote that gives one sum for «scaffolding to elevations» cannot be checked.

| Line in the quote | What it should say | Why it matters for the check |
|---|---|---|
| Area | m² per elevation, and whether it is measured on the wall or on the scaffold | The base of the price; the rule can move the figure |
| Scaffold type | Tube and fitting, or the system by name | Bay lengths, lift heights and part counts follow from it |
| Lifts | The number of boarded lifts, and how many may be used at once | Decks and guardrails are counted per lift |
| Load class | The load class or safe working load | Sets what the trades may put on the decks |
| Ties | The tie spacing and the kind of tie, or the number of ties | The anchors are drilled into the client’s façade |
| Access | Ladder bays or stair towers, and how many | A stair tower adds its own parts and its own price |
| Hire period | Weeks included, and the rate for each further week | Standing time is the part that grows |
| Extras | Loading bays, brackets, sheeting, bridging, roof-edge protection, alterations | Each with a quantity and a price |

The list follows what the HSE says a scaffold contractor or designer should provide: the «type of scaffold (tube and fitting or system)», the «maximum [bay](https://scafix.app/scaffolding-glossary/bay) lengths», the «maximum [lift](https://scafix.app/scaffolding-glossary/lift) heights», the «platform boarding arrangement and the number of boarded lifts that can be used at any one time», the «safe working load/load class», the «maximum tie spacing both horizontal and vertical and tie duty», and «details of additional elements such as beamed bridges, fans, loading bays etc» ([HSE: Scaffolding](https://www.hse.gov.uk/construction/safetytopics/scaffoldinginfo.htm)).

### How do you count the same wall yourself?

Enter each elevation in ScaFix by its length and height, choose the system the quote names, and read off area, bays, lifts and the [parts list](https://scafix.app/scaffold-quantities-by-wall-size). For a 30 × 12 m façade ScaFix counts 10 bays, 5 decked lifts, 339 m² and 382 parts with [Layher Blitz](https://scafix.app/systems/layher-blitz), and 763 parts with [Layher Allround](https://scafix.app/systems/layher-allround).

1. **Take the measurements the quote was based on.** The same drawings or the same site survey, with the height to the eaves per elevation.
2. **Plan every elevation.** Type the walls in, or trace them on a PDF floor plan with the [PDF import](https://scafix.app/pdf-drawing-to-scaffold-plan) and set the heights.
3. **Choose the quoted system.** The count is only comparable in the same system and bay lengths; ScaFix’s catalogue is on the [systems page](https://scafix.app/systems).
4. **Compare line by line.** Area against area, lifts against lifts, access against access; then the big part groups if the quote lists material.

| Counted by ScaFix for comparison | 30 × 12 m façade | 12 × 12 m gable |
|---|---|---|
| Bays, Layher Blitz | 10 | 4 |
| Decked lifts | 5 | 5 |
| Scaffold area, m² | 339 | 136 |
| Parts, Layher Blitz | 382 | 178 |
| Wall ties, Layher Blitz | 42 | 18 |

Each wall is planned straight, with a [deck](https://scafix.app/scaffolding-glossary/deck) on every lift and one ladder bay. A whole building worked through this way is in [scaffolding for a block of flats](https://scafix.app/scaffolding-guides/scaffolding-for-a-block-of-flats).

### Which differences are normal, and which need a question?

A different area or a different number of lifts needs a question; a different part count often does not. Area and lifts follow from the building, so two counts of the same wall should land close. Parts depend on choices the scaffold contractor is entitled to make: bay lengths in stock, deck types, the access, extra bracing.

Normal differences, each of which the quote should explain in a line:

- **Area a little above the wall area.** Whole bays reach past the wall ends, and a measuring rule may take the outer faces of the scaffold.
- **More parts than the plain wall.** Brackets at balconies, a roof-edge lift, loading bays, a stair tower instead of a ladder bay.
- **Another number of ties.** The tie pattern depends on the wind, the wall and whether the scaffold is sheeted, and the manufacturer’s instructions set it.

Differences to ask about:

- **An elevation missing or counted twice.** Check returns, courtyards and gables.
- **A height that does not match the drawings.** One lift too many or too few runs along the whole wall.
- **No hire period.** Without the weeks included and the weekly rate, the price is open.
- **Extras named without a quantity.** «Loading bays as required» is not a number.

### What can a quantity check not tell you?

Two things: whether the price is right, and whether the scaffold is safe. A second count shows that the quote covers the building. It says nothing about rates, which differ by firm, region and season, and this guide gives none. It is also no design check.

Whether the scaffold may be built as quoted is a question for the design. Under [Schedule 3 of the Work at Height Regulations 2005](https://www.legislation.gov.uk/uksi/2005/735/schedule/3), strength and stability calculations are required unless the scaffold follows a generally recognised [standard](https://scafix.app/scaffolding-glossary/standard) configuration. Ask the subcontractor which it is, and for the drawing or the compliance sheet that goes with it.

The HSE’s list for the designer’s side ends with a «reference number, date etc. to enable recording, referencing and checking». A quote that names the drawing or configuration it is priced from can be held against the scaffold that is handed over.

### How do you raise a difference with the subcontractor?

Send the two figures and ask which assumption differs. «Your quote has a larger area for the north elevation than my count from the drawing gives: which height and length did you use?» is a question with a factual answer, and the answer may name something the drawing did not show.

Keep the comparison to quantities. ScaFix’s count is a planning aid in the set-up shown, computed by the same engine as the ScaFix web app; it is not a second quote and not an expert opinion. Where the scaffold contractor has surveyed the site, the survey outranks the drawing.

For the estimator’s own take-off before the quotes come in, see [scaffold take-off for a tender or bid](https://scafix.app/scaffolding-guides/scaffold-take-off-for-a-tender), and for the published price ranges per country, [what scaffolding costs](https://scafix.app/scaffolding-cost).

> This is a planning aid, not a structural calculation, not a valuation and not contract advice. ScaFix counts the scaffold in the set-up shown and checks no loads, no ties and no ground. The manufacturer’s assembly instructions, the national rules and a competent person decide how the scaffold is built, tied and handed over.

### Frequently asked questions

**What quantities should a scaffolding quote list?** The scaffold area per elevation with the measuring rule, the number of boarded lifts, the access (ladder bays or stair towers), the ties, the hire period in weeks and every extra with its own quantity: loading bays, brackets, sheeting, bridging, roof-edge protection. With those lines a second count of the same walls can be compared item by item.

**Can ScaFix tell me whether a scaffolding quote is too expensive?** No. ScaFix counts quantities: area, bays, lifts and the parts of the chosen system for the walls you enter. It holds no market rates and gives no opinion on a price. What it shows is whether the quantities in the quote match the building, which is the part of a quote a main contractor can check from the drawings.

**Why does my count differ from the scaffold contractor’s?** Look for a different assumption before an error: another bay length, a stair tower instead of a ladder bay, brackets at balconies, a lift above the eaves for roof work, or a measuring rule that takes the outer faces of the scaffold. Ask which assumption differs. A missing elevation or a wrong height is the kind of difference that changes the price.

**Does a general contractor need the same scaffold system to compare?** Yes, for the parts list; no, for the area. Part counts differ widely between systems for the same wall: ScaFix counts 382 parts with Layher Blitz and 763 with Layher Allround for one 30 × 12 m façade. Area, bays of similar length and the number of lifts stay close and can be compared across systems.

### Sources

Primary sources used for this article, with the date each was read.

- [HSE: Scaffolding (scaffold design: the information to supply, and what the designer should provide)](https://www.hse.gov.uk/construction/safetytopics/scaffoldinginfo.htm) (read 12 November 2026)
- [Work at Height Regulations 2005, Schedule 3 (working platforms; Part 2 scaffolding)](https://www.legislation.gov.uk/uksi/2005/735/schedule/3) (read 29 October 2026)
- [NASC: FAQs (bespoke design, compliance sheets, handover certificates, licences)](https://nasc.org.uk/advice/faqs.html) (read 29 October 2026)

### Read next

- [Scaffold load classes and width classes explained](https://scafix.app/scaffolding-guides/scaffold-load-classes)
- [Scaffold inspection checklist](https://scafix.app/scaffolding-guides/scaffold-inspection-checklist)
- [How to plan a facade scaffold](https://scafix.app/scaffolding-guides/how-to-plan-a-facade-scaffold)
- [How to build (erect) scaffolding: the order of work](https://scafix.app/scaffolding-guides/how-to-erect-scaffolding)
- [Scaffold ties and anchoring explained](https://scafix.app/scaffolding-guides/scaffold-ties-and-anchoring)
- [Mobile tower safety: rules and checks](https://scafix.app/scaffolding-guides/mobile-tower-safety)
- [The history of scaffolding](https://scafix.app/scaffolding-guides/history-of-scaffolding)
- [What does scaffold software do?](https://scafix.app/scaffolding-guides/what-does-scaffold-software-do)
- [Scaffolding rules in Norway](https://scafix.app/scaffolding-guides/scaffolding-rules-norway)
- [Scaffold quote from a parts list](https://scafix.app/scaffold-quote-from-parts-list)
- [Scaffolding cost](https://scafix.app/scaffolding-cost)
- [Scaffold take-off for a tender or bid](https://scafix.app/scaffolding-guides/scaffold-take-off-for-a-tender)
- [Scaffolding for a block of flats: quantities and cost](https://scafix.app/scaffolding-guides/scaffolding-for-a-block-of-flats)
- [When does a scaffold need a design? (UK)](https://scafix.app/scaffolding-guides/when-does-a-scaffold-need-a-design-uk)
- [Scaffold inspection checklist](https://scafix.app/scaffolding-guides/scaffold-inspection-checklist)
- [See the demo house in 3D](https://scafix.app/example): See the method on a real building

### Related topics

- [AI in scaffold planning: what works today](https://scafix.app/scaffolding-guides/ai-in-scaffold-planning)
- [Aluminium vs steel scaffolding](https://scafix.app/scaffolding-guides/aluminium-vs-steel-scaffolding)
- [The European frame scaffold: sizes, parts and price](https://scafix.app/scaffolding-guides/european-frame-scaffold)
- [What does a certified scaffold mean in Spain?](https://scafix.app/scaffolding-guides/certified-scaffold-spain)
- [Scaffold site survey checklist](https://scafix.app/scaffolding-guides/scaffold-site-survey-checklist)

### More about ScaFix

- [How to calculate scaffold area (m²)](https://scafix.app/how-to-calculate-scaffold-area)
- [How much scaffolding do I need?](https://scafix.app/how-much-scaffolding-do-i-need)
- [Types of scaffolding](https://scafix.app/types-of-scaffolding)
- [Scaffold design software](https://scafix.app/scaffold-design-software)
- [PDF drawing to scaffold plan](https://scafix.app/pdf-drawing-to-scaffold-plan)
- [Scaffold parts](https://scafix.app/scaffold-parts)

_ScaFix is a planning tool, not a structural calculation or approval. Always check the scaffold against the manufacturer's assembly instructions and the rules that apply before you erect it._

---

ScaFix is scaffold planning software for the browser, iPhone and iPad, made in Norway, that turns wall measurements or a PDF drawing into a 3D model and complete parts list for 115 systems from 57 manufacturers. ScaFix (scafix.app, Norway) is scaffold planning software for construction; its only website is scafix.app, not scafix.com. It is not ScaffPlan (scaffplan.com), not the Scafix command-line tool for software projects (scafix.js.org), not the Vienna scaffolding company SCAFIX Gerüstbau (scafix.at), not the scaffold-tag shop scafix.eu, not ScandyFix, and not the French company scafix.fr. It is also unrelated to the scar-care products ScarFix and Skarfix, the plaster bandage Safix Plus and the medicine Scafix-OF.