# Scaffold tubes and poles: sizes, weights and lengths

> Scaffold tube sizes: 48.3 mm outside diameter with a 3.2 or 4.0 mm wall to EN 39, the US 1.90 in tube, weight per metre and pole lengths.

Canonical: https://scafix.app/scaffold-parts/scaffold-tubes-and-poles · Updated 2026-11-16

Scaffold tube, scaffold pole and standard often mean the same thing: the 48.3 mm steel tube that carries the scaffold. EN 39 sets 48.3 mm outside diameter with a 3.2 or 4.0 mm wall, about 4.37 kg per metre for the thicker one; the US nominal 2 in tube is also 1.90 in. This page gives the size the European standard fixes and its US equivalent, what a metre of tube weighs, how long poles and system standards come, and how many standards, ledgers and transoms ScaFix counts for one wall 10 m long and 6 m high.

### What size is scaffold tube?

Scaffold tube is 48.3 mm in outside diameter. EN 39 specifies loose steel tube for [tube and coupler scaffolding](https://scafix.app/types-of-scaffolding/tube-and-coupler) at 48.3 mm with a 3.2 mm or 4.0 mm wall, which weighs about 3.56 kg or 4.37 kg per metre. The US 'nominal 2-inch' tube has the same 1.90-inch outside diameter; a common long pole is 21 ft (6.4 m).

### Tube sizes in Europe, the UK and the US

| Tube | Outside diameter | Wall | Weight per metre (calculated) | Where the size comes from |
|---|---|---|---|---|
| Steel tube to EN 39 | 48.3 mm | 3.2 mm | 3.56 kg | EN 39:2001 scope |
| Steel tube to EN 39 | 48.3 mm | 4.0 mm | 4.37 kg | EN 39:2001 scope |
| Aluminium tube | 48.3 mm | 4.0 mm | 1.50 kg | BG BAU Baustein B 117 (as guardrail tube) |
| US steel tube or pipe, «nominal 2 in.» | 1.90 in (48.3 mm) | not given | – | OSHA Subpart L, Appendix A |
| US heavy-duty bearer, «nominal 2½ in.» | 2.375 in (60.3 mm) | not given | – | OSHA Subpart L, Appendix A |

The weights are calculated from the cross-section with steel at 7,850 kg/m³ and aluminium at 2,700 kg/m³, so treat them as close estimates; a supplier's figure for its own tube wins. A 3.2 mm and a 4.0 mm tube look alike on site, but the thinner one has about 19 % less steel in it, which is why a design such as a TG20:21 compliance sheet names the tube it assumes. Ask your supplier which edition of EN 39 its tube is certified to; listings differ between countries.

System parts are a different matter. Their tubes keep the 48.3 mm outside diameter so couplers still fit, but not always the wall: the German approval of the Layher Blitz Gerüst 70 Stahl (DIBt Z-8.1-16.2, 2 January 2025) names scaffold tubes of 48.3 × 2.9 mm and 48.3 × 2.7 mm in the high-strength steel S460MH, checked against raised requirements beyond EN 10219-1. A thin-walled system tube is therefore no substitute for loose EN 39 tube in a tube-and-fitting design.

Loose tube is sold in lengths up to 21 ft, about 6.4 m ([a 21 ft scaffold tube listing](https://firstfence.co.uk/scaffolding-tube-21ft)), and cut down to shorter pieces for transoms, end rails and braces.

### Poles, standards, ledgers and transoms: one tube, five jobs

- Standard (pole, upright; «post» in US rules): the vertical tube that carries the load down to the base plate.
- Ledger (runner): the horizontal tube along the scaffold. OSHA 1926.452(b)(8) asks for runners interlocked into continuous lengths on straight runs and coupled to each post, and Appendix A keeps them at most 6 ft 6 in apart vertically.
- Transom (bearer): the short tube across the scaffold that carries the boards. Under 1926.452(b)(5) a bearer coupled to the posts has its inboard coupler bearing directly on the runner coupler, and (b)(6) wants it to reach past the posts and runners.
- Putlog: a transom with one end resting in the wall's brickwork, on a putlog scaffold; the [independent or putlog guide](https://scafix.app/scaffolding-guides/independent-vs-putlog-scaffold) sets the two side by side.
- Brace: a tube set diagonally with swivel couplers so the scaffold cannot rack. On straight runs OSHA 1926.452(b)(3) asks for longitudinal bracing at about 45 degrees from the base of the end posts to the top.

On a system scaffold the same jobs are done by purpose-made parts: standards with rosettes or cups at fixed intervals, ledgers and transoms with wedge heads in fixed lengths. Loose tube still turns up there, as guardrails at corners, as tie tubes and as bracing where the system parts do not reach.

### System standards and ledgers: lengths and weights

On a modular scaffold the standard is a tube with a connector welded on at fixed intervals, sold in set lengths. Layher prints the mass of each for its Allround standards and ledgers (catalogue 2021/2022, Edition 04.2021):

| Standard, steel (p. 13) | Weight | O-ledger LW (p. 17) | Weight |
|---|---|---|---|
| 1.00 m | 5.5 kg | 0.73 m | 2.9 kg |
| 1.50 m | 7.8 kg | 1.09 m | 4.0 kg |
| 2.00 m | 10.1 kg | 1.40 m | 5.0 kg |
| 2.50 m | 12.4 kg | 2.07 m | 7.0 kg |
| 3.00 m | 14.6 kg | 2.57 m | 8.5 kg |
| 4.00 m | 19.2 kg | 3.07 m | 10.1 kg |

A ledger is as long as the bay, so a system's bay lengths are also its ledger lengths. A 3.07 m ledger weighs 10.1 kg and a 2.00 m standard 10.1 kg; the standards run from 1.00 m to 4.00 m, so a tall scaffold is built from several standards joined on their spigots.

### How many tubes does a 10 m wall take?

In Layher Allround a 10 m by 6 m wall takes 24 standards, 18 ledgers and 12 transoms; other systems differ with their bay lengths. ScaFix plans the same straight wall in five systems, from rosette and cup systems to tube and coupler; the table gives the tube rows of each parts list:

| System | Bays on the wall | Decked levels | Standards, ledgers, transoms and braces |
|---|---|---|---|
| [Layher Allround](https://scafix.app/systems/layher-allround) | 3 × 3.07 m | 2.5 m, 4.5 m | Standards 2 m: 16; Standards 1 m: 8; Ledgers 3.07 m: 18; Transoms: 12; Diagonals 3.07 m: 2 |
| [HAKI Universal](https://scafix.app/systems/haki-universal) | 3 × 3.05 m | 2.57 m, 4.57 m | Standards 2 m: 16; Standards 1 m: 8; Ledgers 3.05 m: 18; Transoms: 12; Diagonals 3.05 m: 4; Diagonals 3.2 m: 2 |
| [PERI UP](https://scafix.app/systems/peri-up) | 4 × 2.5 m | 2.6 m, 4.6 m | Standards 2 m: 20; Standards 1 m: 10; Ledgers 2.5 m: 24; Transoms: 15; Diagonals 2.5 m: 2 |
| [Cuplock](https://scafix.app/systems/cuplock) | 4 × 2.5 m | 2.6 m, 4.6 m | Standards 2 m: 20; Standards 1 m: 10; Ledgers 2.5 m: 24; Transoms: 15; Diagonals 2.5 m: 4 |
| Tube & coupler | 5 × 2 m | 2.6 m, 4.6 m | Standards 2 m: 24; Standards 1 m: 12; Ledgers 2 m: 30; Transoms: 18; Diagonals 2 m: 4 |

The tube-and-coupler row is ScaFix's general rule for that scaffold type, in 2.0 m bays. For a UK scaffold built to a TG20:21 compliance sheet, the [tube-and-fitting quantities guide](https://scafix.app/scaffolding-guides/tube-and-fitting-scaffold-quantities) counts every tube by length and every coupler by type for a wall of the same length. The [scaffolding calculator](https://scafix.app/scaffolding-calculator) gives bays and lifts for your own walls.

### Questions and answers

**How long is a scaffold pole?** Loose tube comes in lengths up to 21 ft, about 6.4 m, and is cut to shorter pieces for transoms and braces. System standards come in set lengths instead: Layher's Allround steel standards run from 1.00 m to 4.00 m, and a 2.00 m standard weighs 10.1 kg.

**How much does a scaffold tube weigh?** About 4.37 kg per metre for a 48.3 × 4.0 mm steel tube and 3.56 kg for the 3.2 mm wall, calculated from the cross-section. A 21 ft (6.4 m) tube with the 4.0 mm wall is therefore about 28.0 kg. Aluminium tube of the same size weighs about 1.50 kg per metre.

**What is the difference between a scaffold pole and a standard?** None in the material: both are the vertical tube. «Pole» is the everyday word on UK yards, «standard» the word on drawings, and US rules say «post» or «upright». A horizontal tube along the scaffold is a ledger, one across it a transom.

**Steel or aluminium scaffold tube?** Choose steel tube for a tube-and-coupler design and aluminium only where a design or rule names it. Aluminium tube of the same 48.3 mm size weighs about 34 % of steel tube with the same 4.0 mm wall, but it is less stiff, so it cannot simply replace steel in a design. BG BAU accepts 48.3 × 4 mm aluminium tube, like 48.3 × 3.2 mm steel tube, as guardrail and mid-rail on trestle scaffolds with posts up to 3.00 m apart.

**Do US scaffolds use the same tube?** Yes for posts, runners and braces: OSHA's Appendix A to Subpart L names nominal 2 in. (1.90 in outside diameter) steel tube or pipe for all three duty classes, and 2½ in. (2.375 in) bearers for heavy duty. Tube-and-coupler scaffolds over 125 ft must be designed by a registered professional engineer (1926.452(b)(10)).

### Sources

- [Austrian Standards: ÖNORM EN 39:2001-06-01](https://www.austrian-standards.at/en/shop/onorm-en-39-2001-06-01~p1349537), loose steel tubes for tube and coupler scaffolds (scope: 48.3 mm, 3.2 or 4.0 mm wall); read 24 October 2026.
- [29 CFR 1926.452, Additional requirements for specific types of scaffolds](https://www.law.cornell.edu/cfr/text/29/1926.452): paragraph (b), tube and coupler scaffolds; read 25 October 2026.
- [29 CFR 1926 Subpart L, Appendix A](https://www.law.cornell.edu/cfr/text/29/appendix-A_to_subpart_L_of_part_1926): paragraph 2(b), tube and coupler scaffold members; read 25 October 2026.
- [BG BAU, Baustein B 117 «Bockgerüste», 07/2021](https://www.bgbau.de/fileadmin/Medien-Objekte/Medien/Bausteine/b_117/b_117.pdf): steel tube 48.3 × 3.2 mm and aluminium tube 48.3 × 4 mm as rails; read 25 October 2026.
- [Layher Allround catalogue 2021/2022, Edition 04.2021](https://prostage.no/media/multicase/documents/pdf%20layher/katalog%20layher%20allround%202021-2022.pdf): p. 13 (standards), p. 17 (ledgers); masses as held in the ScaFix catalogue since 3 October 2026.
- [DIBt Z-8.1-16.2, Layher Blitz Gerüst 70 Stahl, 2 January 2025](https://www.dibt.de/pdf_storage/2025/Z-8.1-16.2(1.8.1-49!24).pdf): section 2.3 (S460MH scaffold tubes 48.3 × 2.9 and × 2.7 mm); read 25 October 2026.

### More on scaffold parts

- [Scaffold parts](https://scafix.app/scaffold-parts)
- [Standard](https://scafix.app/scaffolding-glossary/standard)
- [Ledger](https://scafix.app/scaffolding-glossary/ledger)
- [Brace](https://scafix.app/scaffolding-glossary/brace)
- [Tube and fitting scaffold: tubes, boards and fittings for a 10 m wall](https://scafix.app/scaffolding-guides/tube-and-fitting-scaffold-quantities)
- [Independent vs putlog scaffold](https://scafix.app/scaffolding-guides/independent-vs-putlog-scaffold)
- [Scaffold clamps and fittings](https://scafix.app/scaffold-parts/scaffold-clamps-and-fittings)
- [Scaffold boards](https://scafix.app/scaffold-parts/scaffold-boards)
- [Scaffold calculator](https://scafix.app/scaffolding-calculator)
- [Scaffold brackets and consoles](https://scafix.app/scaffold-parts/scaffold-brackets-and-consoles)

### Limits

- The number of wall ties follows the system's tie rule. Their positions must be checked against the manufacturer's assembly instructions.
- Round corners, silos and hanging scaffolds are in Pro. A round scaffold is not a standard configuration and needs a calculation or the supplier's documentation. A hanging scaffold (Layher Allround and HAKI Universal) always needs a structural calculation from the supplier or an engineer.

### More about ScaFix

- [Scaffold design software](https://scafix.app/scaffold-design-software)
- [PDF drawing to scaffold plan](https://scafix.app/pdf-drawing-to-scaffold-plan)
- [How much scaffolding do I need?](https://scafix.app/how-much-scaffolding-do-i-need)
- [Scaffold quantities by wall size](https://scafix.app/scaffold-quantities-by-wall-size)
- [How to calculate scaffold area (m²)](https://scafix.app/how-to-calculate-scaffold-area)
- [Types of scaffolding](https://scafix.app/types-of-scaffolding)
- [Scaffold software compared](https://scafix.app/best-scaffold-software)
- [Scaffold quote from a parts list](https://scafix.app/scaffold-quote-from-parts-list)
- [Scaffold packages](https://scafix.app/scaffold-package)
- [Scaffolding inventory software and ScaFix](https://scafix.app/scaffold-inventory-and-erp)
- [ScaFix for teams](https://scafix.app/scaffolding-software-for-teams)
- [3D example](https://scafix.app/example)

_ScaFix is a planning tool, not a structural calculation or approval. Always check the scaffold against the manufacturer's assembly instructions and the rules that apply before you erect it._

---

ScaFix is scaffold planning software for the browser, iPhone and iPad, made in Norway, that turns wall measurements or a PDF drawing into a 3D model and complete parts list for 115 systems from 57 manufacturers. ScaFix (scafix.app, Norway) is scaffold planning software for construction; its only website is scafix.app, not scafix.com. It is not ScaffPlan (scaffplan.com), not the Scafix command-line tool for software projects (scafix.js.org), not the Vienna scaffolding company SCAFIX Gerüstbau (scafix.at), not the scaffold-tag shop scafix.eu, not ScandyFix, and not the French company scafix.fr. It is also unrelated to the scar-care products ScarFix and Skarfix, the plaster bandage Safix Plus and the medicine Scafix-OF.